- None of the items above have yet been resolved
- The lack of reflected ceiling plans is affecting all the MEP
consultants's work. Robert is still working on this issue... I have,
and our structural consultants have previously indicated to Robert
that they require a two way beam system where the hang points are
located. As of this morning this question was again asked of the
structural engineers. No progress on the reflective ceilings for the
second and third floor. We are in our third week of this study where
basic criteria problems are not addressed. Where are we going from
here? I believe it is our team's common goal to minimize the
construction cost impact wherever possible. Therefore I have
specifically asked that the floor framing (SDE's electronic file) be
used when laying out the reflected ceiling plans. The framing plans
indicate east/ west bracing at 22'0oc, this means that there is
already a beam at the bottom cord of the truss elevation that can be
used for hang point supports. I have asked Robert to use 11'3'
dimension in the east / west direction in order to minimize the
amount of steel needed to only support the hang points. Minimize, not
maximize the amount of miscellaneous support steel required!!!!
[On 980929 entered in
JV Coordination meeting.]
- The size of the column jacket ( precast concrete) is an obvious
starting point for the movable wall layout. As disscussed before we
need clearance between the column jacket and the movable wall
location . 1'0"from the column to the center line of the movable wall
is a minimum dimension. The partitions are 4" thick.. Interior Column
detail: this affects the layout of the ceiling. It needs to be
resolved before the ceiling soffits/ layouts are addressed. I believe
you sent the detail to your office. Is there an answer? Is this
holding up the ceiling?
[On 980929 entered in
JV Coordination meeting.]
- The edge of the gypsum board soffit as it relates to the movable
wall truck is another determining factor in the ceiling soffit/
acoustical suspended ceiling layout.. A zero dimension from the edge
of the track cover to the edge of gypsum board soffit is not a
desirable nor an acceptable dimension. Asking our mechanical
consultants to reduce the size of the 16" round duct that connects
the diffuser to a 12'" round increases the number of diffusers to
approximately 40 in lieu of 30 as indicated. This is also not
acceptable. So, where do we go from here? Can you have somebody else
look at the ceilings?
[On 980929 entered in
JV Coordination meeting.]
- I have asked your team to provide a sketch for the sky fold partition at
the third floor at F line. We reviewed a Sketch that Robert started,
however it needed work. Where is the solution? Does it work? Do we have
the clearances?
[On 980929 entered in
JV Coordination meeting.]
- Access to mechanical rooms is not yet resolved. There are
problems with all the stairs to the west mechanical mezzanine. This
affects the mechanical consultant's work.
[On 980929 entered in
JV Coordination meeting.]
- Access to elevator equipment rooms 5,6 and 7,8 is not yet
resolved. In talking with Al Williams it appears that a hatch from
the mechanical penthouse to the elevator machine room is not
possible. 60 degree slope ship ladder is the minimum Elevator code
acceptable. We need a sketch for tomorrow's meeting with Al Williams.
[On 980929 entered in
JV Coordination meeting.]
- I marked up your elevator 5 & 6 section . The elevator pit may infringe
into the headroom if the bus ducts are indicated. Pit construction is
concrete, similar to floor boxes construction indicated on the structural
drawings..
[On 980929 entered in
JV Coordination meeting.]
- Access to roof mechanical penthouse is not yet resolved. This affects the
fire protection, mechanical consultant' s work..
[On 980929 entered in
JV Coordination meeting.]
- I have asked your team to address the fire damper enclosure at column
line B and F. No dimensional and detail/section yet started. This may
be a big problem. It may affect the ceiling. I provided you with a copy
of the same detail I previously gave Robert.
[On 980929 entered in
JV Coordination meeting.]
- Door frames, partition locations. Partition, especially where we indicate
a 5' 0" wide wall need to be revised. We do not want to waste any floor
space. We should look at all locations where bracing does not occur and
revise the thicknesse of walls. Just because it is easy to maintain a
strait drafting line it is not necessarily an acceptable solution.
Indicate furring walls where they occur (basement, against the concrete
block walls, etc)
[On 980929 entered in
JV Coordination meeting.]
- I started red marking the 25% package. As we agreed on Monday,
the package is nowhere close to 25% complete. My red marks are
available for your review. There are quite a few mark ups!!! Some of
the mark ups are old and not yet picked up. The " automatic" plotting
routine together with the layer control is not yet accomplished.
[On 980929 entered in
JV Coordination meeting.]
- Restroom layouts. As of yesterday the ratio of water closets to
lavatories is not yet resolved. I have not seen any new layouts. This
is needed by our consultants. They are using old backgrounds for
their layouts. This is a critical item. Floor slopes drawings need to
be started. This information is needed by the plumbing engineer.
[On 980929 entered in
JV Coordination meeting.]
- Coordination with plumbing raisers, fire protection risers. The
25% plumbing and fire protection drawings contain the riser
information. This information has not much chanced from the DD set,
however is not yet coordinated. Our drawings must acknowledge major
risers in our partition plans (plumbing chase walls, etc) If
something does not fit, please mark it up and advise the mechanical
consultant that it needs to me relocated.
[On 980929 entered in
JV Coordination meeting.]
- Issue of wall thickness. The interior partitions are indicated
as various sizes, although the span and rating is the same. This
needs to be re done for all floors. This item is especially critical
at stairs and building perimeter. We have previously indicated to
your team that the exit stairs do not receive any finished dry wall.
Your drawings have not been corrected yet, sections not started,
therefore we do not know if there are any potential problems.
[On 980929 entered in
JV Coordination meeting.]
- Exit stairs. All ADA issues need to be addressed. Provide
railings at Fire Department valves. (ADA issue)
[On 980929 entered in
JV Coordination meeting.]
- We do not seem to make much progress on any items.
[On 980929 entered in
JV Coordination meeting.]
- No details added to package
[On 980929 entered in
JV Coordination meeting.]
- No coordination with various disciplines (red marking of the DD
package not yet done, red marking of the 25% package not yet started)
[On 980929 entered in
JV Coordination meeting.]
- Interior section / elevations/ details/ not yet started
[On 980929 entered in
JV Coordination meeting.]
- There are a list of major items, but there is no senior person
that appears to be able to start developing details for this project
[On 980929 entered in
JV Coordination meeting.]
- I asked that the pre function ceiling drawing drafted (CADD drawings) by
Peter be further developed to indicate sprinklers (spacing as per memo I
gave you previously), speakers (see DD package). This affects both AV and
Fire protection consultant. We have provided the ceiling layout,
contacted the manufacturer, received information on detailing, however
there is nobody on your team assigned to this effort of coordination/
detail development.
[On 980929 entered in
JV Coordination meeting.]
- I asked Bolivar today to start on the Ground floor ceiling
revision. Indicate floor support structure ( use SDE's electronic
file) add the fixture clusters I previously gave you at 30' oc , add
AV speaker layout as indicated on the DD drawings. ) We need to get
this going.
[On 980929 entered in
JV Coordination meeting.]
- Kitchen drawings. At DD phase your team copied the partition
layouts from the kitchen consultant backgrounds. Did your office do
an ADA check? We now need to make sure that the layouts are code
compliant not only equipment compliant. Revise wall thicknesses, door
clearances, etc. Coordinationdinate with plumbing drawings, see if any
modifications need to be made to the layouts. Coordinationdinate with all
details provided already in the DD package by the kitchen
consultant. Freezer slab, refrigerator door details, hood detail,
grease duct details. The kitchen section I originally marked up at
the DD phase has not yet been touched. Floor slopes not indicated. No
details to date. If any modifications are needed to the layouts it
may drastically affect the food service consultant. We want to
eliminate their request for additional fees due to our lack of
coordination.
[On 980929 entered in
JV Coordination meeting.]
- Steven H. and I have done most of the coordination with our MEPS
consultants. We do expect your team to fully participate in the
coordination as part of your office responsibilities. Please
instruct your team to fax (copy to us) questions, not only telephone
conversations with no telephone record copied to us. Your presence at
coordination meetings is important. Shared meeting notes
responsibilities between you and Steven I believe is recommended.
[On 980929 entered in
JV Coordination meeting.]
- It seems to me that since you do not have any senior help from
your team you can not address the coordination, red marking of your
team work and the consultant work as well.
[On 980929 entered in
JV Coordination meeting.]
- It is also apparent that without a minimum of two senior people,
in addition to yourself, that can work independently (work out all
details, coordinate with consultants on specific questions) we can
not complete our drawings. Starting somebody new on this complicated
project may take approximately two weeks to come up to speed with
this work. Time is of the essence.
[On 980929 entered in
JV Coordination meeting.]
- This 25% set is not something we can present to our client and
expect to be paid for it!!!! If any thing the drawings are not at the
level of Design Development yet. Are you planning to at list work
overtime? None of your team members seam to stay late. Again, I
believe that an extra effort if absolutely needed by your office. It
is very scary to think abiout our deadline when looking at the 25%
set of drawings
[On 980929 entered in
JV Coordination meeting.]