DIARY: October 15, 1998 02:00 PM Thursday; Rod Welch

Coordinating meeting with Structural consultants on Moscone III.

1...Summary/Objective
2...Elevator 5 & 6, Restrooms
3...Catwalk for Fire Damper Access at Elevators 5 and 6
4...Elevator 5 and 6 Pit Framing
5...Elevators 1 - 4, Grease Duct
6...Elevator Equipment Rooms
7...Pre Function Floors Terrazzo
8...Sky Folding Partition at Column Line B
9...Basement, CMU Wall Above Kitchen, Locate to Miss Mech Ducts

ACTION ITEMS.................. Click here to comment!

1...SDE will modify the structural design to support Janet's solution.
2...SDE will modify structural drawings to show support of the grease duct
3...Jon advised that SDE will submit drawings tomorrow for the elevator
4...Michael will submit KH package to SDE and to TEE tomorrow.

CONTACTS 
0201 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020101 - Mr. Ivan Romero, AIA; Project Architect
020102 - Kwan Henmi Architects
020103 - Interior Design/Documentation
0202 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020201 - Ms. Clonia Cautis, AIA, RA
020202 - Project Manager
020203 - Executive Committee
0203 - Structural Design Engineers          415 781 1505 fax 2718
020301 - Mr. Jon D. Andrews
020302 - Project Engineer
0204 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020401 - Mr. Michael NLN; Architect
020402 - Kwan Henmi Architects
020403 - Interior Design/Documentation
0205 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020501 - Ms. Jannett NLN; Architect
020502 - Kwan Henmi Architects
020503 - Interior Design/Documentation

SUBJECTS
Structural Meeting, 981015

0503 -    ..
0504 - Summary/Objective
0505 -
050501 - Follow up ref SDS 8 0000, ref SDS 6 0000.
050502 -
050503 -    [On 981018 prepared notes using Gensler format. ref SDS 10 1120]
050504 -
050505 -    [On 981019 issued notes to Ivan for edits. ref SDS 11 4320]
050506 -
050507 -    [On 981020 Ivan advised Gensler issued notes. ref SDS 12 3920]
050508 -
050509 -    [On 981022 Gensler did not issue notes, KH will edit and issue for
050510 -    the project record. ref SDS 13 6478]
050511 -
050512 -    [On 981027 issued notes for distribution. ref SDS 15 0000]
050513 -
050514 -
050515 -
050516 -
050517 -
050518 -
0506 -

SUBJECTS
Elevator 5, 6
Structural, Coordination Mechanical Shafts
Ductwork Clearances
Elevator 5&6 Framing Duct Clearance
Elevators 5 & 6 Fire Damper Access
Elevator Pit 5 and 6
Elev Pit 5&6, Note Required

2010 -
201001 -  ..
201002 - Elevator 5 & 6, Restrooms
201003 -
201004 - Janet showed drawings KH has in progress to coordinate mechanical and
201005 - structural at elevator 5 and 6, so that main beams do not go through
201006 - HVAC shafts. ref DIP 1 7789
201007 -
201008 - Jon reported that SDE has changed some dimensions on its structural
201009 - drawings to resolve mechanical and structural coordination for the
201010 - restrooms, per meeting with A&P on October 14, 1998. ref SDS 9 8032
201011 -
201012 - SDE will modify the structural design to support Janet's solution.
201013 -
201014 -     [On 981111 SDE to design elevator pit. ref SDS 16 3975]
201015 -
201016 - Jon noted that SDE's design is not well enough established yet to
201017 - provide the exact number of seismic dampers.
201018 -
201019 - KH will continue present design parameters for resolving mechanical
201020 - and structural issues.
201021 -
201022 -
201023 -  ..
201024 - Catwalk for Fire Damper Access at Elevators 5 and 6
201025 -
201026 - Clonia advised that the catwalk cannot interfere with HVAC.
201027 -
201028 - Janet noted that KH will resolve these issues. ref DIP 1 4020
201029 -
201030 - Clonia thought this problem was solved some time ago.
201031 -
201032 -
201033 -
201034 -  ..
201035 - Elevator 5 and 6 Pit Framing
201036 -
201037 - CC advised that the elevator pit does not require a sump.
201038 -
201039 -     [On 981111 SDE to design elevator pit. ref SDS 16 3975]
201040 -
201041 -
201042 -
201043 -
201044 -
2011 -

SUBJECTS
Elevator 1 - 4
Grease Duct in Kitchen
Grease Duct
Kitchen, Grease Duct
Mech Rooms for Elev 1 - 4
Equip Rooms Elev 1-4 Not on CP

3209 -
320901 -  ..
320902 - Elevators 1 - 4, Grease Duct
320903 -
320904 - Michael showed a KH sketch on the grease duct at lines between 4.6, 5,
320905 - and A.5, per background from meeting on 980929. ref SDS 2 6300
320906 -
320907 - The grease duct separation requires structural support at all floor
320908 - locations. ref DIP 1 6004
320909 -
320910 - Clonia asked if the grease duct location was changed in the 25% CD
320911 - package. Michael advised there has been no change.
320912 -
320913 - During the meeting, Michael prepared copies of details from KH
320914 - drawings for SDE to use in updating structural drawings for core at
320915 - elevators 1 - 4.
320916 -
320917 - Jon and Michael reviewed the KH drawings to verify dimensional
320918 - requirements.
320919 -
320920 - SDE will modify structural drawings to show support of the grease duct
320921 - at separation.
320922 -
320923 - Clonia noted that vents may be required at the grease shaft.
320924 -
320925 - Michael reported on understandings from the meeting with A&P yesterday
320926 - that no vents are required. They are, however, tied to exhaust fans.
320927 - ref SDS 9 0588
320928 -
320929 -
320930 -  ..
320931 - Elevator Equipment Rooms
320932 -
320933 - Jon advised that SDE will submit drawings tomorrow for the elevator
320934 - equipment room. ref DIP 1 4590
320935 -
320936 - Clonia advised that this is not on the critical path of the project
320937 - schedule, as reviewed in the record on 980929. ref SDS 2 2240  There
320938 - was no reference to a schedule or other submission showing what is on
320939 - the critical path.
320940 -
320941 -     [On 981113 Robert's reports that Clonia advised KH that the
320942 -     Operable Wall package is not needed on 981221, as earlier
320943 -     represented. ref SDS 17 3987]
320944 -
320945 -
320946 -
3210 -

SUBJECTS
Terrazzo

3304 -
330401 -  ..
330402 - Pre Function Floors Terrazzo
330403 -
330404 - JA advised that SDE is aware that the 1st floor Pre Function area is
330405 - terrazzo. ref DIP 1 4563
330406 -
330407 -
330408 -
330409 -
330410 -
3305 -

SUBJECTS
Structural Framing
Electrical
Coordinate Col Line B
Sky Fold Partition

4007 -
400701 -  ..
400702 - Sky Folding Partition at Column Line B
400703 -
400704 - Michael advised that KH is preparing a design package for submission
400705 - to SDE on the Sky Folding Partition system. ref DIP 1 0204
400706 -
400707 - Clonia asked that this information also be submitted to the electrical
400708 - consultant.
400709 -
400710 - Michael will submit KH package to SDE and to TEE tomorrow.
400711 -
400712 -    [On 981111 SDE to prepare support details. ref SDS 16 8620]
400713 -
400714 -
400715 -
400716 -
4008 -

SUBJECTS
Masonry Wall Above Kitchen
CMU Wall Support, Duct Clearances
Masonry Wall Above Kitchen
CMU Wall Support above Kitchen
Structural Support Maintain Clearance for

4508 -
450801 -  ..
450802 - Basement, CMU Wall Above Kitchen, Locate to Miss Mech Ducts
450803 -
450804 - There was discussion about coordinating columns at line A4 between
450805 - lines 3 and 4. ref DIP 1 0720
450806 -
450807 - Jon indicated a preference for locating a concrete block wall outside
450808 - the columns.
450809 -
450810 - SDE has KH sketch and will incorporate.
450811 -
450812 - Subframe layout will be reviewed by SDE for 50% CD set.
450813 -
450814 -     [On 981022 SDE reported progress. ref SDS 14 3851]
450815 -
450816 -
450817 -
Distribution. . . . See "CONTACTS"