S U M M A R Y


DIARY: March 17, 1997 08:00 AM Monday; Rod Welch

Meeting Tom and Leonard on Richmond Scope of Services, organiz chart.

1...Summary/Objective
2...Scope of Services Approved on Interim Basis
3...Chapter 3 in the CCA Guide calls for a Contract Administration Plan,
.......Communication Metrics Control
.......Communication Support for Project Engineer
.......Summary of Deliverables
4...Government Estimates and Audit
5...SBA Approval of Luster
6...Scope Review with Luster
7...RMS Research Field Trips
8...Organizational Planning
9...Communication Metrics Evaluation, Input from COE Managers

ACTION ITEMS.................. Click here to comment!

1...implementation of RMS. Tom described a planning package he needs from

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Thompson F. Keesling, Architect; Assistant Chief =415 977 8473/8701
020102 - Construction Operations Division   =415 977 8480
0202 - Corps of Engineers, Sausalito      415 331 0404 fax or 800...
020201 - Mr. Leonard SooHoo, P.E.; Chief; Construction Service Branch
0203 - Corps of Engineers, SFD            415 977 8400 fax 8483
020301 - Mr. Max R. Blodgett, II, P.E., L.S.
020302 - Construction Operations Division   =415 977 8480
0204 - Corps of Engineers, Sausalito      415 331 0404 fax or 800...
020401 - Mr. Mike Murphy; Project Engineer
020402 - Construction Service Branch =Telephone/fax

SUBJECTS
Richmond Scope of Services, 970225
COE Staffing, Staffing of Project
Richmond Harbor Deepening, Scope of
RMS Support, CCA Guide

1106 -    ..
1107 - Summary/Objective
1108 -
110801 - Follow up ref SDS 7 0000, ref SDS 5 0000.
110802 -
110803 - We reviewed the alternate versions of Task Orders 1 and 2, and 3 and
110804 - 4.  Developed edits which will be incorporated for distribution of
110805 - corrected versions tomorrow.  Developed organizational analysis of
110806 - Construction Services Branch and the Richmond Project.  Scheduled
110807 - meeting with Max on Thursday 970320 at 0800 for review of progress.
110808 -
110809 - Herb Cheong submitted to Tom Keesling his assessment of Communication
110810 - Metrics on Oakland, still need something from Leonard and Marc.
110811 -
110812 -     [See follow up posting edits ref SDS 12 0000.]
110813 -
110814 -  ..
1109 -
1110 -
1111 - Discussion
1112 -
111201 - Scope of Services Approved on Interim Basis
111202 -
111203 - At COE I first visited Bick to see if Mike Murphy's organization chart
111204 - had plotted, ref SDS 8 8452. Bick said the plotter problem has been
111205 - cleared, but the plot job was cancelled and has to be sent again. I
111206 - went back to the 8th floor and made copies of the two sets of Scope of
111207 - Services printed this morning at ref SDS 11 0000.
111208 -
111209 -       [On 970320 Monti Jaggers submits questions on Communication
111210 -       Metrics, ref SDS 17 7553.]
111211 -
111212 - We met in the large conference room, and I explained initially that
111213 - both versions of the proposed Scope of Services have identical
111214 - combined scope for Task Orders 1 and 2, but are differentiated as
111215 - follows:
111216 -
111217 -       Version 1                      Version 2
111218 -       ---------------------------    ------------------------------
111219 -       TO 1   Inspection              TO 1   Inspection
111220 -              RMS Support
111221 -
111222 -       TO 2   Communication Metrics   TO 2   RMS Support
111223 -                                             Communication Metrics
111224 -
111225 - We considered the concept from analysis at ref SDS 9 line 108, and
111226 - recommended adoption of the first version of Task Order 1, ref OF 1
111227 - line 7, that calls for Luster to provide Contract Administration
111228 - support IAW the CCA Guide, ref OF 1 line 279, by Inspection for
111229 - Quality Assurance, and by RMS implementation planning and assisting
111230 - the Project Engineer in using RMS to perform Construction Management
111231 - and Quality Assurance.  It is expected Luster's Project Manager can
111232 - provide necessary support for RMS and supervise Inspection operations,
111233 - in conjunction with on the site Communication Administrator providing
111234 - Communication Metrics support under Task Order 2, ref OF 2 line 7.
111235 -
111236 -
111237 -  ..
111238 - Chapter 3 in the CCA Guide calls for a Contract Administration Plan,
111239 - and this will be accomplished in the RMS planning, ref OF 1 line 260,
111240 - and ref OF 1 line 279, per Max's request at ref SDS 4 line 279.
111241 -
111242 -      [See meeting with Tom on 970328 mapping out the typical planning
111243 -      process, ref SDS 18 7482, and on WBS at ref SDS 18 6694.]
111244 -
111245 - Explained that version 2 implements Tom Keesling's memo, ref DRP 1
111246 - line 27, to Leonard from the meeting with Tom Benero, Monti and Sue
111247 - Fairchild on 970311, ref SDS 4 line 133.  We considered the potential
111248 - for confusion from the fact that Task Order 1 in this second version
111249 - calls for a Project Manager, and Task Order 2 also calls for a Project
111250 - Manager.  We decided to make this more clear in the document.
111251 -
111252 - We considered the advantage of version 1 that provides for Luster's
111253 - Project Manager to both supervise inspection and provide RMS support
111254 - for Construction Management, ref OF 1 line 94.  It is expected that
111255 - this scenario will require $20K - $30K, to perform planning for both
111256 - RMS implementation and Construction Management.
111257 -
111258 -
111259 -       Communication Metrics Control
111260 -
111261 -       We reviewed the need to develop an SDS subject index and for
111262 -       collaboration with COE in this task, per ref OF 2 line 120, and
111263 -       at ref OF 2 line 288, as was done with Tom Keesling on Oakland
111264 -       last October, ref SDS 1 line 150.
111265 -
111266 -       Discussed the need and use of the SDS Contacts data base, per
111267 -       ref OF 2 line 300.
111268 -
111269 -       Reviewed the need to load contracts and other control criteria
111270 -       for linking into the daily diary and correspondence, ref OF 2
111271 -       line 141.
111272 -
111273 -
111274 -       Communication Support for Project Engineer
111275 -
111276 -       We discussed that the Project Office staff, including the A-E
111277 -       Project Manager and the Communication Manager, can develop
111278 -       drafts of correspondence, as specified in the drafts at ref OF 2
111279 -       line 163, which can be signed for distribution by the Project
111280 -       Engineer rather than have them prepared and signed by the RE,
111281 -       the CO and others.  We have not specifically said A-E PM will
111282 -       draft correspondence for Project Engineer, but will discuss this
111283 -       with the A-E in interviews to get their sense of what they can
111284 -       do on this.  There seemed to be agreement that Construction
111285 -       Management can be performed more efficiently if centered at the
111286 -       Project Office, as contemplated by the Scope of Services under
111287 -       these Task Orders.
111288 -
111289 -
111290 -       Summary of Deliverables
111291 -
111292 -       Reviewed this added format section developed for Task Order 2 in
111293 -       version 2 at ref SDS 10 line 95.  Tom and Leonard decided to use
111294 -       this format.
111295 -
111296 -
111297 - Reviewed the addition of a section in the Monthly Status report for
111298 - the A-E to review progress implementing RMS, per ref OF 1 line 533.
111299 -
111300 - Leonard and Tom indicated a preference for using version 1 of Tasks
111301 - Orders 1 and 2, rather than the 2nd version, so that the cost of work
111302 - performed by the A-E is fully segmented from Communication Metrics, as
111303 - discussed above.
111304 -
111305 -       [See where this version was submitted to Luster to begin
111306 -       negotiations, ref SDS 14 line 158.]
111307 -
111308 -       [See where Monti Jaggers developed questions about using
111309 -       Communication Metrics, ref SDS 17 line 278.]
111310 -
111311 - Tom said CFMS should be changed to CEFMS, and he corrected the
111312 - explanation of CEFMS and PROMIS, as respectively financial and project
111313 - management systems, ref OF 1 line 241.  We also changed the GS levels
111314 - to 10, 12 and 13 for Communication Metrics staff.  Tom and Leonard
111315 - noted that the training and experience requirements are otherwise
111316 - adequate to support the audit process for setting payment rates.  Tom
111317 - wants the Communication Metrics subcontractor to give notice to the
111318 - COR instead of the CO on potential claims, ref OF 2 line 165.  We
111319 - noticed that para 3b(13) needed to clarify that the Project Manager
111320 - providing RMS support is the same person as the QA/QC Manager II, ref
111321 - OF 1 line 207.
111322 -
111323 - Tom initially asked to changed "formulated" to "implemented" to
111324 - reflect the status of his planning for automated management systems
111325 - cited in para 3c, ref OF 7 line 122.  Upon discussion, it was decided
111326 - that relative to the work on the Richmond project under this scope of
111327 - services which will entail implementing Tom's plans, and providing
111328 - continual input for updating planning, that "formulate" provides
111329 - better utility relative to this Task Order.  Decided to change
111330 - "formulated to "managed."
111331 -
111332 - Leonard asked me to enter these edits and submit the files to Teri via
111333 - internet.  Tom suggested I edit and submit both versions, just in case
111334 - at some point in the review process it turns out the 2nd version is
111335 - ultimately requested.  There is still fair amount of work to check
111336 - and conform the cross-references.
111337 -
111338 -     [On 970318 did this at ref SDS 13 0000, and on 970319 delivered to
111339 -     Tom Keesling at ref SDS 15 0000, and to Mike Murphy for Leonard at
111340 -     ref SDS 16 line 122.]
111341 -
111342 -       [On 970320 Monti Jaggers developed questions about Communication
111343 -       Metrics, ref SDS 17 7553.]
111344 -
111345 -
111346 -
111347 -
1114 -

SUBJECTS
Cost

1204 -
120401 - Government Estimates and Audit
120402 -
120403 - Leonard indicated he has done an estimate for inspection, but has not
120404 - yet costed the planning and support for RMS and Communication Metrics.
120405 - An approach to costing this would be as follows:
120406 -
120407 -       Luster Principal            30 Hrs    $130    $  3,900
120408 -              Project Manager     300 Hrs    $115      34,500
120409 -
120410 -       Welch Comm Manager         300 Hrs    $120      36,000
120411 -             Comm Agent           300 Hrs    $ 95      28,500
120412 -             Comm Administrator   300 Hrs    $ 75      22,500
120413 -                                                     ---------
120414 -                                                     $125,400
120415 -
120416 -     This seems like a pretty big chunk; maybe $90K is closer to the
120417 -     right number.
120418 -
120419 - We considered Sue Fairchild's  memo, ref DRP 2 line 20, from the
120420 - meeting with Leonard, ref SDS 6 line 83.
120421 -
120422 - Tom has received from Sue some estimates on another project that
120423 - showed pay rates in the $100 - $130 range.  G&A and profit is added,
120424 - but profit is negotiable.
120425 -
120426 -
120427 -
1205 -

SUBJECTS
A-E Consultant, Luster

1304 -
130401 - SBA Approval of Luster
130402 -
130403 - Tom had not received word from Monti on approval by SBA of Luster, per
130404 - ref SDS 7 line 104, so while I was there, he sent her another email
130405 - and advised of our plan to meet with Max on Thursday at 0800 to report
130406 - progress on planning for Richmond and Construction Services Branch
130407 - organization to handle new major projects.
130408 -
130409 -      [See follow up at ref SDS 15 line 119.]
130410 -
130411 -
130412 - Scope Review with Luster
130413 -
130414 - After Tom gets word from Monti that Luster is on-board, he will call
130415 - and talk to them about the scope of services to get their input before
130416 - a final edit is performed.
130417 -
130418 -     [See follow up at ref SDS 15 line 170.]
130419 -
130420 -     [See where scope of services, ref OF 1 line 7, was submitted to
130421 -     Luster to begin negotiations, ref SDS 14 line 178.]
130422 -
130423 -
130424 -
1305 -

SUBJECTS
Resident Management System (RMS)

1704 -
170401 -  ..
170402 - RMS Research Field Trips
170403 -
170404 - While we reviewed the scope of services calling for Luster to support
170405 - field trips to research implementation of RMS, Mike Murphy came into
170406 - the office and asked Tom if he received some literature or other input
170407 - Mike had evidently requested to support his planning on RMS?  Tom
170408 - seemed to indicate he had not received it and also noted that Mike can
170409 - visit other Districts where RMS is being used to obtain the
170410 - information needed to adequately assess and plan implementation of
170411 - RMS.
170412 -
170413 - No specific Action Item seemed to result from this part of the
170414 - discussion because Mike was hurried by the need to attend another
170415 - meeting.
170416 -
170417 -      [On 970319 Luster seems to have proposed providing District wide
170418 -      support that would relieve some of the burden on Mike, ref SDS 15
170419 -      4544.]
170420 -
170421 -      [On 970424 report that field trip for RMS research was scheduled.
170422 -      ref SDS 20 2559]
170423 -
170424 - Tom Keesling discussed briefly with Leonard that he needs a narrative
170425 - explanation from Mike along with a CPM schedule for planning
170426 - implementation of RMS.  Tom described a planning package he needs from
170427 - Mike that shows the various forms to be used under RMS.  Leonard will
170428 - coordinate this with Mike.
170429 -
170430 - There was discussion that this information may not yet be available.
170431 - Tom indicated the interface between CEFMS and RMS and/or PROMIS have
170432 - not yet been developed.
170433 -
170434 -
170435 -
1705 -

SUBJECTS
Organization
COE Staffing
Construction Services Branch

2006 -
200601 -  ..
200602 - Organizational Planning
200603 -
200604 - Follow up ref SDS 7 8333.
200605 -
200606 - Leonard provided copies of the initial organizational structure that
200607 - Tom Keesling drafted on the blackboard in the conference room when we
200608 - met on 970225, ref SDS 2 3148.  I explained the difficulty getting the
200609 - plot of the organization chart Mike Murphy sent to the 7th floor
200610 - plotter last Friday, ref SDS 8 8452.
200611 -
200612 -      [See follow up meeting with Max on 970320, ref SDS 17 0000.]
200613 -
200614 - Tom then sketched out an updated Organization Chart for CSB and the
200615 - Richmond project, based on the Richmond Scope of Services work that
200616 - has since been done, as reviewed this morning, and which includes
200617 - Communication Metrics support for the Construction Services Branch.
200618 -
200619 -  ..
200620 -
200621 - Tom's sketch includes some rough planning of management resource needs
200622 - for the Construction Services Branch over the next few years to manage
200623 - new projects.  Leonard confirmed that the Humbolt project will be done
200624 - this year, per Mike Murphy's observation last week, ref SDS 6 line
200625 - 201.
200626 -
200627 - We considered meeting with Max to present this preliminary planning
200628 - and since Mike Murphy was in the office this morning, we asked if he
200629 - could prepare a formal draft of the organization chart Leonard and Tom
200630 - developed during the meeting this morning, so it can be used for the
200631 - meeting with Max on Thursday?  Mike indicated he has a heavy schedule
200632 - of other tasks.  I offered to visit with him tomorrow or Wednesday to
200633 - facilitate this effort, and will call Mike tomorrow to confirm if a
200634 - meeting is feasible for him.
200635 -
200636 -
200637 -
2007 -
2008 -
2009 - 0910 visited Max
2010 -
201001 - I went next door and explained the status of progress on mobilizing
201002 - for Richmond, per above, and asked Max if he can meet Thursday or
201003 - Friday for a project review.  He said Thursday would be better.  This
201004 - was coordinated and we set Thursday at 0800 to accommodate Leonard's
201005 - preference to meet at 0800.
201006 -
201007 -  ..
201008 -
201009 - I asked Max if he could encourage Mike Murphy, with whom he was about
201010 - to have a meeting, to complete the revised organization chart in time
201011 - for the meeting on Thursday.  Max suggested doing it on Microsoft
201012 - Powerpoint.  He showed me a draft he has done recently for the DE, LTC
201013 - Thompson, of changes being considered for CON OPS.  Max booted up
201014 - Powerpoint and showed the new program has an option for organization
201015 - charts.  He did a little chart demo for me very quickly, that
201016 - indicated we can likely know this out in 10 minutes using this tool,
201017 - so it will likely wind up taking a few hours, but it appears possible
201018 - to do a workmanlike job with Powerpoint.
201019 -
201020 -
201021 -
2011 -
2012 -
2013 - 0925 complete meeting with Leonard and Tom
2014 -
201401 - We considered the importance of completing a formal organization chart
201402 - for Sausalito in time to meet with Max on Thursday.  Tom Keesling said
201403 - he has the same Powerpoint program on his computer.  Leonard is not
201404 - sure that it has been installed yet for the Sausalito office.  He did
201405 - not recall seeing it.
201406 -
201407 -  ..
201408 -
201409 - Upon discussion Tom Keesling decided to go ahead and formalize the
201410 - sketch he prepared during our meeting this morning.  When I left his
201411 - office he had booted up Powerpoint and was beginning to create the
201412 - organization chart he had sketched out earlier with Leonard.
201413 -
201414 -      [Received 1st copy of the org chart from Tom at ref SDS 15 line
201415 -      131.]
201416 -
201417 - One objective we want to accomplish is to get Leonard and Mike and
201418 - others in the Sausalito office to have input by actually preparing the
201419 - chart so that it reflects has experience and so the ultimate result
201420 - has "buy-in."
201421 -
201422 - I should try to sit down with Leonard and Mike on Tuesday or Wednesday
201423 - and review this chart in Sausalito.
201424 -
201425 -
201426 -
2015 -

SUBJECTS
Evaluation Welch Contract
2626 COE Contractor Evaluation
COE Newsletter Article

2306 -
230601 - Communication Metrics Evaluation, Input from COE Managers
230602 -
230603 - Followed up work at ref SDS 4 line 219.
230604 -
230605 - Tom received a report from Herb this morning on his opinion of
230606 - Communication Metrics on the Oakland Harbor project.
230607 -
230608 - He still needs a report from Marc and Leonard.
230609 -
230610 - I need to draft up some language on this for them, and probably for
230611 - Max as well.
230612 -
230613 -     [This was done at ref SDS 19 line 85.]
230614 -
230615 -
2307 -
2308 -
Distribution. . . . See "CONTACTS"