U.S. Army Corps of Engineers
San Francisco District
333 Market Street
San Francisco, CA  94105 1905
| CESPN-PM (Keesling, 415 977 8473) | October 7, 1997 | 
|
| MEMO FOR: 
 
 | CEMP-E (Jim Jones) HQUSACE Washington, D.C.
 | 
|
..
 | Subject: | Communication Metrics Cost Savings | 
|  | Preparing for the 21st Century 
 | 
      -  References:
          -  Memo to CEMP-E, Jim Jones Sep 29, 1997
          
-  Jim Jones memo (email) to Keesling, received Sep 4, 1997
          
-  Keesling memo (email) to Jim Jones, Sep 4, 1997
          
-  San Francisco District report on Comm Metrics, Mar 28, 1997
          
-  Estimate Cost Savings Comm Metrics, Oct 7, 1997 (Attach 1)
          
-  Strategic Vision, USACE Commander, Lt. Gen. Joe N. Ballard
 
 
 
-  Per your
      request,
      ref b, attached is an estimate of cost savings
      for Communication Metrics, ref e, which should
      compare favorably with savings from recent Corps-wide initiatives
      to use Project Management, CFMS and RMS.
      Communication
      Metrics
      offers a strategic, core competency to improve performance and
      cost effectiveness, as reported earlier on March 28, 1997.
      ref d.  This new
      capability supports the Commander's charge to prepare for the
      challenge of new realities that require better methods in
      the 21st century, ref f.
 ..
 
-   Communication Metrics saved construction management expense
      on Oakland, including S&A, approximately $317K and
      substantially contributed to cost avoidance on pending
      claims of about $3.4M.  The cost of this savings was
      approximately $50K for 3 months.
 ..
 Communication Metrics also saved the prime contractor added
      expense on part of the work, consistent with our partnering
      policy.
 ..
 
-   Communication Metrics would have saved approximately
      $2M on construction management cost if used for the 2 year
      construction period on Oakland.  The cost to the government for
      these services would be about $500K.  Based on adjusted project
      total outlays of $56M, it is estimated Communication Metrics
      would save the government $5.8M or about 10% of construction
      cost.
 ..
 This return of $10 for each $1 of cost, i.e., ROI is
      10:1, could be substantially higher on the Oakland Harbor
      project due to significant value at risk, now nearly $65M.
 ..
 
-  
      Cost avoidance reflects estimates
      of results on two claims by the contractor which total $22M.
      Communication Metrics developed our position which is expected to
      prevail.  Assigning a current value is clearly
      speculative due to
      the vagaries of litigation.  This estimate reflects the
      contribution of Communication Metrics in avoiding payment of
      unearned sums to the contractor.  Cost avoidance would likely be
      much higher, if Communication Metrics were used for the duration
      of the project.
 ..
 
-   Saving $2M from construction management expense
      reflects increased time District Operations staff expended on
      Oakland due to practices of the contractor and changes in the
      business environment that cause information overload. Limited
      span of attention, like span of control in the military, means
      increased attention to Oakland has a cascading negative impact on
      District Operations.  However, added effort on Oakland is
      required to avoid significant risk from $65M in claims.  Greater
      savings can therefore result by using Communication Metrics from
      project recon through design in order to fix initial upstream
      problems that are otherise overlooked, forgotten or ignored until
      much later when construction cost is impacted.
 ..
 
-   Communication Metrics applied to District Operations could
      yield cost savings in the range of 6%, based on limited results
      from Oakland.  This will enable current staff to handle business
      growth.  Our District has expanding commitments that require
      added capability.  Adding "metrics" to communications for all
      business processes will produce better service at less cost with
      less claims and more benefit to customers and the community.
 ..
 
-   Cost savings come from proactive management to reduce
      the explosion of rework caused by new realities of formation
      overload.  Adding metrics to communication provides
      intelligence
      that expedites and aligns work with requirements to arrest cost
      and schedule growth.  This supplements RMS and strengthens Risk
      Management, as seen from cost savings.  Communication Metrics
      adds value that can prepare USACE for change in the 21st century
      by leading the way in cost reduction and effectiveness.
 ..
 
-   More experience with Communication Metrics can determine the
      best fit with organizational culture.  It could be part of a
      composite "Communications Office" that has both Public Affairs
      and Communication Metrics.  This would support Commanders and
      operational Divisions, as needed.  Alternatively, Communication
      Metrics might be a stand-alone unit.  Or, if this is too bold a
      change, it could be incorporated into Project Management, and for
      the time being used for District Operations on an ad hoc basis.
Thompson F. Keesling
Program Project Management Division
..
ATTACHMENTS
      -  Estimate Cost Savings Communication Metrics
 
 
..
 Attachment 1 - Estimate of Cost Savings Communication Metrics
Prepared by:   Thompson F. Keesling (CESPN-PM)
Dated:         October 7, 1997
1.  Purpose
    Communication on Sep 29 and Sep 4, ref a - c, resulted in a
    request by HQUSACE for an estimate of savings on the cost of
    Operations by using Communication Metrics, in order to
    evaluate potential for wider use (recommended in ref d), and
    in particular to undertake a broader test to substantiate
    these preliminary findings.
..
      Communication Metrics is in the 6% - 8% range of Supervision
    and Administration (S&A) cost for Construction Management.
    Therefore, it does not add to existing cost parameters.
    However, the expense is justified on the broader grounds of
    cost savings for District Operations, including projects.
2.  <0148- Methodology
    Savings on operations can be estimated based on the common
    value of communication for operations and projects.  In other
    words the benefit of Communication Metrics to weekly progress
    meetings, for example, would be similar for District staff
    meetings. Organizing the record and analysing alignment of
    project decisions, would be valuable for operations, as
    discussed on Sep 26, ref a.  We can therefore estimate
    operations cost savings by calculating savings on the Oakland
    Harbor project, and applying an adjusted percentage to the
    cost of operations.
..
      District Operations costs are calculated as a multiplier of
    project budgets.  This analysis dampens cost savings on
    Oakland, which has unique cost characteristics, in order to
    give a clearer picture of value from using Communication
    Metrics District-wide.
3.  ..
    b.    Project Cost Savings from Communication Metrics
        Cost Avoidance Project Claim Exposure
        Navy Sewer Line                    .4M
        Soft to Hard Polygon Change       1.0M
        Todd/Schnitzer Wing
          Contaminated Materials Claim    2.0M
                                         -----
          Total Cost Avoidance............3.4M ............... $3.4M
          See detailed estimate below.
..
          Cost Reduction (Savings) Construction Management
        ------------------------------------------------
        Cost Avoidance has a component of Cost Savings because
        Communication Metrics was applied to daily management of
        issues which led to Cost Avoidance shown above.
           Estimated Actual for 3 Months
           -----------------------------
           Navy Sewer Line                 30K
           Soft to Hard Polygon            23K
           Todd/Schnitzer                  38K
           Other issues                    30K
           Preparation/Research            26K
           Rework                         170K
                                         -----
                                          317K       317K
..
             Estimated 2 year Period
           -----------------------
           Progress Meetings             $117K
           Preparation/Research           312K
           Rework                         978K
           Litigation                     650K
                                      ---------
                                        2,057      2,057K
                                                 --------
           Total savings Constrct Mngmnt.........  2,374K       2.4
                                                              ------
        Total savings on project.............................. $5.8M
..
    c.    Communication Metrics Cost for 2 years
                 200K x 2             =   400K
        Welch made extended effort on Oakland to demonstrate
        viability of Communication Metrics.  Allow additional
        budget for normal staffing
                                          150K
                                        -------
        Total cost of savings........... $550K ................. .6M
..
    d.    ROI on Oakland Project (5.8/.6)......................... 10:1
        Return on Investment (ROI) of Communication Metrics shows
        value added from special technology and work practices
        that improve cost effectiveness.  Adding more managerial
        staff cannot substitute for Communication Metrics.  It
        would increase congestion without adding "intelligence"
        nor expertise implicit in ROI of Communication Metrics.
..
    e.    District Operations Savings
        USACE HQ's request for cost savings on Operations is
        taken to mean reduction of non-project direct costs.
        Estimate $5.8M savings on $56M adjusted project cost is
        approximately 10% savings.  Assume Oakland Harbor was
        unusual due to bankruptcy of contractor, and so savings
        may be less for typical project.
..
          Therefore, assume 6% savings on typical projects.
        Since communications is a higher percentage of District
        Operations, Communication Metrics should yield higher
        percentage of savings on District Operations costs.
        Conservative estimating considering factors in the letter
        dated Sep 26, 1997, ref a, would therefore plan on a
        comparable range of 6% savings for District Operations.
        The total District budget is approximately $65M per year.
        $15M is non-project outlay.  Savings then would be:
                   .06 x 15M      =  $900K
        Estimated cost would be       200K
..
          The record of savings on Oakland construction operations
        indicates a good chance that savings can increase by
        using Communication Metrics from the beginning of a
        project through the design phase.
..
    f.    Partnering Yields Savings under Communication Metrics
        Communication Metrics avoided potential cost of $377K on
        the Navy Sewer Line matter, described below; and it saved
        the government another $30K in direct management expense.
        This total $400K savings also enhanced the contractor's
        income potential on this scope of work under the Oakland
        project, and so accomplishes the Corps of Engineers'
        partnering policy.
4.  <0311- Detailed Estimate of Cost Savings
    This has two components:
       (a)  Cost Avoidance is speculative but substantial
            The contractor has filed $65M in claims, and may be
            entitled to some increased payment but has not yet
            substantiated the amount.  Litigation will establish
            the amount owed, either by settlement or judgement.
            The record of performance is a key factor in the
            litigation process, but not the only factor.
            Therefore, the record prepared under Communication
            Metrics contributes to cost avoidance, but the impact
            is speculative.
..
        b)    Cost Reduction reduces level of effort to accomplish
            the same or increased work, i.e., better productivity
    a.  Cost Avoidance
        Navy Sewer Line
        ---------------
        Marc McGovern, Construction Manager on Oakland, reported
        Communication Metrics identified a solution to the Navy
        Sewer Line problem, ref d Appendix A.  Over many months
        the Contractor demanded a  change order for alleged
        defects in contract drawings.  At the Progress Meeting on
        October 15, 1996, the contractor submitted a proposal:
             Extra Cost to stabilize slope per Dwgs.        $373K
..
          Analysis showed a possible basis for a changed condition,
        but Communication Metrics discovered alignment in the
        underlying record, which had been overlooked, that
        eliminated this cost. The solution enabled the contractor
        to realize improved earnings at no increase in cost to
        the Corps of Engineers.
..
          Soft to Hard Change in Material
        -------------------------------
        From approximately October 1995 to March 1996 the
        contractor filed notices of encountering hard material at
        locations where the drawings showed soft material.  A
        series of 5 RFPs were issued by the Resident Engineer.
        The contractor responded to all RFPs at once on 960730,
        seeking a total of approximately $7M extra payment.
..
          The Corps maintained that the contractor bid the same
        unit price to dredge areas shown as "hard" as it bid to
        dredge areas shown as "soft," and so requested
        justification from the Contractor for an increased unit
        price.
        A major source of communication arose over the form of
        the original RFPs which requested a lump sum price for
        work that was bid as unit price. The form of the language
        became so embroiled as to cause the cost-sharing sponsor
        to argue on behalf of the contractor's cost request,
        despite the fact that the cost-sharing sponsor regularly
        voiced opposition to the contractor's claim.
..
          Communication Metrics was begun in September 1996.
        Within a month or so it was applied to the Soft to Hard
        Polygon claim.
        Analysis showed:
           1.  Mathematical and contractual errors in the
               contractor's submission.
..
           2.    Lack of alignment between the record of samples
               taken in the field that spawned the RFPs, and the
               sweeping scope of the RFPs which converted an
               entire area from soft to hard, rather than merely
               acknowledge that an area may contain some harder
               material for which justification was needed to
               support increasing the unit price bid for
               comparable work.
..
           3.    Support for the Corps of Engineer's position that
               no increase in payment was warranted.
           4.  A strategic adjustment was needed to withdraw the
               5 original RFPs and combine them into a single RFP
               with an express requirement to submit a unit
               price.
..
                 This strategy transcended endless argument with
               the contractor about application of FAR
               regulations to the contractor's lump sum cost
               proposals for the original RFPs.
            As a consequence RFP #19 was issued in accordance
            with point 4 that focused analysis on justification
            of unit price increases relative to original bid
            pricing.
..
              Total savings is approximately $7M.  We will estimate
            savings due to the contribution of Communication
            Metrics as:
                                                         =   $1M
..
          Todd/Schnitzer Wing Contaminated Materials Claim
        ------------------------------------------------
        The contractor encountered underwater debris in an area
        of the work.  Communication Metrics aligned the record of
        conditions found in the field with the notice by the
        contractor and with contract provisions.  This supported
        a determination that a changed condition existed.  An RFP
        was crafted to enable the work to proceed.
..
          The contractor refused to perform the RFP claiming later
        events established that contaminated materials existed in
        the Todd/Schnitzer wings which required special handling.
        Due to a mix-up from not applying Communication Metrics
        RFP #20 was rescinded by the District, relieving the
        contractor from a direction to perform the work.
        Eventually, the contractor claimed $15M in extra payment
        was needed to perform debris removal estimated by the
        government to cost approximately $500K.  Communication
        Metrics tracked conflicting promises and unsubstantiated
        contentions by the contractor that it had commissioned
        tests proving contamination.  Since this matter remains
        open, for purposes of this estimate, the savings
        attributable to Communication Metrics is approximately:
                                                         =   $2M
..
    b.    Cost Savings (Reduction) on Construction Management
        Navy Sewer Line
        ---------------
        The Corps of Engineers avoided expending approximately
        160 hours (4 weeks work) in administering this matter as
        a result of using Communication Metrics for research,
        organization and analysis that revealed a win/win outcome
        for the Corps and the Contractor.  It is estimated that
        at least another 40 hours would have been expended by the
        Corps but for the solution by Communication Metrics.
                200 hours at $150/Hr                     =   $30K
..
          In fact, the contractor was claiming entitlement to
        additional payment of $500K.  Since the matter was
        resolved without the government incurring this expense
        a reasonable argument is that Communication Metrics
        avoided this additional expense to the government.  In
        the interests of clarity, this assessment of savings
        merely recognizes $30K savings in the reduction of
        COE personnel costs.
..
          Soft to Hard Change in Material
        -------------------------------
        Approximately 160 hours of Construction Management was
        saved by Communication Metrics work product that yielded
        the strategy of combining RFPs which completely changed
        the level of effort required to administer this claim.
                              150 x $150                 =   $23K
..
          Todd/Schnitzer Wing Contaminated Materials Claim
        ------------------------------------------------
        Approximately 250 hours was saved by expediting review
        among affected District and Project staff and formulating
        analysis to issue RFP #19, and further by providing
        information from the record to support understanding of
        complex environmental issues.
                              250 x $150                 =   $38K
..
          Other Issues (Mud Bucket, Weekly Planning, Schedule)
        ----------------------------------------------------
        During the short period Communication Metrics was used,
        it revealed the contractor was not performing critical
        contract requirements.  Problems that were being worked
        by Corps of Engineers staff were shown to be contractor
        responsibilities. A prominent example was a meeting on
        December 13, 1996.  The contractor presented an updated
        schedule with voluminous "backup."  Welch did not attend
        this meeting, but through interviews and documents
        Communication Metrics discovered the contractor gave
        incorrect and incomplete information at the meeting that
        initially misled the District on a critical project
        decision.
..
          For this order of magnitude estimate, rather than explain
        every matter, we estimate savings as follows:
              10 issues x 20 hours per issue
                          200 x $150                     =   $30K
..
          Progress Meetings
        -----------------
        As a result of contractor difficulties leading to major
        claims by the Contractor, the Corps of Engineers began
        staffing weekly Progress Meetings with 10 to 15 people
        from Engineering, Contracting, Construction,
        Environmental, etc.
..
          This attendance posture was intended to improve
        "communication" among affected staff whose work may have
        been impacted by various issues.  It may have been
        intended to demonstrate heightened scrutiny and concern
        by the Corps of Engineers in improving performance by the
        Contractor.
..
          Communication Metrics demonstrated this level of
        attendance was unnecessary.  Better understanding was
        achieved through the meeting notes, and it was maintained
        through the record, rather than become distorted by
        constant recall from each attendee.
..
          Follow up was more rigorous and effective using the
        Action Item system endemic to SDS that supports
        Communication Metrics. As a result Chief Con Ops was able
        to order attendance restricted to RE, PE and the
        Communication Manager. The PM attended on occasion,
        however, as  Herb Cheong's memo states, research prior to
        meetings and post meeting briefings by the Communication
        Manager ensured more thorough and productive meetings,
        ref d Appendix A.
..
          A conservative estimate of cost savings assumes avoid 5
        people for 1.5 hours per meeting for the 2 year duration
        of the job.
               5 x 1.5 x 52 x 2 = 780 hours x $150       = $117K
        The more important contribution of Communication Metrics
        is making meetings productive, as discussed below under
        re-work.
..
          Planning, Analysis, Alignment, Preparation
        ------------------------------------------
        Communication Metrics is a dedicated  "intelligence" role
        that uses technology to organize information and provide
        timely analysis for decision support.  When there is not
        enough time to add intelligence to information, "rework"
        results, as discussed below. 
..
          On Oakland, Communication Metrics reduced the time
        required for Corps of Engineers staff to prepare for
        meetings, as reported by  Herb Cheong, our Project Manager
        (see ref D Appendix A).
        Welch spent from 15 minutes to an hour to prepare for
        these meetings, then briefed Corps of Engineers' managers
        who might be leading a meeting, or otherwise need to be
        aware of key information to be developed at a meeting.
        The level of preparation would not be possible to perform
        by conventional means in even 2 hours, so we use 1 hour
        of saved time per attendee, since all attendees do not
        need the same amount of preparation at each meeting.
..
          For simplicity, 1 hour of time saved is estimated for all
        attendees, even though some were Contractor and Port of
        Oakland staff.  This reflects the general point that
        preparation and research benefits everyone, advancing
        partnering objectives; and further that this practice was
        actually performed more broadly on a daily basis, rather
        than just for weekly progress meetings.
..
          SDS diagnostics for Weekly Progress Meetings under
        "Rework" below, shows a total of 177 attendees for 15
        meetings over 3 months.  This yields for 3 months:
                        177 x 1 x $150                   =   $26K
..
          Total savings on project for 2 year job.
                  3 x 4 x 2 x 26                         =  $312K
..
          The benefit of investing time to be prepared is seen from
        the avoided cost of rework.
        Rework
        Authorities recognize "rework" to fix mistakes is a major
        cause of cost escalation that increases over time, because,
        as information becomes more complex, understanding and
        follow up to get things done degrade toward entropy, per
        study by the U.S. Air Force Institute of Technology (AFIT)
        (see "Uncertainty Analysis for Program Management" published
        by PMI, 1981).
..
        
        Cost savings from improving communication to avoid
        rework are calculated below based on analysis of information
        overload in "New World Order Needs Old Time Religion."
..
        
        The more common description of "rework" is problem handling
        through trial and error.  Costs of rework are absorbed as
        "Murphy's Law" or litigation results in cost avoidance, or
        in further cost escalation.
..
        
        This estimate for rework looks only at costs that are
        absorbed.  Litigation expense is considered separately.
..
        
        "Rework" arises from inability to attain closure on
        issues due to conflicts between decisions and reality
        that leak out through trial and error over weeks and
        months due to lack of "intelligence,"  discussed above.
..
        
        Decisions are made that seem correct at the
        moment; but, then suffer continual corrections over time
        due to lack of alignment with controlling factors, e.g.,
        facts of performance and conditions, prior commitments,
        contract provisions, policies, procedures, guidelines,
        regulations and laws. Meetings, calls and email increase,
        but understanding and progress decline.  Communication
        worsens as new players come on the scene and original
        objectives are forgotten leading to information entropy.
..
        
        Limited span of attention inherent to human mental acuity
        prevents alignment except through trial and error, called
        rework.  Span of attention is similar to span of control
        where the military recognizes that increasing the number
        of people to lead has diminishing returns.  Similarly,
        increasing the amount of information beyond human limits
        causes "information overload" that results in critical
        factors falling outside the span of attention until problems
        force them into the span of attention.
..
        
        "Feel Good" management causes rework when decisions
        seem correct, or good enough at the moment, based on
        factors within span of attention.  Managers feel that the
        time required to obtain, organize and analyse information
        to generate "intelligence," is greater than the cost of
        rework to fix mistakes due to lack of good intelligence.
..
        
        Growing complaints of not having...
                       enough time to think
        ...reflect a painful reality that information overload
        means managers do not have time to think about all of the
        factors that impact the work. Deferred "pain" of future
        adjustments is therefore traded for immediate relief from
        having to think more deeply, hunt for information to
        verify accuracy of impressions, discover that information
        is missing, obtain missing information, incur emotional
        stress and frustration seeking feedback from people who
        have limited time, fear and object to providing feedback.
        This amalgam of momentary relief from the effort required
        for good management, is summarized by the term "feel
        good" management.
..
        
        Often, however, acrimony and confrontation set in
        despite reliance on "feel good" management, because
        misunderstanding, cost and schedules grow when effective
        metrics are ignored in daily communication.  Posturing and
        belligerence permeate every communication.  Nobody feels
        good when too much rework leads to information entropy
        that causes cost growth and project failure.
..
        
        Communication Metrics reduces rework in two ways:
           1-  It expands span of attention by proactively
               aligning understandings, and therefore decisions
               and actions with a broader spectrum of controlling
               factors, including authority, than is possible by
               conventional means.
..
               
               Proactive alignment avoids the steady drip, drip
               of new and unforeseen correlations, as decisions
               and conduct gradually encounter the ultimate
               metric of reality that otherwise prevents closure
               under conventional practice of trial and error,
               guess and gossip, hunch and hope.
..
               
               Communication Metrics uses SDS technology to
               discover greater nuance and more correlations
               (i.e., intelligence) than are evident under normal
               limited span of attention.  The result is
               proactive management rather than trial and error
               problem handling.
..
               
               Communication Metrics provides three types of
               alignment that support organization and analysis
               to produce "intelligence" that saves time and money:
                  a-  Subjects
                      These are categories or classifications of
                      information, matters and issues requiring
                      common treatment.  Examples are meeting
                      agendas, file descriptions, groupings of
                      documents on a desk according to common
                      meaning, application etc.
..
                      
                  b-  Links
                      Specialized technology makes it fast and
                      easy link related events, analysis, and
                      controlling authorities called "original
                      sources," that produce a web of connected
                      "knowledge."
..
                      
                  c-  Feedback
                      The organization, links and analysis in
                      Communication Metrics, give managers early
                      notice of adjustments in communication and
                      decisions to avoid delays and extra cost.
                      Deliverying intelligence via Internet and
                      in a summary format linked to details,
                      enables feedback to be accomplished with
                      minimal time.
..
               
           2-  Action Items (cited by Herb Cheong, in his
                memo on Apr 7, 1997) are scheduled to maintain
               visibility by linking to original reasoning and
               factual history, so that needed action is not
               forgotten by the passage of time, high information
               flows, nor by the arrival of new tasks and new
               players.  This correlation (integration) between
               time and information (schedule and diary)
               overcomes the growing risk of complexity in the
               business environment due to the limited span of
               attention.
..
        
        On Oakland, there are approximately 11 key players:
                                                      Hrs/Week
                                                  Planned    Actual
           Project Engineer                           40       45
           Inspector Supervisors                      80       90
           Inspectors AE                             240      250
           Resident Engineer                           5       20
           Construction Manager                       10       22
           Chief Construction Operations               2        6
           Asst. Chief Con Ops                         4       15
           Project Manager                             5       12
           Design Engineer                             5       10
           Chief Planning/Engineering                  2        5
           Contract Officer                            3       10
           Contract Specialist                         2        5
           Environmental Engineer                      2        5
                                                    -----    -----
               Total hours per week................. 396      495
..
        
        Actual time to manage the work is 25% above budgeted
        time, but for District staff the investment is 200% - 300%
        greater that budgeted time, which causes significant
        reduced attention to other matters, snow-balling reduced
        effectiveness on everything.
..
        
        Increased time for rework to fix mistakes, caused by
        information overload, reduces the time to prepare for
        meetings, which makes communication ineffective due to
        cursory understanding and over reliance on conversation,
        called "guess and gossip" in the District's Communication
        Metrics  report published on March 28, 1997, ref d.
..
        
        The amount of time lost due to rework can be calculated
        from the difference between the typical agenda prepared
        for meetings which reflects subjects that are recognized
        as material to performance, and the actual number of
        subjects tracked by Communication Metrics.  A second
        factor is the number of links (citations) that align
        understandings in the record, since this represents the
        potential for conflicts that require correction.
..
        
        The agenda prepared by the Corps for the Oct 1, 1996
        Progress Meeting had 10 items.  This is a typical agenda
        for weekly progress meetings.  Most meetings average from
        6 - 12 subjects.
..
        
        Communication Metrics actually tracked the following
        factors at weekly progress meetings:
            SDS Diagnostics Progress Meetings
            ---------------------------------
                          Partici-        Sub-  Cita-  Action
            Date   Time    pants  Words   jects tions  Items
            961001 1000      19    1125    40     10      7
            961009 1300      19    1861    47     29      9
            961015 1000      15    2193    61     32      7
            961022 1000      21    2974    57     24      7
            961029 1000      15    2898    60     44     12
            961105 1000      14    3671    65     36     11
            961112 1000      14    4553    56     91     16
            961119 1000      13    4377    48     93      4
            961126 1000      12    2811    39     59     11
            961203 1000      11    1416    27     30      2
            961209 1330       4    3162    31     69     14
            961219 1000       4    2521    28     48      9
            961230 1330       4    1956    32     37      6
            970106 1200       6    2626     6     32     15
            970106 1400       6    1753    22     27      6
                           -----         -----  -----   ----
                            177           619    661    136
..
        
        Since, as noted, common practice identifies about 10
        subjects per meeting, then for these 15 meetings, a total
        of 150 subjects would have been worked.
..
        
        Communication Metrics identified 619 or 469 more subjects
        for these particular meetings, approximately 400% more.
..
        
        This reflects added value of proactive management
        identifying correlations and implications to avoid rework
        on 469 subjects that would otherwise have been discovered
        by trial and error problem handling over weeks and
        months.  Increasing from 150 to 619 subjects is a
        significant increase in management span of attention
        uniquely possible under Communication Metrics.
..
        
        Citations should be added to this amount because they
        reflect alignment which is impossible under conventional
        management due to limited span of attention, and so
        otherwise leads directly to rework.
                     Additional Subjects     469
                     Citations (alignment)   661
                                            -----
                                            1130
               Note:  this is a conservative valuation since it
               ignores the difference between the number of
               action items people are able to recognize and
               those tracked by Communication Metrics.  It is
               likely in the range of 2:1 or 3:1.  The analysis
               also ignores additional subjects and linkages
               tracked by Communication Metrics from other
               meetings, discussions, calls and documents,
               including email.  In less formal communications,
               people generally recognize 2 or 3 subjects and a
               similar number of action items.  Like formal
               events, no one has time to link understandings
               from less formal communications to original
               sources.  These factors increase the potential of
               Communication Metrics to save the cost of rework
               by overcoming limits on span of attention.
..
        
        Assume each missed alignment results in one (1) hour of
        rework by a Corps of Engineer manager.  Therefore,
        Communication Metrics produced savings of:
                     1130 x 1 x $150                     =  $170K
..
        
        Total savings on project for 2 year job.
                  3 x 4 x 2 x 170 - 170 = $3,910K
        Assume normal bell curve and that period when
        Communication Metrics was applied was at or near peak
        activity on the project, so that actual savings is only
        25% of peak rate.
                       .25 x 3910                        =  $978K
..
        
        Where was this money expended by the Corps?
        Average savings per week over 3 months
                            $170/12 = $14K
..
        
        The weekly savings from Communication Metrics correlates
        with increased expense for Corps of Engineers' District
        staff who were forced into performing "problem handling"
        that escalated into a constant daily grind of putting out
        fires that developed on Oakland.
..
        
        Planned - Actual operations hours is 495 - 396 = 99
                          99 x $150 = $15K
        A major advantage of Communication Metrics, in addition
        to avoiding increased District staff time, so it can
        perform normal duties, is that Communication Metrics
        produces a record that is constant.  It can be used
        repeatedly without decay of understandings due to time,
        and distortion of reality when "too many cooks" get
        embroiled in the "kitchen."  This avoids the problem of
        congestion, and produces a record that supports dispute
        resolution, including litigation, if necessary.
..
        
        Litigation
        ----------
        Jim Stout, former member of District counsel staff, who
        specialized in contracts, examined Communication Metrics
        work product on the Oakland Harbor project.  In a meeting
        on October 15, 1996, Jim advised the Contracting Officer,
        Tom Benero, that the methodology of providing context and
        alignment with requirements and prior events and
        commitments is helpful to the District, and should be
        continued for the duration of the Oakland project to
        assist in resolving disputes.
..
        
        Communication Metrics was ended OA December 31, 1996.
        The Contractor filed for Chapter 11 Bankruptcy at about
        the same time.  Contractor claims have since been filed
        in a total amount of about $65M.  District counsel have
        requested support from Communication Metrics for the
        reasons cited by Jim Stout, who has since retired.
..
        
        Communication Metrics is intended to avoid disputes and
        litigation by using Concurrent Discovery to accomplish
        win/win results for the Corps of Engineers and for the
        Contractor, as was done on the Navy Sewer Line matter.
        Such outcomes advance our partnering policy objectives,
        and our project management goals for cost reduction.
..
        
        Of course situations arise, where, for example, a
        contractor in severe financial difficulty may find it
        useful to present unfounded claims in hopes of salvaging
        its existence. This observation makes no reference to the
        Dutra situation per se.  As well, legitimate differences
        in the application of contract provisions and the law may
        require determination by a neutral, and this is essential
        to a vital procurement program.
..
        
        Where litigation cannot be avoided, the record produced
        by Communication Metrics is essentially court-room ready
        evidence. This saves the Corps of Engineers significant
        legal expense, as found by Jim Stout.
..
        
        Currently, the District has two full time lawyers working
        on the Oakland project, and approximately 6 claims
        management staff.  I estimate that by virtue of enhanced
        organization, faster information handling and retrieval,
        Communication Metrics would, if used for Construction
        Management (see expense para 3c) permit reduction of
        one-half lawyer and 2 claims management staff.  Assuming
        this savings accrues for 10 months, which seems likely
        based on current progress, the total savings would be;
                 2.5 x 40 x 52 x 10/12 x $150            =  $650K
..
        
        Saving $650K of direct expense is of course not the big
        prize.  The interest of the Corps is to ensure that it
        avoids paying more than is equitable to the contractor.
        We have identified above some specific issues claimed by
        the contractor which appear at this time will result in
        cost avoidance, or savings, of approximately $3M
        attributable directly to Communication Metrics.  This
        savings comes at a cost of under $50K which produced other
        benefits and direct savings, as shown in para 3b, above.
        The most notable example is $500K claimed on the Navy Sewer
        Line that was resovled by Communication Metrics without
        requiring extra payment to the contractor.
..
        
        Since Contractor's claims have escalated, Communication
        Metrics should realize a much larger savings, or cost
        avoidance, if applied for litigation support of current
        exposure. The amount is not clear enough at this time to
        form a judgement and so renders any such estimate too
        speculative for evaluating Communication Metrics.