DIARY: October 7, 1998 07:23 AM Wednesday; Rod Welch

Review Gensler memos to KH on Moscone III re 50% CD schedule.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 

SUBJECTS
JV Coordination Meeting, 980929
Document Logs
WBS
Management Plan
Work Plans

0807 -    ..
0808 - Summary/Objective
0809 -
080901 - Follow up ref SDS 14 0000, ref SDS 12 0000.
080902 -
080903 - Now that I have documents, received last night, ref SDS 14 2574,
080904 - worked entire day analysing Clonia's memo on 980922, ref DRP 2 8492,
080905 - for application to JV coordination meeting on 980929. ref SDS 6 3099
080906 -
080907 - Clonia asked at the meeting on 980929 for status on her memos.  This
080908 - enables KH to review each item and track performance in the record
080909 - going forward.  The memo also provide a structure for organizing
080910 - meetings.
080911 -
080912 -    The memo has about 20 action items.
080913 -
080914 - Began analysis of Clonia's memo on 980917. ref DRP 1 8492
080915 -
080916 - This analysis enables KH to develop work plans based on schedule
080917 - objectives for accomplishing action items cited by Gensler.  The only
080918 - problem is there is no CPM schedule to permit allocation of float. see
080919 - ref SDS 6 6020
080920 -
080921 - It supports proposals to formulate stronger Project Management plan
080922 - and procedures, so that KH can do its work.