DIARY: November 4, 1998 02:41 PM Wednesday; Rod Welch

Visited Moscone Project Office on meeting note review with Ivan.

1...Summary/Objective
2...Review Structural Meeting Notes Reveal Clarifications Needed
3...Work Station and desk for Robert Rudeen
4...Delivered Notes of Mech Meeting for 981021 with Robert's Edits


..............
Click here to comment!

CONTACTS 
0201 - Gensler/Michael Willis/Kwan Henmi    415 433 3700 fax 415 627 3700
020101 - Mr. Robert Rudeen; Architect
020102 - Kwan Henmi Architects
020103 - Interior Design/Documentation

SUBJECTS
Structural Meeting, 981022
Notes for Meetings
Feedback

0905 -    ..
0906 - Summary/Objective
0907 -
090701 - Follow up ref SDS 21 0000, ref SDS 20 0000.
090702 -
090703 - Reviewed current edits on notes for structural meeting on 981022. Phil
090704 - will revise his report.  Janet will provide edits on her portion of
090705 - the notes.
090706 -
090707 - Gensler has reaaranged the office to provide a desk for Robert
090708 - Rudeen.
090709 -
090710 - Submitted final notes with Robert's edits of mechanical meeting on
090711 - 981021.
090712 -
090713 -
090714 -
0908 -
0909 -
0910 - Discussion
0911 -
091101 - Ivan Romero was in the office today.  He left on vacation last week,
091102 - but his grandmother died, and so he returned to attend the funeral.
091103 -
091104 -
091105 -  ..
091106 - Review Structural Meeting Notes Reveal Clarifications Needed
091107 -
091108 - Ivan reviewed the notes for the structural meeting held on 981022,...
091109 - ref SDS 7 0000, and submitted on 981028. ref SDS 14 0140.
091110 -
091111 - Ivan edited a printed set of the notes I prepared and discussed with
091112 - him on 981029. ref SDS 17 3885
091113 -
091114 -  ..
091115 -
091116 - He showed edits prepared by Michael on elevators 1 and 2, and 3 and 4,
091117 - entered on the printed draft.
091118 -
091119 - Ivan edited notes on the CMU wall, hang points and fireproofing.
091120 - ..
091121 - Phil Buscmi and Ivan developed extensive edits on Phil's initial
091122 - memo covering his part of the structural meeting, which were received
091123 - from Phil on 981030. ref SDS 19 4483
091124 -
091125 - This was a good meeting that begins to accomplish the goals for
091126 - obtaining feedback and spawning discovery discussed at the KH team
091127 - meeting on 981016, ref SDS 4 1446, and set in the review analysis on
091128 - 981014. ref SDS 3 3575
091129 -
091130 - Phil will prepare a new memo that incorporate the discussion today
091131 - with Ivan about the objectives, understandings, problems identified
091132 - and resulting action items from his part of the meeting with SDE on
091133 - 981022.
091134 -
091135 - An example of the clarification pertained to the scope of slab edge
091136 - beam support requested by Clonia for a stair landing.  When he and
091137 - Ivan discussed it and observed the sketch that was discussed in the
091138 - meeting, they both remembered important issues that need clarification
091139 - in the record that were not actually disucssed in the meeting and were
091140 - not in Phil's initial notes.
091141 -
091142 - Phil will cite the sketches and details that were reviewed which
091143 - support the meeting notes.
091144 -
091145 -     [On 981105 received Phil's memo to Ivan. ref SDS 22 0000]
091146 -
091147 -  ..
091148 -
091149 - Ivan indicated that Janet will prepare a separate memo and submit it
091150 - to help in finalizing these notes on the portion of the meeting that
091151 - pertained to her work.  We reviewed the intial draft, and Ivan could
091152 - not fully make out what she was discussing and the results.
091153 -
091154 -     [On 981106 Janet emailed notes. ref SDS 23 3466]
091155 -
091156 -
091157 -
0912 -

SUBJECTS
Mechanical Meeting, 981021
Office Space for Increased Staff
Office Congestion, 980929

1306 -
130601 -  ..
130602 - Work Station and desk for Robert Rudeen
130603 - Delivered Notes of Mech Meeting for 981021 with Robert's Edits
130604 -
130605 - Follow up ref SDS 21 1169, ref SDS 20 8955.
130606 -
130607 - I initially gave Ivan the printed version of the notes for the
130608 - mechanical meeting held on 981021, which has the edits received from
130609 - Robert this morning. ref SDS 21 5145
130610 -
130611 - When Robert came into the office about 1500, he asked me to the notes
130612 - on his desk, which is a new work station that has been created for him
130613 - in the Project Office.
130614 -
130615 - The Project Office has been rearranged so there is space for Robert's
130616 - desk at the end of the room opposite from the Project Manager's desk.
130617 - The copy machine has been been moved to the walkway between KH and MW
130618 - staff workstations.
130619 -
130620 - This does not provide the "war room" Robert and the project need for
130621 - thorough planning and management, but it does improve on the initial
130622 - plan for Robert to use other people's desks while they are in
130623 - meetings, as discussed on 981020. ref SDS 5 5005
130624 - ..
130625 - The congestion problem due to inadequate space shown in the
130626 - record on 980929 has been compounded by these changes. ref SDS 1 4966
130627 -
130628 - To make room for Robert's desk, the conference table was replaced by a
130629 - smaller table that is inadequate for the meetings that have been held
130630 - up until now, with sometimes 6 - 8 people involved.  These meetings
130631 - now have to be held outside the project office and this means
130632 - coordination with staff during meetings is more difficult.  When
130633 - things are difficult, marginal clarifications are avoided and this
130634 - leads to error under Aristotle's rule about the least initial
130635 - deviation from the truth...
130636 -
130637 -
130638 -
1307 -