DIARY: October 1, 1998 09:00 AM Thursday; Rod Welch

Meeting with Structural consultants on Moscone III.

1...Summary/Objective
2...Final Geo Technical Report Issued
3...CD Drawings Distrubution to SDE
4...Drawings on Existing Buildings to Be Provided to SDE
5...Increase Framing Clearance for Ductwork at B Line
6...Floor Framing Bracing Needs Coordination with Mechanical Ducts
7...Elevators Kwan Henmi Focusing on 50% Package
8...Elevator Cores 1 - 4
9...Elevator Cores 5 & 6 Complicated, Need Attention
10...Elevator Pits for 5 and 6 to Be Suspended Concrete
11...Elevator Shaft, Machine Room Framing Using Structural Input
12...Backgrounds for 50% CD Target Date to Consultants 981019
13...Stair Parameters Needed for Structural Design
14...WMA Needs Structural Solution for Op Wall Shaft/Stair on Minna St.
15...Ceiling Hook Layout Provided to SDE
16...Floor Utility Boxes Need Study to Verify Location, Scope
17...Alternate Designs Considered to Fireproof Floor Boxes
18...Soundproof 1st Floor Above Chillers in Basement, Design Pending
19...Entry Plaza on Howard Street Framing
20...Basement
21...Basement Electrical Room Col Layout Coordinate with Equipment
22...Basement Floor Slab Alternate Designs under Consideration
23...Connections for North Pre Function Window Wall
24...Clearances May Require Moving Building Shell 1.5'
25...PG&E Vault May Be Removed, Alternate Utility Location Pending
26...Thermal Expansion of Building, Impacts Being Studied
27...Information on Relocation of Dampers Provided to SDE
28...KH and MWA Provide Separate Meeting Notes

ACTION ITEMS.................. Click here to comment!

1...A&P to verify changes made by SDE from para 1 of notes for Structural
2...981019 target for submitting backgrounds on cores for 50% CD package
3...SDE to provide tude steel size modifications for KH elevator design.
4...SDE to issue design on Elevator pit for 5 and 6 OA 981006.
5...Kwan Henmi target date for stair data to SDE is 981019.
6...Steve will prepare a drawing to formalize the sketch reviewed at the
7...KH will verify common alignment of floor boxes between architectural
8...KH to develop alternate details of floor boxes for review of 50% CD
9...SDE submit design for 75 PSF and 150 PSF concrete slab design for
10...MWA to support coordination on framing Howard St. Entry Plaza.
11...Civil consultant will be notified to move floor drains in basement.
12...KH will verify columns in electrical room fits equipment.
13...MWA will prepare details showing the connections.
14...MHA will submit preliminary details to SDE for review.
15...MWA will provide information to SDE on status of PG&E vaule.

CONTACTS 
0201 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020101 - Mr. Ivan Romero, AIA; Project Architect
020102 - Kwan Henmi Architects
020103 - Interior Design/Documentation
0202 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020201 - Ms. Clonia Cautis, AIA, RA
020202 - Project Manager
020203 - Executive Committee
0203 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020301 - Mr. Steven Hergert; Architect
020302 - Michael Willis & Associates
020303 - Exterior Design/Documentation
0204 - Fay, Bernstein & Associates          415 397 3193 fax 5219
020401 - Mr. Alain Placido, P.E.; Engineer
0205 - Fay, Bernstein & Associates          415 397 3193 fax 5219
020501 - Mr. Hamid Fatehi, S.E.
020502 - Vice President
0206 - Structural Design Engineers          415 781 1505 fax 2718
020601 - Mr. Jon D. Andrews
020602 - Project Engineer
0207 - Structural Design Engineers          415 781 1505 fax 2718
020701 - Mr. John W. Laws; Principal

SUBJECTS
Structural Coordination Meeting 980924

0503 -    ..
0504 - Summary/Objective
0505 -
050501 - Follow up ref SDS 2 0000, ref SDS 1 0000.
050502 -
050503 - Reviewed notes from meeting on 980924.  Clonia set dates for KH work
050504 - on 50% CD package.
050505 -
050506 - New issues:
050507 -
050508 -     1.  Need study of floor boxes for alignment. ref SDS 0 5195
050509 -
050510 -     2.  PG&E Vault may not be needed. ref SDS 0 8120
050511 -
050512 -   [On 981006 received Clonia's memo summarizing scheduled assignments
050513 -   for KH on today's understandings. ref SDS 8 2574]
050514 -
050515 -   [On 981006 received WMA's notes. ref SDS 8 2575]
050516 -
050517 -
050518 -
050519 -
0506 -

SUBJECTS
Geotechnical Reports

0704 - Discussion
0705 -
070501 - Final Geo Technical Report Issued
070502 -
070503 - Jon initially, noted that SDE has received the final geo technical
070504 - report.
070505 -
070506 - There was not extended discussion of the results, perhaps reflecting
070507 - that the report has not yet been thoroughly reviewed.
070508 -
070509 - No impacts on project design were reported today.
070510 -
070511 - No impacts are anticpated on KH work.
070512 -
070513 -
070514 -
070515 -
0706 -

SUBJECTS
Administratio, Distribute Drawings
Structural, Distribute Drawings
Existing Buildings, Provide Drawings to Structural Engineer

1206 -
120601 -  ..
120602 - CD Drawings Distrubution to SDE
120603 -
120604 - Follow up ref SDS 2 2856.
120605 -
120606 - Jon requested 3 sets of the 25% CD package to support structural
120607 - engineering.
120608 -
120609 - SDE also requests 3 sets of 50% CD package.
120610 -
120611 - Clonia will follow up.
120612 -
120613 -
120614 -  ..
120615 - Drawings on Existing Buildings to Be Provided to SDE
120616 -
120617 - JV team submitted to SDE available drawings on existing buildings, per
120618 - 980924 meeting, reported under Issues Still Pending para 3 of notes
120619 - published on 980925. ref DRT 1 7930
120620 -
120621 - Additional drawings will be submitted when provided by the City of San
120622 - Francisco.
120623 -
120624 -
120625 -
1207 -

SUBJECTS
Structural Mechanical B Line Coordinate
Clearances

2005 -
200501 -  ..
200502 - Increase Framing Clearance for Ductwork at B Line
200503 -
200504 - Follow up ref SDS 2 2880.
200505 -
200506 - Kwan Henmi coordinating solution to duct problem at column line B from
200507 - JV Coordination meeting on 980929. ref SDS 2 2880
200508 -
200509 - A&P to verify changes made by SDE from para 1 of notes for Structural
200510 - Coordination meeting on 980924, issued on 980925. ref DRT 1 7788
200511 -
200512 - There was discussion of a call to Allen.
200513 -
200514 -
200515 -  ..
200516 - Floor Framing Bracing Needs Coordination with Mechanical Ducts
200517 -
200518 - JV team coordinating floor framing to provide clearance for ducts, as
200519 - reported at Coordination meeting on 980929. ref SDS 2 5712
200520 -
200521 - Continue work reported at Structural Meeting on 980924 in para 2 of
200522 - notes issued on 980925. ref DRT 1 1035
200523 -
200524 -
200525 -
200526 -
2006 -

SUBJECTS
Elevators
Coordinate Structural
Elevator Mechanical Rooms

3606 -
360601 -  ..
360602 - Elevators Kwan Henmi Focusing on 50% Package
360603 -
360604 - 981019 target for submitting backgrounds on cores for 50% CD package
360605 - to consultants.
360606 -
360607 - Need coordination with SDE and with elevator consultant to meet
360608 - schedule objective.
360609 - ..
360610 - No evident progress on Kwan Henmi's request from SDE for tube
360611 - steel size modifications for elevator framing, reported in para 3 of
360612 - notes for meeting on 980924, published on 980925. ref DRT 1 1944
360613 -
360614 - No submittal was cited showing information has been provided.
360615 -
360616 - SDE to provide tude steel size modifications for KH elevator design.
360617 -
360618 -
360619 - Elevator Cores 1 - 4
360620 -
360621 - Kwan Henmi developing elevator design, and expects to have information
360622 - for structural engineering within a week or so.
360623 -
360624 - SDE did not indicate priority on this matter.
360625 -
360626 - Kwan Henmi adding staff for stair design. see JV Coordination meeting
360627 - on 980929. ref SDS 2 9280
360628 -
360629 -
360630 - Elevator Cores 5 & 6 Complicated, Need Attention
360631 -
360632 - Clonia indicated elevator cores 5 and 6 are the most complicated
360633 - design problems, which may indicate these are needed earlier by the
360634 - structural engineer, however, there was no mention of this during the
360635 - meeting.
360636 -
360637 -
360638 - 1823
360639 - Elevator Pits for 5 and 6 to Be Suspended Concrete
360640 -
360641 - The record for structural meeting on 980924 shows Clonia's idea to
360642 - design suspended concrete pits for elevators 5 and 6, see para 9 under
360643 - Issues Still Pending in notes published on 980925. ref DRT 1 3198
360644 -
360645 - SDE to issue design on Elevator pit for 5 and 6 OA 981006.
360646 -
360647 -
360648 -  ..
360649 - Elevator Shaft, Machine Room Framing Using Structural Input
360650 -
360651 - Follow up ref SDS 2 5700.
360652 -
360653 - On 980924 SDE submitted steel framing sizes and sketches for
360654 - elevators, as reported in meeting notes para 4 under Issues Still
360655 - Pending published on 980925. ref DRT 1 9831
360656 -
360657 - A target date is 981012 for resolving elevator design using structural
360658 - information provided by SDE.
360659 -
360660 - On 980929 at JV Coordination meeting other information on access and
360661 - mechanical ducts also impact this work. ref SDS 2 5700
360662 -
360663 -
360664 -
360665 -
360666 -
3607 -

SUBJECTS
Restrooms, Backgrounds
50% CD Schedule Submit Backgrounds to

3805 -
380501 -  ..
380502 - Backgrounds for 50% CD Target Date to Consultants 981019
380503 -
380504 - Follow up ref SDS 2 3099.
380505 -
380506 - Clonia requested target date for 50% CD on restrooms, stairs to
380507 - mechanical mezzanines, roof and to elevator mechanical rooms.
380508 -
380509 - Factors impacting schedule on backgrounds for...
380510 -
380511 -         •  stair design are discussed in next segment. ref SDS 0 3848.
380512 -
380513 -         •  restrooms were reviewed on 980929. ref2 7738
380514 -
380515 -
380516 - KH is shooting for 981019 based on coordination of controlling
380517 - information and staffing, as discussed at the JV Coordination meeting
380518 - on 980929. ref SDS 2 6804
380519 -
380520 -     [On 981016 date changed from 981019 to 981026. ref SDS 10 9792]
380521 -
380522 -
380523 -
380524 -
380525 -
3806 -

SUBJECTS
Stairs, Structural

4104 -
410401 -  ..
410402 - Stair Parameters Needed for Structural Design
410403 -
410404 - JV team will provide information (e.g,, sections showing head
410405 - clearances, railing locations) on stair design needed for structural
410406 - engineering, as reported in para 5 under Issues Still Pending of notes
410407 - published on 980925 for meeting on 980924. ref DRT 1 5040
410408 -
410409 - Kwan Henmi target date for stair data to SDE is 981019.
410410 -
410411 - Clonia suggests that stair sections show tube steel framing and other
410412 - controlling elements.
410413 -
410414 - The scope of stair design was discussed at JV coordination meeting on
410415 - 980929. ref SDS 2 6240
410416 -
410417 - JV team recognizes that stairs are complicated, see meeting on 980929.
410418 - ref SDS 2 4272  Getting the solution right requires adequate time for
410419 - adequate attention to detail.
410420 -
410421 -
410422 -
4105 -

SUBJECTS
Stairs, Structural
Operable Wall Enclosures, South, Minna Street
Louvers/Vents
E Line

6207 -
620701 -  ..
620702 - WMA Needs Structural Solution for Op Wall Shaft/Stair on Minna St.
620703 -
620704 - Steve Hergert showed a sketch that illustrates a problem at E line.
620705 -
620706 - This seems related to the problem of "mechanical" shafts and stair on
620707 - the Minna street side that was discussed at the structural meeting on
620708 - 980924, as reported in para 7 under Issues Still Pending in notes
620709 - published on 980925. ref DRT 1 4515
620710 -
620711 - Steve's sketch showed that the structural beam design does provide
620712 - enough room for the exterior skin.
620713 -
620714 - There was consideration of bracing the walls back.
620715 -
620716 - Jon Andrews asked how much SDE needs to shift the beam?
620717 -
620718 - Steve related that adjustment is needed to provide a 9' 11" clear
620719 - opening.
620720 -
620721 - Clonia suggests a study to align the architectural and structural
620722 - drawings.
620723 -
620724 - Hamid Fatehi with FBA proposed consideration of an intermediate
620725 - support.
620726 -
620727 - Clonia suggested that Kwan Henmi lead the coordination.
620728 -
620729 - Steve wants to coordinate this solution to ensure it accomodates the
620730 - requirements of WMA's exterior design work.
620731 -
620732 - KH will support WMA in resolving this design, based on work reviewed
620733 - in record on 980929 of JV coordination meeting. ref SDS 2 7381
620734 -
620735 - Steve will prepare a drawing to formalize the sketch reviewed at the
620736 - meeting this morning.
620737 -
620738 - There was no date discussed on this work.
620739 -
620740 - The sketch will study stair and louver issues that impact structural
620741 - framing locations.
620742 -
620743 -      [On 981006 Steve reported progress. ref SDS 7 6552]
620744 -
620745 -
620746 -
620747 -
6208 -

SUBJECTS
Ceiling Hang Points
Coordinate Structural

6705 -
670501 -  ..
670502 - Ceiling Hook Layout Provided to SDE
670503 -
670504 - Follow up ref SDS 2 0528.
670505 -
670506 - Jon Andrews reported having received reflected ceilig plans yesterday.
670507 -
670508 - Kwan Henmi submitted via email today, a layout for ceiling hang points
670509 - using 11' 3" grid.  The submission shows floor 1.  Floors 2 and 3 are
670510 - the same.
670511 -
670512 - Hang points were discussed at structural meeting on 980924, as
670513 - reported in para 7 under Issues Still Pending of notes published on
670514 - 980925. see ref DRT 1 9330
670515 -
670516 - JV Coordination meeting on 980929 reviewed hang point issues. see the
670517 - record at ref SDS 2 0528
670518 -
670519 -    [On 981022 change in hang point layout reviewed. ref SDS 13 4839]
670520 -
670521 -
670522 -
670523 -
670524 -
670525 -
6706 -

SUBJECTS
Floor Utility Boxes, Layout
Utility Boxes in Floors
Floor Boxes, Utilities
Structural Floor, S2-20
Fire Protection, Floor Boxes

7608 -
760801 -  ..
760802 - Floor Utility Boxes Need Study to Verify Location, Scope
760803 -
760804 - Jon Andrews asked if there has been a change in the design that
760805 - reduces the number of utility boxes in the floors?  He pointed out
760806 - drawing S2.20 as possibly not being aligned with architectural layout.
760807 -
760808 - Ivan recalled there may be a slight (3/8") differential between
760809 - architectural and structural drawings on the alignment of floor boxes.
760810 -
760811 - The goal is to review booth layouts and floor boxes for all three (3)
760812 - floors on 981005.
760813 -
760814 - KH will verify common alignment of floor boxes between architectural
760815 - and structural drawings.
760816 -
760817 -      [On 981123 records a Project Work Summary on 981120 that
760818 -      indicates the review on floor boxes is complete. ref SDS 16 6507]
760819 -
760820 -
760821 -  ..
760822 - Alternate Designs Considered to Fireproof Floor Boxes
760823 -
760824 - There was discussion of a letter from Paoletti on fireproofing the
760825 - floor utility boxes.
760826 -
760827 - At the structural meeting on 980924 the design was changed from metal
760828 - to concrete, see para 8 under Issues Still Pending in notes issued on
760829 - 980925. ref DRT 1 3120
760830 -
760831 - SDE will prepare a design for a concrete floor box.
760832 -
760833 - The Life Safety consultant is writing a letter on requirements.
760834 -
760835 - Clonia has written a letter on the code for fire rating.
760836 -
760837 - Alternate designs are under consideration, e.g., using conventional
760838 - spray fireproofing; using multiple layers of gypboard.
760839 -
760840 - Consideration of acoustical (sound??) and fireproofing is needed.
760841 -
760842 - KH to develop alternate details of floor boxes for review of 50% CD
760843 - package.
760844 -
760845 - KH will follow up.
760846 -
760847 -      [On 981123 records a Project Work Summary on 981120 that
760848 -      indicates the review on floor boxes is complete. ref SDS 16 6507]
760849 -
760850 -
760851 -
760852 -
760853 -
7609 -

SUBJECTS
Slab Thickness for Soundproofing above Chiller in Basement

8104 -
810401 -  ..
810402 - Soundproof 1st Floor Above Chillers in Basement, Design Pending
810403 -
810404 - Jack Laws advised that SDE has prepared a design with 150 PSF concrete
810405 - for thickened slab to soundproof above the chiller area in the
810406 - basement.
810407 -
810408 - At the structural meeting on 980924 the need for soundproofing was
810409 - identified, see notes para 8 under Issues Still Pending published on
810410 - 980925. ref DRT 1 3120
810411 -
810412 - Today, there was consideration of using a 15" light weight or 12"
810413 - normal weight concrete slab.
810414 -
810415 - Clonia asked that...
810416 -
810417 -    SDE submit design for 75 PSF and 150 PSF concrete slab design for
810418 -    studying feasibility and cost.
810419 -
810420 -
810421 -
810422 -
810423 -
8105 -

SUBJECTS
Entry Plaza, Howard Street

8204 -
820401 -  ..
820402 - Entry Plaza on Howard Street Framing
820403 -
820404 - SDE and FBA coordinating solution for framing the Entry Plaza on
820405 - Howard Street, by extending basement to perimeter of plaza stairs, as
820406 - reported in para 1 under Issues Still Pending published on 980925 for
820407 - the meeting on 980924. ref DRT 1 1540
820408 -
820409 - Impacts on basement design, stairs, other consultants and schedule
820410 - where not discussed pending submission from SDE.
820411 -
820412 - MWA to support coordination on framing Howard St. Entry Plaza.
820413 -
820414 - No target date was discussed on this work.
820415 -
820416 -
820417 -
8205 -

SUBJECTS
Basement, Floor Plans/Layout
Coordinate Plumbing, Basement

8605 -
860501 -  ..
860502 - Basement
860503 -
860504 - Floor drains at location 3 E.5 and 2.3 E.5 both need to be shifted to
860505 - avoid conflict with column footings.
860506 -
860507 - Civil consultant will be notified to move floor drains in basement.
860508 -
860509 -
860510 -    [On 981006 progress reported. ref SDS 7 7150]
860511 -
860512 -
860513 -
8606 -

SUBJECTS
Basement, Floor Plans/Layout
Coordinate Col and Elec Equipment, Avoid Conflicts

9705 -
970501 -  ..
970502 - Basement Electrical Room Col Layout Coordinate with Equipment
970503 -
970504 - At the Structural meeting on 980924, Clonia suggested study to verify
970505 - electrical equipment in the NW corner electrical room will fit within
970506 - the dimensions of the structural columns.  See notes published on
970507 - 980924 para 2 under Issues Still Pending. ref DRT 1 2640
970508 -
970509 - The results of SDE and FBA coordination are not clear from the
970510 - record.
970511 -
970512 - KH will verify columns in electrical room fits equipment.
970513 -
970514 - Should have feedback from electrical information by 981005.
970515 -
970516 -     [On 981006 progress on study reported. ref SDS 7 7150]
970517 -
970518 - Impact on other project tasks was not discussed.
970519 -
970520 -
970521 -
970522 -
9706 -

SUBJECTS
Ramps
Basement, Structural, Floor

A405 -
A40501 -  ..
A40502 - Basement Floor Slab Alternate Designs under Consideration
A40503 -
A40504 - Changes of 6" in the design of the floor slab and its support elements
A40505 - impact basement elevations.  These changes follow up the structural
A40506 - meeting on 980924 reported in para 10 under Issues Still Pending for
A40507 - notes published on 980925. ref DRT 1 3306
A40508 -
A40509 - Clonia advised that the net impact is 3" at the trench drain which
A40510 - transitions from the bottom of the entry ramp to the basement floor
A40511 - slab.
A40512 -
A40513 - Steven advised of having asked Ivan to inform the civil consultants
A40514 - that a 6" adjustment was required, rather than a 3" adjustment at the
A40515 - trench drain location.
A40516 -
A40517 - Clonia urged that Kwan Henmi was responsible for having misinformed
A40518 - the civil consultant to make a 6" adjustment, because she recalls
A40519 - having told Kwan Henmi's CADD specialist, Bolivar, to advise Ivan
A40520 - about a 3" net impact.
A40521 -
A40522 - Steven affirmed that this was a Michael Willis error.
A40523 -
A40524 - Clonia was adament that the record show Kwan Henmi erred.
A40525 -
A40526 - Affected consultants will be notified of corrections.
A40527 -
A40528 - The construction cost consultant, Hanscome, will provide information
A40529 - on cost advantages of alternate floor slab designs.
A40530 -
A40531 - Civil, plumbing and structural coordination required.
A40532 -
A40533 - KH will review AGS mark up to determine correct impacts.
A40534 -
A40535 - Target to complete study is 981006.
A40536 -
A40537 -    [On 981006 progress reported. ref SDS 7 7150]
A40538 -
A40539 -    [On 981015 AGS reported incorporating 3" adjustment in civil
A40540 -    drawings, as reported on 981018. ref SDS 12 0936]
A40541 -
A40542 -
A40543 -
A40544 -
A406 -

SUBJECTS
Pre-function
Window Walls, North

A705 -
A70501 -  ..
A70502 - Connections for North Pre Function Window Wall
A70503 -
A70504 - Steven indicated that a solution has generally been established for
A70505 - connecting the window wall frame and the gravity wall, as set out in
A70506 - para 11 under Issues Still Pending of the notes for the structural
A70507 - meeting on 980924, published on 980925. ref DRT 1 3045
A70508 -
A70509 - MWA will prepare details showing the connections.
A70510 -
A70511 - There was no date discussed on when this is needed.
A70512 -
A70513 -
A70514 -
A70515 -
A70516 -
A706 -

SUBJECTS
Requirements, Clearances Building Shell
Clearances

AB05 -
AB0501 -  ..
AB0502 - Clearances May Require Moving Building Shell 1.5'
AB0503 -
AB0504 - Steven related considerations being given to moving the building shell
AB0505 - 1.5' to obtain needed clearences, as discussed at the JV Coordination
AB0506 - meeting on 989029. ref SDS 2 4224
AB0507 -
AB0508 - This seems related to the condition at the exterior wall near the
AB0509 - existing mechanical building, reported in para 12 under Issues Still
AB0510 - Pending for notes of structural meeting on 980924 published on 980925.
AB0511 - ref DRT 1 1938
AB0512 -
AB0513 - There was discussion of modifying precast wall thickness, and
AB0514 - requirements for fire rating and water proofing, in order to increase
AB0515 - clearance.
AB0516 -
AB0517 - One system has 5 layers of gypboard.
AB0518 -
AB0519 - Jack Laws advised that SDE will review wall thickness issue.
AB0520 -
AB0521 - There was discussion that normalizing wall width for the 1st floor
AB0522 - would solve 4 hour fire rating problem.
AB0523 -
AB0524 - MHA will submit preliminary details to SDE for review.
AB0525 -
AB0526 - There was no time discussed on when this work is needed.
AB0527 -
AB0528 -
AB0529 -
AB06 -

SUBJECTS
PG&E Vault

AC04 -
AC0401 -  ..
AC0402 - PG&E Vault May Be Removed, Alternate Utility Location Pending
AC0403 -
AC0404 - Existing PG&E utility vault may be removed.  Study underway on need to
AC0405 - build a new vault.
AC0406 -
AC0407 - MWA will provide information to SDE on status of PG&E vaule.
AC0408 -
AC0409 - There was no date discussed for this work; information will be
AC0410 - provided as soon as possible.
AC0411 -
AC0412 -
AC0413 -
AC0414 -
AC05 -

SUBJECTS
Thermal Expansion of Building

AE04 -
AE0401 -  ..
AE0402 - Thermal Expansion of Building, Impacts Being Studied
AE0403 -
AE0404 - There was no discussion of this subject shown in para 13 under Issues
AE0405 - Still Pending of notes for structural meeting on 980929 published on
AE0406 - 980925. ref DRT 1 4256
AE0407 -
AE0408 -
AE0409 -
AE0410 -
AE05 -

SUBJECTS
Col Line A Fire Dampers
Dampers, Coordinate Structural

AJ05 -
AJ0501 -  ..
AJ0502 - Information on Relocation of Dampers Provided to SDE
AJ0503 -
AJ0504 - MWA provided information to SDE on relocating dampers, as reported in
AJ0505 - para 14 of notes for structural meeting on 980924 published on 980925.
AJ0506 - ref DRT 1 6113
AJ0507 -
AJ0508 - Fire dampers were discussed at the 980929 JV coordination meeting.
AJ0509 - see ref SDS 2 5829
AJ0510 -
AJ0511 - Additional information on lines A, 1 and 6 will be submitted.
AJ0512 -
AJ0513 - There was no date discussed on when this is needed.
AJ0514 -
AJ0515 -
AJ0516 -
AJ0517 -
AJ0518 -
AJ06 -

SUBJECTS
Communication
Meeting Notes
Gensler's Manual
Gensler Fails to Provide Clear, Concise,
PM Record of Coordination Unclear,
Expertise in Discipline NOT Essential for
Communication Manager Needs Expertise

AX10 -
AX1001 -  ..
AX1002 - KH and MWA Provide Separate Meeting Notes
AX1003 -
AX1004 - Follow up ref SDS 2 7930.
AX1005 -
AX1006 - Clonia advised that KH will prepare meeting notes on interior work,
AX1007 - and MWA will do notes for exterior work.
AX1008 -
AX1009 - There was no discussion on procedures for coordinating notes, review
AX1010 - of action items, composite and transition issues, and using a common
AX1011 - WBS.
AX1012 - ..
AX1013 - Clonia requested that Communication Metrics work product conform
AX1014 - to the format for meeting notes in a Gensler Project Management manual
AX1015 - which she advised that the JV has adopted for the Moscone project.
AX1016 -
AX1017 -      [On 981006 received Gensler memo dated 981002 on results of this
AX1018 -      meeting, Clonia sets out in para 10 procedures for preparing
AX1019 -      notes on meetings. ref SDS 8 2579]
AX1020 -
AX1021 -      [On 981018 created HTML form to accomplish Gensler's Meeting
AX1022 -      Notes format. ref SDS 11 6046]
AX1023 -
AX1024 - This format has a column for discussion and one for action items.
AX1025 - ..
AX1026 - Gensler's documents in the record show there is no consistent
AX1027 - application of the form.  Actions items are shown in the Discussion
AX1028 - column, and discussion is entered in the Action field.  Explanations
AX1029 - are cryptic without references or citations to support understanding
AX1030 - of meaning, chronology, responsibility and results.  There is no
AX1031 - location given with respect to drawing numbers, plan details, floor
AX1032 - levels.
AX1033 -
AX1034 -      [On 981215 Bill Long advised that Gensler was correct to have an
AX1035 -      architect prepare meeting notes. ref SDS 17 2090]
AX1036 -
AX1037 -      [On 981123 Robert Rudeen reviewed docs. ref SDS 14 7072]
AX1038 -
AX1039 - There is no consistency in identification of continuing issues.
AX1040 -
AX1041 - An item identified as #7 in one document is #12 or #3 in later
AX1042 - documents.
AX1043 -
AX1044 - Gensler's work scope descriptions in notes of meeting evolve from one
AX1045 - meeting to the next, so establishing in the record that anything has
AX1046 - been done, requires review of multiple documents, consuming inordinate
AX1047 - time, resulting in management by guess and gossip, because people do
AX1048 - not have enough time to look up the record.
AX1049 -
AX1050 -     [On 981123 Robert Rudeen notified Gensler of need for clear,
AX1051 -     concise, complete communication. ref SDS 15 7072]
AX1052 - ..
AX1053 - Clonia asked if there were questions on her mark up of the
AX1054 - record for the JV coordination meeting on 980929 received this
AX1055 - morning. ref SDS 5 6720
AX1056 -
AX1057 - This matter is reported separately. ref SDS 5 3888
AX1058 -
AX1059 -
AX1060 -
Distribution. . . . See "CONTACTS"