S U M M A R Y


DIARY: September 30, 1998 01:34 PM Wednesday; Rod Welch

Continue set up Moscone III project; review JV Agreement.

1...Summary/Objective
2...Responsibilities of Parties, Article 2
3...Professional Negligence, Willful Misconduct
4...Management of Association, Claudia Project Manager, Article 4.2
5...Work Plan
6...Project Management Scope, Appendix E para I
7...Kwan Henmi Entitled to Project Management and Design Coordinator
......Question
......Question
8...Dispute Resolution, Article 15
9...Attorney Fees, Article 16

ACTION ITEMS.................. Click here to comment!

1...Where is the manual?
2...Where is the Work Plan?
3...Where are the notes of meetings with the City?
4...Does it require records of meetings?

CONTACTS 

SUBJECTS
Communication Metrics
Management Plan
Contracts/Agreements
Schedule
Project Management
Planning Schedule, WBS, Recource Allocation
Planning Schedule, WBS, Resource
Project Manager, Claudia Cautis

1210 -    ..
1211 - Summary/Objective
1212 -
121201 - Follow up ref SDS 8 0000, ref SDS 6 0000.
121202 -
121203 - Need to do...
121204 -
121205 -          Contacts
121206 -          Subject Index
121207 -          Enter Contracts and other documents
121208 -
121209 - Set up a specific contact record for the JV based on agreement between
121210 - the parties.
121211 -
121212 -  ..
121213 - Responsibilities of Parties, Article 2
121214 - Professional Negligence, Willful Misconduct
121215 -
121216 - On page 1, section 2.5 says
121217 -
121218 -     Except as to professional negligence and willful misconduct, the
121219 -     parties intend that the responsibilities and obligations,
121220 -     financial and otherwise, assumed under Project Agreement shall be
121221 -     borne by each as described in the Project Agreement and Appendix
121222 -     C.
121223 -
121224 - This section establishes that professional negligence and willful
121225 - misconduct are implied requirements, which if breached, are grounds
121226 - for recovery by Kwan Henmi.
121227 -
121228 -     [On 981113 review of meeting on 981112 indicates professional and
121229 -     willful misconduct. ref SDS 12 2673]
121230 -
121231 -  ..
121232 - Management of Association, Claudia Project Manager, Article 4.2
121233 -
121234 - Clonia Cautis shall be the Project Manager.  The Project Manager shall
121235 - be responsible for the day-to-day direction and management of the
121236 - work, shall coordinate the work and be responsible for all contracts
121237 - with the Owner and the Owner's authorized representatives, and all
121238 - contacts with consultants.
121239 -
121240 -     Schedules, WBS and resource requirements, are integral to
121241 -     providing professional "...direction and management of the work."
121242 -
121243 -     This section can be read to say that the project manager is
121244 -     responsible for "...all contacts with consultants."
121245 -
121246 -     Does this provision intend that JV partner coordination with
121247 -     consultants be conducted through the Project Manager?
121248 -
121249 -     What does it mean to "be responsible" for contacts with
121250 -     consultants?  Is the project manager required to maintain the
121251 -     record of contacts with consultants?
121252 -
121253 -
121254 -
121255 - Work Plan
121256 - Project Management Scope, Appendix E para I
121257 -
121258 - It appears that Appendix E para I defines the scope of Project
121259 - Management duties to be performed by the Project Manager.
121260 -
121261 - Gensler is to prepare, update and monitor a project schedule.
121262 -
121263 - Schedule to include all meetings and approval and milestone dates.
121264 -
121265 -     What does "all meetings" mean?
121266 - ..
121267 - Gensler is to develop a Project Management Manual and Work Plan
121268 -
121269 -     Where is the manual?
121270 -
121271 -     Where is the Work Plan?
121272 -
121273 - Gensler is responsible to meet with the City.
121274 - ..
121275 - Gensler is responsible to prepare and distribute meeting notes.
121276 -
121277 -     Where are the notes of meetings with the City?
121278 -
121279 - The Agreement with the City says in para...
121280 -
121281 -     3.2.4 Construction Document Phase...
121282 -
121283 -         para (2) use ...procedures set forth in "Consulting
121284 -         Architect's Guide for Building Projects."
121285 -
121286 -     This evidently is a City document.
121287 -
121288 -     Does it require records of meetings?
121289 -
121290 -         para (7) says to submit a drawing set at 50% and 95% to the
121291 -         City.
121292 - ..
121293 - Appendix E on page 11 says MW and KH have responsibility for
121294 - coordinating consultants during the construction document phase, and
121295 - Gensler has responsibility to review.
121296 -
121297 -
121298 -
121299 - Kwan Henmi Entitled to Project Management and Design Coordinator
121300 -
121301 - Have not had time to scan the agreements, but cursory analysis
121302 - indicates cause of project schedule problems.
121303 -
121304 -     Gensler is responsible for Project Management, and that task is
121305 -     not being performed.
121306 - ..
121307 - The last page in the agreement says Clonia is the Project
121308 - Manager, and Kevin Hart is the Project Design Director.
121309 -
121310 - Project Management duties are budgeting, scheduling and team project
121311 - direction and coordination, including production and distribution of
121312 - meeting notes.
121313 -
121314 -       ..
121315 -      Question
121316 -
121317 -      Where is Gensler's schedule, WBS, staffing requirements, that
121318 -      shows the work needed to reach milestones?
121319 -
121320 -         This was considered on 980928, ref SDS 5 2448, and at the JV
121321 -         Coordination meeting on 980929. ref SDS 7 6804
121322 -
121323 -         [On 981001 discussed with Denis. ref SDS 10 3135]
121324 -
121325 -      There is no big CPM on the wall showing precedence, chronology
121326 -      and critical tasks.
121327 -
121328 -      Where is Gensler's notice to KH of when to begin 50% CD, what
121329 -      level of effort is needed, and what sequence of activities should
121330 -      be followed to coordinate with others?
121331 -
121332 -          [On 981016 Gensler's memo to JV team on 980826 sets milestone
121333 -          dates, but does not show any task sequence, work package or
121334 -          resource requirements. ref SDS 11 2717]
121335 -
121336 -
121337 - The Agreement between the City of San Francisco and the JV says on
121338 - page 9 under section 3.1 e that Kevin Hart is the Design Principal,
121339 - whose role shall be as defined in Attachment 5.  I do not find
121340 - Attachment 5 in the document received from Kwan Henmi, however,
121341 - Aggendix G to the JV Agreement says...
121342 -
121343 -     Mr. Hart will be responsible for coordinating the team design
121344 -     efforts.
121345 -
121346 -
121347 -       ..
121348 -      Question
121349 -
121350 -      Where is Kevin?
121351 -
121352 -      Clonia is trying to perform design coordination, but this takes
121353 -      valuable time away from her true duties to perform project
121354 -      management.
121355 -
121356 -
121357 - This explains why KH is having trouble.  The project manager is trying
121358 - to be the design director, with the result that there is no project
121359 - management getting done.
121360 -
121361 - The Project Manager is spread too thin, and Kwan Henmi and MW are
121362 - paying the price.
121363 -
121364 - Gensler is asking KH to perform project management and provide design
121365 - services, with the result that KH Project Architect, Ivan, is
121366 - overwhelmed.
121367 -
121368 - KH is assuming some project management scope, but reluctantly due to
121369 - budget constraints.
121370 -
121371 -     [On 981001 discussed with Denis. ref SDS 10 3135]
121372 -
121373 -
121374 -
121375 -
1214 -

SUBJECTS
Dispute Resolution

1304 -
130401 -  ..
130401 - Dispute Resolution, Article 15
130402 -
130403 - The agreement says on page 10 that disputes are to be submitted
130404 - initially to mediation before a mediator mutually acceptable to the
130405 - parties.
130406 -
130407 - Disputes not resolved by mediation shall be submitted to arbitration
130408 - using Construction Industry Arbitration Rules of American Arbitration
130409 - Association.  Disputes in excess of $100K shall be heard by a 3
130410 - member panel.
130411 -
130412 -
130413 - Attorney Fees, Article 16
130414 -
130415 - Prevailing party shall receive attorney fees and reasonable costs,
130416 - including the time of parties' personnel at normal billing rates.
130417 -
130418 - "Prevailing party" means that if an action is filed, and then is
130419 - dismissed by the moving party in exhange for payment by the
130420 - respondent, then attorney fees and costs may be recovered as well.
130421 -
130422 -
130423 -
130424 -
130425 -