S U M M A R Y


DIARY: March 28, 1997 09:30 AM Friday; Rod Welch

Meeting with Tom on Richmond/CSB organization and project launch.

1...Summary/Objective
2...Tom Assigned PM for Richmond
3...Project Management Implemetation Procedures Project
4...Richmond Launch Schedule Prototype
.................."Supervision and Administration."
5...Supervision and Administration is the work by Con Ops to manage the
6...Tom indicated the cost for Supervision and Administration has averaged
7...Lessons Learned
.......Construction Management Plan (CMP)
8...WBS Needs to Integrate with COE Accounts
9...No Progress Reported on Luster and COE Contract
10...CSB to Submit Organization and RMS Planning Next Week
11...RMS Flow Chart Not Available in Sacramento
12...Schedule, Management Planning Reviews
13...CSB Needs Organizational Development Support


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Thompson F. Keesling, Architect; Assistant Chief =415 977 8473/8701
020102 - Construction Operations Division   =415 977 8480
0202 - Corps of Engineers, SFD            415 977 8400 fax 8483
020201 - Mr. Max R. Blodgett, II, P.E., L.S.
020202 - Construction Operations Division   =415 977 8480

SUBJECTS
Keesling PM for Richmond, Automated Management in District, Keesling
Project Management Review
Automated Management, Keesling's Assignment
Richmond Project Launch, Construction Launch Planning
Objectives/Requirements, Schedule Launch Project
SDS Captures History to Guide Future
Project Manager, COE, Keesling
Supervision & Admin Cost

2210 -    ..
2211 - Summary/Objective
2212 -
221201 - Follow up ref SDS 15 0000, ref SDS 13 0000.
221202 -
221203 - Reviewed and edited launch schedule for Richmond project.  DE assigned
221204 - Tom this morning to be the PM for Richmond and to develop procedures
221205 - and process for PM in the District.  We discussed project management
221206 - process, including WBS, focusing on construction operations to launch
221207 - a new project, using Richmond as a prototype. Discussed briefly with
221208 - Max the need to support Leonard in meeting schedule targets to prepare
221209 - for start of construction on 970601.
221210 -
221211 -
221212 -
221213 -
221214 -
2213 -
2214 -
2215 - Progress
2216 -
221601 - Tom Assigned PM for Richmond
221602 -
221603 - DE asked Tom to be the Project Manager for Richmond and for another
221604 - project, plus take over management of some kind of training mission,
221605 - seems like it is related to technicial managers.
221606 -
221607 -      [On 970428 someone else is doing this, ref SDS 32 5P4N
221608 -
221609 -
221610 -  ..
221611 - Project Management Implemetation Procedures Project
221612 -
221613 - DE seems to have asked Tom to develop a Project Management process in
221614 - the District to implement COE PM regulations and procedures.  This is
221615 - a research effort that is incorporated into the Richmond spec for
221616 - Luster to support under Task Order 1, ref OF 1 line 260.
221617 -
221618 -      [On 970417 DE raised this in meeting with Luster, ref SDS 27 4588
221619 -
221620 -      [On 970427 creating this position for CSB and Richmond
221621 -      organization and management planning, ref SDS 30 KQ3L
221622 -
221623 -
221624 -
221625 -  ..
221626 - Richmond Launch Schedule Prototype
221627 -
221628 - We reviewed the schedule for launching the Richmond project, ref OF 6
221629 - line 30.  Tom generally agreed with the process.  There were no
221630 - significant changes in the logic precedence or activity durations.  We
221631 - considered extending the task for awarding the AE contract to reflect
221632 - that a lot of work can be accomplished by the AE during that period.
221633 -
221634 - Considered providing detail for the activity "Objectives/Requirements"
221635 - showing review of plans and specs, and an Engineering report drawing
221636 - attention to Con Ops any significant planning and scheduling
221637 - considerations in the plans and specs, e.g., GC to provide project
221638 - office for COE.  GC to provide CPM schedule x days following NTP.
221639 -
221640 - Tom suggests citing PMP, PCA, CCA and RMS as inputs to be considered
221641 - in developig project requirements.  Each of these take time for review
221642 - to develop a comprehensive Construction Management Plan.
221643 -
221644 - Tom will ask Leonard to submit comments and/or questions the first
221645 - part of next week.
221646 -
221647 -      [See follow up with Leonard at ref SDS 24 line 149.]
221648 -
221649 - Tom noted that this schedule scenario for launching Richmond could be
221650 - promulgated as a generic process for launching all construction
221651 - projects in the District.
221652 -
221653 - We discussed the correlation with controlling regulations.  The aim is
221654 - to use descriptions of activities that reflect current regulations and
221655 - a consistent structure vis a vis project management, construction
221656 - management, Construction Contract Administration, per CCA Guide, and a
221657 - term that is new for me that Tom called
221658 -
221659 -                  "Supervision and Administration."
221660 -
221661 - We spent considerable time trying various alternate descriptions to
221662 - reflect the work at succeeding planning phases and for different
221663 - levels of COE management.  Tom did some work on this a number of years
221664 - ago that got set aside due to the other assignments, so this is an
221665 - opportunity to think this through, including the current need to plan
221666 - the start of construction beginning with completion of the plans and
221667 - specs.
221668 -
221669 -      [Added a task for Project Team to develop a deliverable called a
221670 -      Supervision and Administration Plan that would be the field
221671 -      implementation of the Construction Management Plan, per Tom's
221672 -      explanation this morning, ref SDS 21 line 105.]
221673 -
221674 - He retrieved the COE regulation on Project Management that is dated
221675 - 1992.  It does not seem to actually mention Construction Management,
221676 - but the introduction the document indicates a general process of
221677 - developing sponsor agreements, engineering management and then
221678 - construction management.
221679 -
221680 - Tom drew out a schematic of the process that covers "Recon"
221681 - Feasability, PDE, which I think is Planning, Design and Engineering,
221682 - then Construction and then O&M.  Recon is investigating project ideas
221683 - to see if feasability should be performed.
221684 -
221685 - Tom discussed having the AE provide a QC process for its work to
221686 - support QA by Project Engineer, similar to General Contractor who
221687 - provides Quality Control for its work.
221688 -
221689 -      [Added this at ref SDS 22 line 60.]
221690 -
221691 -  ..
221692 - Supervision and Administration is the work by Con Ops to manage the
221693 - contractor in performing the work at the site.  This entails use of
221694 - the Construction Contract Administration (CCA) Guide, which calls for
221695 - an implementation plan, per ref SDS 14 line 145.
221696 -
221697 -
221698 - Tom indicated the cost for Supervision and Administration has averaged
221699 - 6% - 8% of direct cost on prior projects.
221700 -
221701 -      [See follow up where budget reported on Richmond does not reflect
221702 -      these valuations, ref SDS 33 line 291.]
221703 -
221704 - The discussion indicated that the project launch schedule should
221705 - typically be prepared by the CSB, as reflected by putting Leonard's
221706 - name at the top of the Richmond schedule.  Another thought would be
221707 - that the CON OPS Construction Manager might be responsible for the
221708 - initial Construction Management Plan that provides liason between
221709 - Engineering Division and CSB.
221710 -
221711 -
221712 - Lessons Learned
221713 -
221714 - We wound up deciding to make a primary deliverable of the Construction
221715 - Launch Schedule a "Construction Management Plan" (CMP), since this is
221716 - the construction phase of the project. It sets roles, responsibilities
221717 - and procedures to implement the Project Management Plan (PMP) produced
221718 - and maintained earlier in the life cycle. Tom feels it should identify
221719 - relationships between CON OPS, PPMD, Contracting Division, the PCA and
221720 - good management practices based on lessons learned on prior projects,
221721 - which reflects Tom Benero's objective in the meeting on 971001,
221722 - ref SDS 1 line 162.
221723 -
221724 - He listed the following elements:
221725 -
221726 -       Construction Management Plan (CMP)
221727 -
221728 -       •  Organization
221729 -       •  Roles and Responsiblities
221730 -       •  Schedule
221731 -       •  Budget/Funding
221732 -       •  Change Order Control
221733 -       •  RMS
221734 -       •  Procure AE Services
221735 -       •  QA/QC by AE
221736 -       •  Contract Administration
221737 -
221738 -
221739 -   [See implementation at ref SDS 21 line 106.]
221740 -
221741 -
221742 -
221743 -
2218 -

SUBJECTS
WBS

2404 -
240401 -  ..
240402 - WBS Needs to Integrate with COE Accounts
240403 -
240404 - We did not consider WBS in the Richmond launch schedule in detail.
240405 - There were no specific changes or additinos, however I want to revise
240406 - the WBS to make it simpler, and apply the double letter structure.
240407 -
240408 -      [See follow up at ref SDS 20 line 98; final submittal at ref SDS
240409 -      23 line 173.]
240410 -
240411 - I asked if the District has a WBS for the project.  Tom seemed to
240412 - indicate there is a general WBS.  When we returned to his office from
240413 - the conference room after our meeting, he showed a large chart that
240414 - has been taped together and which is the District WBS.  Presumably
240415 - there is a component for project launch activities.
240416 -
240417 - We examined COE's WBS later in Tom's office.  It is a huge document
240418 - comprised of approximately 15 sheets taped together.  There is no
240419 - scope description with the elements.  There does not seem to be room
240420 - in the numbering sequence for adding work packages between existing
240421 - ones.  Tom said he asked about this matter and was told the WBS is
240422 - comprehensive.
240423 -
240424 -    [See follow up developing WBS for Richmond that recognizes these
240425 -    concerns, ref SDS 26 line 104.]
240426 -
240427 -
240428 -
240429 -
2405 -

SUBJECTS
Negotiations, Start to Start Work

2504 -
250401 - No Progress Reported on Luster and COE Contract
250402 -
250403 - Tom has not heard from Monti about setting a meeting with Luster. He
250404 - got the impression that DE is not yet fully acquainted with the
250405 - strengths of Luster.
250406 -
250407 -      [See call received from Ahmet, ref SDS 19 line 71.]
250408 -
250409 -
250410 -
2505 -

SUBJECTS
Richmond Scope of Services, 970225
COE Staffing
Staffing of Project
Management Plan

3407 -
340701 -  ..
340702 - CSB to Submit Organization and RMS Planning Next Week
340703 -
340704 - Followed up work at ref SDS 16 8456.
340705 -
340706 - Tom indicated he spoke to Leonard and they plan to meet toward the end
340707 - of next week to review the update on the information flow chart for
340708 - RMS from the results of the meeting last week with Max, ref SDS 16
340709 - line 187.  This reflects discussions with Leonard yesterday at ref SDS
340710 - 18 line 158.
340711 -
340712 - We did not have time this morning to review the updated CSB
340713 - organization chart that was discussed last week, ref SDS 16 line 187.
340714 -
340715 -      [See review meeting on 970404 where updated CSB organization
340716 -      chart not available, ref SDS 25 line 229; prepared on 970428 ref
340717 -      SDS 31 line 89.]
340718 -
340719 -
340720 -
340721 -  ..
340722 - RMS Flow Chart Not Available in Sacramento
340723 -
340724 - Follow up ref SDS 16 1752.
340725 -
340726 - Tom advised his contact in the Sacramento District called and said
340727 - they do not have a formal Information Flow chart for RMS use, per our
340728 - discussion last week, ref SDS 17 8488.
340729 -
340730 -
340731 -
340732 - Schedule, Management Planning Reviews
340733 -
340734 - Tom will get results of Leonard's review of the initial schedule
340735 - launch.
340736 -
340737 -      [On 970402 Tom is scheduling review meeting. ref SDS 24 7751.]
340738 -
340739 -
340740 - I spoke to Max for about 20 minutes while Tom was reviewing the notes
340741 - of the schedule that clarify scope of various activities.  He glanced
340742 - briefly through the project launch schedule for Richmond.  Max showed
340743 - a staffing "requisition" Leonard has submitted.  Max feels getting
340744 - adequate staff is crucial in order to meet the schedule objectives for
340745 - launching Richmond and the other projects CSB has coming up over the
340746 - next year.
340747 -
340748 -
340749 -
340750 - CSB Needs Organizational Development Support
340751 -
340752 - Max feels further work is needed on assisting Leonard with the staff
340753 - requisition process relative to work descriptions and organization
340754 - structure, which was to be reviewed in the meeting this morning, per
340755 - understandings last week, ref SDS 16 line 187.
340756 -
340757 -      [See meeting on 970404, ref SDS 25 line 216; submission of
340758 -      positions for PE and Inspectors on 970424, ref SDS 29 line 126;
340759 -      and submission of organizaiton charts for CSB and Richmond, ref
340760 -      SDS 31 line 90.]
340761 -
340762 -
340763 -
340764 -
340765 -
340766 -
340767 -
340768 -
340769 -
340770 -
340771 -
340772 -
3408 -
Distribution. . . . See "CONTACTS"