THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700


S U M M A R Y


DIARY: October 28, 1998 10:32 AM Wednesday; Rod Welch

Received Robert's weekly progress report on Moscone.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020101 - Mr. Robert Rudeen; Architect
020102 - Kwan Henmi Architects
020103 - Interior Design/Documentation

SUBJECTS
Project Work Summary
Policy/Procedures, Project Work Summary Form
Document Management
Forms Management, Project Work Summary

0806 -    ..
0807 - Summary/Objective
0808 -
080801 - Follow up ref SDS 13 3216.
080802 -
080803 - Received ref DIT 1 0000 which is Robert's weekly progress report and
080804 - diary on Moscone for period ending 981023.
080805 -
080806 -     [On 981030 received next report. ref SDS 16 4602]
080807 -
080808 - This is part of his work practice along with the weekly work plan
080809 - system, and his binder with scheduled tasks and notes of daily
080810 - information, also discussed yesterday. ref SDS 13 3234
080811 -
080812 - Created an HTML format so he can get it from the document log system,
080813 - developed beginning on 981015. ref SDS 2 5292
080814 -
080815 - Decided to make a formal document because it has a date and is in the
080816 - vein of a report.  For convenience addressed it from Robert from the
080817 - Moscond project, to Kwan Henmi and used Denis.  Could just as well
080818 - used Bill or Robert himself, since this is really a memo to file.
080819 -
080820 - He uses it as a planning tool.  Writing out what has been
080821 - accomplished, forces consideration of what needs to be done, which is
080822 - the idea of the SDS program, per analysis on 981027, ref SDS 13 3216
080823 -
080824 -
080825 -
080826 -
0809 -
Distribution. . . . See "CONTACTS"