DIARY: January 28, 1997 08:15 AM Tuesday; Rod Welch

Meet with Marc McGovern re status of Oakland Harbor project.

1...Summary/Objective
2...Marc said he has not had enough time to prepare a procurement
3...Dutra Filed Chapter 11
4...Rain Delays Recognized, Dutra Nearly on Schedule
5...Meeting Not Yet Set


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Marc McGovern; Construction Manager =415 977 8467
020102 - Construction Operations Division   =415 977 8480
0202 - Corps of Engineers, SFD            415 977 8400 fax 8483
020201 - Mr. Max R. Blodgett, II, P.E., L.S.
020202 - Construction Operations Division   =415 977 8480

SUBJECTS
Increase Budget, Port of Oakland
COE Staffing
Port of Richmond
Not Enough Time for Conventional Management
New World Order
Not Enough Time for CBD Procurement

1208 -    ..
1209 - Summary/Objective
1210 -
121001 - Follow up ref SDS 22 0000, ref SDS 21 0000.
121002 -
121003 - Tom Keesling has not returned from vacation.  Rose said he is now
121004 - expected back on Thursday.
121005 - ..
121006 - Talked to Marc McGovern about progress on the Welch scope of
121007 - services. He said that Tom Benero told him yesterday that he cannot
121008 - hire Welch nor Jim Stout.  Marc recalled Tom indicating that CON OPS
121009 - and the Engineering Division should have sufficient resources between
121010 - them to manage the Dutra contract.
121011 -
121012 -     [See follow up at ref SDS 29 line 159, and ref SDS 31 line 100.]
121013 - ..
121014 - Marc said he has not had enough time to prepare a procurement
121015 - for the Welch scope of services, ref DIP 13 line 27, submitted at ref
121016 - SDS 26 line 92, similar to meeting on 970110, ref SDS 24 line 691.
121017 -
121018 -     [See similar concern on 970722, ref SDS 32 line 508.]
121019 -
121020 - There was no discussion of using Communication Metrics on the Port of
121021 - Richmond project.
121022 -
121023 -
121024 -
1211 -

SUBJECTS
Cure Notice
Shoaling
Spreadsheet Analysis
0020   Combine RFPs 9-11 and 960312 letter

1607 -
160701 - Dutra Filed Chapter 11
160702 -
160703 - When I arrived, Marc was speaking with Rick Oleniczak with G&B about
160704 - getting support for making payments to Dutra.  Marc confirmed that
160705 - Dutra has filed Chapter 11 protection.  Payments are being paid into
160706 - an escrow account for distribution.  There was a meeting yesterday
160707 - with Dutra and its bonding company.
160708 -
160709 - Marc advised that there will be another meeting within the next few
160710 - days or week, to determine what matters COE can agree to pay Dutra
160711 - additional funds for "changed" work, such as soft to hard polygon
160712 - matter, RFP #20.
160713 -
160714 - When I spoke to Marc after his lengthy discussion with Rick, he
160715 - advised that G&B has not completed the analysis of shoaling on time
160716 - extensions due the contractor.  We considered the advantage of having
160717 - G&B do this.
160718 -
160719 - Marc feels COE must negotiate with Dutra based on its recent response
160720 - to RFP #20 that fails to provide unit prices, as required by the RFP,
160721 - per ref DIP 1 line 91, issued at, ref SDS 2 line 247.  He intends to
160722 - discuss with Tom Keesling, when he returns, the COE position developed
160723 - previously.
160724 -
160725 -
160726 -
160727 -
1608 -

SUBJECTS
Schedule for Construction, 52.236-15
Schedule

1805 -
180501 - Rain Delays Recognized, Dutra Nearly on Schedule
180502 -
180503 - Marc advised that COE has indicated it will recognize rain delays in
180504 - Dutra's schedule to complete the Outer Harbor by 970315, and with
180505 - these added days, Dutra is nearly on schedule.  They have evidently
180506 - not returned the Paula Lee to the job site.
180507 -
180508 -
180509 -
1806 -

SUBJECTS
Sewer Line Installation

1904 -
190401 -  ..
190402 - Meeting Not Yet Set
190403 -
190404 - Marc said Kevin Eherinreich at UPRR is supposed to call him later
190405 - today about a meeting on the NSL.  Marc said that Kevin indicates that
190406 - UPRR will not approve the Open Cut method, citing resistance by Joel
190407 - Adams on the grounds that they cannot get sufficient time from train
190408 - traffic to use this method.
190409 -
190410 -    [On 970406 UPRR endorses Open Cut solution. ref SDS 30 9705]
190411 -
190412 -
190413 -
Distribution. . . . See "CONTACTS"