THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700


S U M M A R Y


DIARY: May 6, 1996 07:33 AM Monday; Rod Welch

Called Tom at COE re Communication Metrics contract.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 744 3033 fax 3449
020101 - Mr. Thompson F. Keesling; Architect =415 744 3033
020102 - Construction - Operations Division

SUBJECTS
SDS, Marketing, Sales, Proposal, Contract & Support
Corps of Engineers, SFD
Initiating Contract

0705 -    ..
0706 - Summary/Objective
0707 -
070701 - Followed up work at ref SDS 20 line 48, submittting notes ref DIP 1
070702 - line 28, of the meeting with Hank Hatch at ref SDS 17 line 84, ref SDS
070703 - 18 line 41, ref SDS 16 line 38, ref SDS 14 line 37, ref SDS
070704 - 116, ref SDS 10 line 93 and ref SDS 7 line 58.
070705 -
070706 - Tom indicated COE SFD expects to have funding for the Welch assignment
070707 - within 3 - 4 weeks.
070708 -
070709 -
070710 -
070711 -
0708 -
0709 -
0710 - Discussion
0711 -
071101 - Tom said they expect to get funding for my assignment in a few weeks
071102 - now that the budget has passed.  He feels they will not need support
071103 - for the organization move, since it will have been completed by the
071104 - time I can come on board in June.
071105 -
071106 - I asked Tom if they continue to feel this assignment should be
071107 - performed?
071108 -
071109 - Tom said they want to do the Communication Metrics project.
071110 - ..
071111 - He said they feel that in addition to DMMO I can support the
071112 - Port of Oakland project.  It is standing down for two months while
071113 - procurement is completed for a dredging machine that can handle the
071114 - harder material that has now been encountered at the site.  The
071115 - machine on site cannot handle this material.  This was evidently
071116 - known, and so another machine was to have been delivered, but either
071117 - the current work went faster than expected or the delivery of the
071118 - other machine is later than planned.  In any case, they feel this
071119 - affords an opportunity to use Welch on the Oakland project.
071120 -
071121 -     [See follow up at ref SDS 21 line 98.]
071122 -
071123 -
0712 -
Distribution. . . . See "CONTACTS"