S U M M A R Y


DIARY: April 2, 1997 09:33 AM Wednesday; Rod Welch

Meeting with Tom on Richmond/CSB organization and project launch.

1...Summary/Objective
2...Tom Assigned PM for Richmond
3...Richmond Launch Schedule Prototype
4...WBS Needs to Integrate with COE Accounts
5...No Progress Reported on Luster and COE Contract


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Thompson F. Keesling, Architect; Assistant Chief =415 977 8473/8701
020102 - Construction Operations Division   =415 977 8480

SUBJECTS
Keesling PM for Richmond
Automated Management in District, Keesling
Project Management Review
Automated Management, Keesling's Assignment
Richmond Project Launch, 970328
Construction Launch Planning
Objectives/Requirements
Schedule Launch Project

1510 -    ..
1511 - Summary/Objective
1512 -
151201 - Follow up ref SDS 18 0000, ref SDS 16 0000.
151202 -
151203 - Submitted and reviewed preliminary schedule revision prepared this
151204 - morning. ref SDS 20 0000.
151205 -
151206 -
151207 -
1513 -
1514 -
1515 - Progress
1516 -
151601 - Tom Assigned PM for Richmond
151602 -
151603 - Followed up work at ref SDS 18 line 116.
151604 -
151605 - Tom has a meeting this afternoon with DDE about the terms of his
151606 - assignment to PPMD.  Apparently the new COE CG is approving
151607 - assignments like Tom's and as a result there may be more documentation
151608 - that may be needed, similar to the Welch contract extension on Oakland
151609 - reviewed on 970110. ref SDS 3 9922
151610 -
151611 - We considered the advantages of using Welch to support Tom's work on
151612 - CEFMS and on Richmond, rather than making the assignment through
151613 - Luster.  We considered Tom meeting with Tom Benero about how to
151614 - accomplish this support.  He feels the scope of services for Richmond
151615 - AE Task Order 2 could simply be advertised.  It would take 60 days,
151616 - but we have 60 days.
151617 -
151618 -
151619 -  ..
151620 - Richmond Launch Schedule Prototype
151621 -
151622 - Followed up work at ref SDS 18 line 115.
151623 -
151624 - Before seeing Tom, I made a copy of the schedule, ref OF 7 0000, and
151625 - put it on Max's desk for review.  While in the copy room, I visited
151626 - briefly with Chris Shields who was making a copy of something.
151627 -
151628 -      [See review with Max on 970403, ref SDS 21 7740]
151629 -
151630 -      [On 970919 report planning not implemented. ref SDS 26 1960]
151631 -
151632 - I asked Chris about the date when construction should start on
151633 - Richmond?  He indicated mid-July because there is a disposal site that
151634 - will not be ready until sometime in August.  I showed him the
151635 - construction launch schedule.  He said there should be an activity for
151636 - NTP following contract award, and said the Contractor will have 60
151637 - days from NTP to begin construction.  Could be there is a block of
151638 - time from date of contract award to NTP which covers submission of
151639 - bonds and insurance certificates, MBE stuff etc.
151640 -
151641 - When I discussed this with Tom he advised that the Contractor could
151642 - start ocean disposal earlier than the availability of the upland
151643 - disposal site in August.  This should be resolved with Chris, as part
151644 - of the review of plans and specs and engineering report.
151645 -
151646 -  ..
151647 -
151648 - Tom examined the schedule and feels it reflects our understandings
151649 - from the meeting last Friday, ref SDS 18 7482.
151650 -
151651 - Tom has not received any comments or changes from Leonard, per our
151652 - discussion last Friday, ref SDS 18 8493.  I called Leonard later and
151653 - he said he does not have any changes, but has not had a chance to
151654 - review it closely.
151655 -
151656 - Tom will try to set up a review meeting with Max, Leonard and Mike
151657 - for Friday morning.
151658 -
151659 -    [On 970404 planning team review meeting. ref SDS 22 0000]
151660 -
151661 -
151662 -
151663 -
1517 -

SUBJECTS
WBS

1604 -
160401 -  ..
160402 - WBS Needs to Integrate with COE Accounts
160403 -
160404 - Followed up work at ref SDS 18 line 267.
160405 -
160406 - I showed Tom the new WBS for responsibilities, ref OF 7 line 10.
160407 -
160408 - He feels it will work.
160409 -
160410 -     [See further improvements on 970406, ref SDS 23 line 56.]
160411 -
160412 -     [See follow up review wtih Tom on 970409 ref SDS 24 line 97.]
160413 -
160414 -     [Later used this as part of Communication Metrics report, ref SDS
160415 -     25 line 155.]
160416 -
160417 -
160418 -
1605 -

SUBJECTS
Negotiations, Start to Start Work
Staffing Acquire
Scope

1906 -
190601 - No Progress Reported on Luster and COE Contract
190602 -
190603 - Followed up work at ref SDS 18 line 209.
190604 -
190605 - Advised of call received from Ahmet, ref SDS 19 line 71.  Tom showed a
190606 - letter dated 970326 COE received from Luster that provides job
190607 - descriptions for a wide range job catagories.  They list a lot things
190608 - that are included in the Richmond scope of services, but that may
190609 - reflect the generic nature of their contract.  One problem is that
190610 - they do not list any catagories that specifically address the
190611 - qualifications in Task Order 1 and 2.
190612 -
190613 - Tom advised that Sue Fairchild said COE should receive tomorrow from
190614 - Luster the report requested on any questions they have about the
190615 - Communication Metrics scope.
190616 -
190617 -
190618 -
190619 -
1907 -
Distribution. . . . See "CONTACTS"