S U M M A R Y


DIARY: December 8, 1994 10:00 AM Thursday; Rod Welch

Progress meeting with CDWR on Coastal Branch Transmission Line.

1...Summary/Objective
2...Follow Up
3...Oct 5, 1994 Meeting
4...Pipeline Construction
.....Comment: Need Quantities & Dates
5...Distribution Contract
6...PG&E Site Visit
7...PG&E's Schedule Reflects CDWR Planning and Objectives
.....Interface with CDWR Work
.....Changes
..........SLO Changes
.....Schedule Notes
.....Completion Targets
..........Meeting in January
.....Summary Schedule
.....Estimate of Pipeline Progress
8...Valve System Power
.....Solutions
9...Access of Delivery Trucks
10...Environmental Training


..............
Click here to comment!

CONTACTS 
0201 - CDWR, Div Op. & Maint.             Telephone;   fax or 800...
020101 - Ms. Lori Brown, E.E.
020102 - Project Manager PG&E Contract, Coastal Branch, Phase II =916 653 9849
020103 - Power Contracts   =916 653 9295 fax
020104 - Mr. Dan Herdocia; =916 653 9677; Power Contracts   =916 653 9295 fax
020105 - Mr. Ed Hills; =916 653 8374; Planning Division
020106 - Mr. Bob Goad; =916 653 8136; Electrical Design
020107 - Mr. Om Lakhotia; =916 653 3313; Electrical Design
020108 - Mr. Bob McDougall; =916 653 8316; Electrical Design
020109 - Mr. Rajendra Dave; Associate Electrical Engineer =916 653 6712
020110 - Electrical Design
020111 - Mr. Gerry Weldon; Cadastral Surveys =916 657 5224
020112 - Land & Right of Way Division
020113 - Ms. Linda Lundblad; Right of Way Agent =916 653 8523
020114 - Land & Right of Way Division
020115 - Mr. Richard Latteri; Chief of Power Allocation Section =916 653 1087
020116 - O & M Comm Br
020117 - Mr. Roman Dalton; =805 858 2211; O & M Comm Br
020118 - Mr. Don Tribble; =916 653 1292; Plant Operations
020119 - Mr. Richard Oravetz; Associate Engineer =916 653 1310; Plant Operations
020120 - Ms. Wilma Ordiz; =916 653 8830 fax 0855; Telecom
0202 - Pacific Gas & Electric Company     415 973 6778 fax 8426
020201 - Mr. Bill DeHart, PMP
020202 - Senior Project Manager, Room 1183B-V11C =415 973 5655; Transmissions Systems
020203 - Mr. Tom Marki; Project Manager, Room 1169B-V11C =415 973 nnnn
020204 - Project Management Group
020205 - Mr. Demetrius J. Pedruco; Project Analyst, Room 1169B-V11C =415 973 6388
020206 - Project Management Group
0203 - PG&E Transm Sys Contracts          415 973 3872 fax 972 0871
020301 - Mr. Kevin Coffee, E.E.
020302 - Contract Manager, Rm 2334 Mail Code B23A =415 973 3872
020303 - Mr. Quincy Dong
020304 - Contract Manager, Rm 2334 Mail Code B23A =415 973 1660
020305 - Transmission Contracts =415 972 0871 (fax)
0204 - PG&E Trans Sys Engineering         415 973 3877 fax 9209
020401 - Mr. Jivat Gidvani, E.E.; Engineer; Rm 580, Mail Code F5C =415 973 3877
0205 - PG&E Building & Land Svcs.         415 223 8273 fax or 800...
020501 - Mr. Robert Masuoka; Room 2027, Mail Code H21A =415 223 8273
0206 - PG&E Fresno Office                 209 821 5000 fax or 800...
020601 - Mr. Michael D. Grinstead; =209 821 5247 or 263 5247
020602 - Building & Land Services    =Telephone/fax
020603 - Mr. Jeff Little; =209 821 5241 or 263 5241
020604 - Reg Land Department    =Telephone/fax
0207 - The Welch Company                  415 781 5700
020701 - Mr. Rod Welch

SUBJECTS
Central Coast Aqueduct, PG&E
Meetings: 941208 Sacramento with CDWR
Introductions
Evaluation PG&E Contract Performance

0706 -    ..
0707 - Summary/Objective
0708 -
070801 - Follow up ref SDS 2 0000.
070802 -
070803 - The meeting today indicated that if Right-of-Way and GO 131-D tasks
070804 - progress as planned, then PG&E can begin construction as scheduled on
070805 - Feb 3, 1994 for Arco - Devils Den transmission line.  CDWR will direct
070806 - the pipeline contractor to submit a plan for removing spoil along the
070807 - Transmission line route, so PG&E can commence work on or about April
070808 - 4, 1995 from Devils Den toward Polonio Pass.  Further planning to
070809 - define scope, tasks, cost and schedule for energizing and testing will
070810 - be carried out in January, 1995 with Lonnie Essig.  Schedule changes
070811 - to SLO Hydro interconnection will require additional coordination.
070812 - ..
070813 - Bill DeHart introduced PG&E's new Project Manager, Tom Marki,
070814 - and Project Analyst, Tito Pedruco.  Tom explained his background in
070815 - the PG&E Land Department.
070816 - ..
070817 - Lori Brown expressed appreciation on behalf of CDWR for Bill's
070818 - management of the project, and wished him well in retirement.
070819 -
070820 -      [...in another record after the meeting today, Lori asked about
070821 -      continuing SDS support. ref SDS 11 8841
070822 -
070823 -
070824 - Follow Up
070825 -
070826 -   1.  Project design, schedule, and other parameters need to be
070827 -       worked out to support CDWR's decision to defer SLO Hydro Power
070828 -       plant, and in its place install a valve control system.  PG&E
070829 -       will comment on alternative means to provide power to the
070830 -       valve control system.
070831 -       ..
070832 -   2.  CDWR will comment on PG&E Schedule Notes.
070833 -
070834 -   3.  PG&E and CDWR will meet in January 1995 to begin defining PG&E
070835 -       completion relative to contract targets for PG&E and CDWR
070836 -       objectives on energizing its facilities.
070837 -
070838 -   4.  CDWR submit quantities from most recent Pay Estimate showing
070839 -       actual pipeline progress, plus clarifications to assist PG&E in
070840 -       preparing for meeting under Action Item #3.
070841 -
070842 -   5.  PG&E will submit a letter to CDWR on restoring final grades
070843 -       along the transmission line route, so PG&E can perform its
070844 -       work.
070845 -
070846 -   6.  PG&E will brief Tom Olson on installation of the 70 kV breaker
070847 -       and Bus Extension.
070848 -       ..
070849 -   7.  CDWR will provide easements so PG&E can commence
070850 -       construction of the Transmission Line on Feb 3, 1994.
070851 -
070852 -   8.  CDWR will submit "clean" copies of the EIR to support PG&E's
070853 -       GO 131-D public notice program.
070854 -
070855 -   9.  CDWR will submit comments within 3 days of receipt of any
070856 -       comments from public review of the EIR.
070857 -
070858 -  10.  CDWR will furnish to PG&E the amended opinion from Fish & Game
070859 -       that approves construction of the transmission line.
070860 -
070861 -  11.  CDWR will provide environmental training for PG&E's
070862 -       construction crews in advance of starting construction on Feb
070863 -       3, 1995.
070864 -
070865 -
0709 -

SUBJECTS
Central Coast Aqueduct, PG&E
Meetings: 941005 Sacramento with CDWR
Review Pending Action Items

1006 -
100601 -  ..
100602 - Oct 5, 1994 Meeting
100603 -
100604 - The record shows CDWR and PG&E have made progress on Action Items from
100605 - the Oct 5 meeting (listed in PG&E letter submitted to CDWR on Oct 31,
100606 - ref DIP 3 line 30, per ref SDS 10 line 47, as explained below.
100607 -
100608 -
100609 -
100610 -
1007 -

SUBJECTS
Project Status, CDWR
Interface PG&E with CDWR Activities
Plants Complete, Operational, CDWR Task #9
Pipeline Reach No. 1, by CDWR

1607 -
160701 - Ed Hills explained the status of various components.
160702 -
160703 -    Devils Den pumping plant - most of the intake channel has been
160704 -    placed.
160705 -
160706 -       Coastal Branch, Phase I has been dewatered.  The tie-in to
160707 -       Phase I is scheduled to be complete by 941215.
160708 -
160709 -    No report on Bluestone nor Polonio Pass.
160710 -
160711 -
160712 -  ..
160713 - Pipeline Construction
160714 -
160715 - Pipeline Reach 1, the contractor is preparing to cross Keck's Road
160716 - and head West.
160717 -
160718 - Pipeline Reach 2, pipe stringing and welding have begun;
160719 - backfilling has not yet started.
160720 -
160721 - Cuesta tunnel, shotcrete work continues from the south portal.
160722 -
160723 -      ..
160724 -     Comment:  Need Quantities & Dates
160725 -
160726 -     Progress constructing the pipeline can be guaged from the con-
160727 -     tractor's monthly pay estimate, compared to his Schedule, in order
160728 -     to estimate the impact on PG&E's schedule to construct the trans-
160729 -     mission line.
160730 -
160731 -
160732 - Distribution Contract
160733 -
160734 - At Tank 1 site (pertaining to the PG&E Distribution work), walls of
160735 - two raw water tanks are complete and about half the wall of the
160736 - third.
160737 -
160738 -
160739 -
160740 -  ..
160741 - PG&E Site Visit
160742 -
160743 - Bill DeHart reported on visiting the project yesterday with Tom Marki,
160744 - ref SDS 10 line 32.  A 5 foot lift of some foundation walls has been
160745 - poured on Polonio Pass pumping plant. The foundation has been poured
160746 - on Devils Den, and the manifold pipe is in place.  Work appears to be
160747 - underway setting wall forms, consistent with Randy McBride's report
160748 - that the contractor is using a single set of forms for all three
160749 - plants (see notes of site visit Nov 15, ref SDS 6 line 129). There
160750 - was no work underway at Bluestone.
160751 -
160752 -
160753 -
1608 -

SUBJECTS
Delays, SLO Hydro Interconnection
Switchyard, CDWR task #24
Meters by CDWR
Obtain Lease Lines, by CDWR
CDWR & PG&E plan change in SLO Hydro work

2308 -
230801 - Lori Brown advised that CDWR is delaying construction of the Hydro
230802 - plant.  They will construct the pipeline and provide temporary valves
230803 - at the Hydro plant location, so water can be delivered according to
230804 - the current schedule.  CDWR plans to build the switchyard, and may
230805 - need power to operate the temporary valves.  [See below "Valve System
230806 - Power".]
230807 -
230808 - Consideration is needed on following:
230809 -
230810 -    a.  Scheduling tasks on engineering and Cost/Schedule impact.
230811 -
230812 -    b.  Line Protection for the Tie Line currently planned to be
230813 -        provided by a transfer trip and telephone communication
230814 -        system.
230815 -        ..
230816 -    c.  Metering to be installed by CDWR.
230817 -
230818 -        Where will the meters be constructed, or what alternative
230819 -        means can be used?
230820 -
230821 -
230822 -
2309 -
2310 -

SUBJECTS
PG&E Schedule Report to CDWR, 941207p.mpp
Energize & Test

3405 -
340501 -  ..
340502 - PG&E's Schedule Reflects CDWR Planning and Objectives
340503 -
340504 - Bill DeHart submitted PG&E's schedule dated Dec 7, 1994, ref OF 2.
340505 - Copies were distributed to attendees during the meeting to support
340506 - discussion.
340507 -
340508 - This Schedule updates the Oct 6 Schedule, ref OF 1, submitted to CDWR
340509 - on Oct 13, 1994 via ref DIP 2 line 30, and discussed with Lori Brown
340510 - at ref SDS 3 line 85.  The Oct 6 schedule applied issues discussed at
340511 - the Oct 5 Progress meeting, ref SDS 2 line 286.
340512 -
340513 -
340514 -      ..
340515 -     Interface with CDWR Work
340516 -
340517 -     PG&E continues to follow CDWR's instruction to schedule PG&E's
340518 -     work independent from progress on the pipeline and plant projects,
340519 -     per ref SDS 1 line 158.
340520 -
340521 -
340522 -     Changes
340523 -
340524 -     The only major change in the schedule is a breakdown of steps
340525 -     needed to implement GO 131-D regulations (explained by Bob Masuoka
340526 -     below).  There is a separate sequence for each main project phase:
340527 -     Arco Sub - Polonio Pass; SLO Hydro; Casmalia Hills.
340528 -
340529 -           ..
340530 -          SLO Changes
340531 -
340532 -          Lori noted that PG&E should continue to schedule completion
340533 -          of its work independent of the changes announced today with
340534 -          respect to delayed construction of the SLO Hydro plant, as
340535 -          discussed at the Oct 5 meeting, ref SDS 2 line 275.
340536 -
340537 -
340538 -     Schedule Notes
340539 -
340540 -     Notes have been added and clarified to reflect evolving under-
340541 -     standings within PG&E, and from working with CDWR during the past
340542 -     month.
340543 -     ..
340544 -     Several of the Notes beginning on page 11 of the Schedule
340545 -     were reviewed today that show how understandings between CDWR and
340546 -     PG&E are applied in the Schedule.
340547 -
340548 -     CDWR has not commented on the Notes (see Action Item 2 from the
340549 -     Oct 5 meeting, ref SDS 2 line 135 and at ref SDS 2 line 291).
340550 -     Lori indicated today, CDWR will advise of any comments to ensure
340551 -     coordination on key objectives.
340552 -
340553 -
340554 -      ..
340555 -     Completion Targets
340556 -
340557 -     Bill DeHart reviewed the correlation between PG&E's Schedule,
340558 -     certain environmental constraints, and key milestones from CDWR's
340559 -     schedule, which were discussed at the Oct 5, meeting (see ref SDS
340560 -     2 line 296).  Tom Marki asked about extra cost to PG&E that may
340561 -     arise from delayed construction.  Kevin Coffee noted a change
340562 -     order would raise FERC permitting considerations.  This may lead
340563 -     to an implied definition of "completion" based on contract dates,
340564 -     and separate arrangements for work beyond those dates.
340565 -
340566 -
340567 -           ..
340568 -          Construction Launch
340569 -          Meeting in January
340570 -
340571 -          Tom plans to meet with Lonnie Essig in January at the site to
340572 -          consider specific scope and timing to energize and test the
340573 -          system.  This will likely require a series of meetings.
340574 -
340575 -          PG&E will revise the Schedule, ref OF 2, so the Notes for
340576 -          task DH6D to Energize and Test, indicate the meeting shown to
340577 -          occur in November, 1994, will be held in January, 1995.
340578 -
340579 -          PG&E's Construction Manager will attend the January meeting
340580 -          to coordinate construction launch issues, e.g., removal of
340581 -          spoil, environmental training, access to the work.
340582 -          ..
340583 -          This is Action Item 1 from Oct 5 meeting, see
340584 -          ref SDS 2 line 308 for details.
340585 -
340586 -
340587 -      ..
340588 -     Summary Schedule
340589 -
340590 -     PG&E submits today, a summary showing its entire schedule on a
340591 -     single sheet.  It supports management reviews and explaining the
340592 -     Schedule to CDWR's Project Team.  The Notes attached to the
340593 -     Summary are extracted from the main Notes, dis- cussed above, and
340594 -     so provide talking points to explain key issues.
340595 -
340596 -
340597 -
340598 -
3406 -

SUBJECTS
CDWR task #1, Pipeline Reach No. 1, by CDWR
Construction, Devils Den - Polonio Pass PP
Excess Spoil from Pipeline
Coordination TL and Pipeline Construction

4407 -
440701 - Bill DeHart and Tom Marki reported meeting with Lonnie Essig at the
440702 - project site yesterday, and observing considerable spoil mounded
440703 - along the transmission line route, which will interfere with PG&E's
440704 - work, as discussed at the Oct 5 progress meeting, ref SDS 2 line 390.
440705 - This comports with observations on Nov 15 site visit, ref SDS 6 line
440706 - 304.
440707 -
440708 - Lonnie said the contractor has not met the scheduled progress on
440709 - restoring plan grades after the pipe is layed and backfilled.  Lonnie
440710 - advised that CDWR has directed the contractor to submit a plan for
440711 - removal of excess spoil.
440712 -
440713 -
440714 - Don Kurosaka asked if PG&E has coordinated on removing the spoil?
440715 -     ..
440716 -     PG&E will submit a letter to CDWR confirming understandings
440717 -     that it requires final grades to be restored along the
440718 -     transmission line route according to the Schedule submitted today,
440719 -     as discussed above.  PG&E will endeavor to meet with CDWR in
440720 -     January or sooner if convenient for CDWR and its contractor to
440721 -     assist in working out a "plan" to avoid extra cost for any party,
440722 -     in order to adequately coordinate access to the work.
440723 -
440724 -         [See follow up at ref SDS 13 line 75.]
440725 -
440726 - PG&E estimates it will install approximately 1 mile of Transmission
440727 - Line per week.  CDWR and the pipeline contractor can use this
440728 - information to estimate rate of progress on building the pipeline
440729 - that is needed in order to avoid being overtaken by Transmission Line
440730 - work.  Joint resource analysis may show mutual adjustments that will
440731 - prevent extra cost by PG&E or the contractor.
440732 -
440733 -
440734 -      ..
440735 -     Estimate of Pipeline Progress
440736 -
440737 -     Progress on constructing the pipeline can be guaged from the con-
440738 -     tractor's monthly pay estimate, compared to his Schedule, in
440739 -     order to estimate the impact on PG&E's schedule to construct the
440740 -     transmission line.
440741 -
440742 -
440743 -
4408 -

SUBJECTS
Transmission Line Design, PG&E
Final Drawings from CDWR
Arco-Polonio Pass 70 kV Line, Engineering
Material Lead Time
Purchase Bill of Materials
Field Measure Switchyards

5309 -
530901 - PG&E understands CDWR has submitted the information it has that
530902 - affects the design of the Transmission line.  This is Action Item 3,
530903 - ref SDS 2 line 136.  The design of the Arco to Polonio Pass
530904 - Transmission Line is 100% complete, per report to Bill DeHart at ref
530905 - SDS 9 line 60.
530906 -
530907 -
530908 - Jeff Little advised that PG&E will take field surveys after the
530909 - switchyards are constructed, in order to insure adequate design of the
530910 - connections to CDWR's facilities.
530911 -
530912 -   [Activities for this work were added to the Schedule on 941213, per
530913 -   ref SDS 12 line 47.]
530914 -
530915 -
530916 -
530917 -
5310 -

SUBJECTS
Arco Substation
Engineering
Material Lead Time
Purchase Bill of Materials
70 kV Breaker & Bus Extension

5908 -
590801 - Jivat Gidvani reported PG&E has ordered 85% of the materials.  He is
590802 - about 30% complete with engineering, and expects to complete according
590803 - to the Schedule, ref SDS 9 line 143.
590804 -
590805 -
590806 - Tom Marki indicated that Tom Olsen needs to be briefed on PG&E's
590807 - installation of the 70 kV breaker and Bus Extension.
590808 -
590809 -
590810 -
590811 -
5909 -

SUBJECTS
Transmission Line Design, PG&E
SLO Hydro Tie Line
Engineering, Material Lead Time
Transfer Trip

7007 -
700701 - Design of the Tie Line is 100% complete based on previous scope, ref
700702 - SDS 9 line 81.
700703 -
700704 - Some materials have been ordered for the Transfer Trip system.  PG&E
700705 - design cannot continue until CDWR submits the design of the Control
700706 - Room and other criteria.  This is Action Item 3, discussed at the Oct
700707 - 5, Progress meeting at ref SDS 2 line 628.  CDWR had indicated this
700708 - information would be submitted by Dec 31, 1994, per ref SDS 2 line
700709 - 633.
700710 -
700711 - The Schedule delay reported today in SLO Hydro plant work may impact
700712 - PG&E's work (i.e., design, schedule, cost). [See above under "SLO
700713 - Hydro Plant Delayed."]
700714 -
700715 -
700716 -  ..
700717 - Valve System Power
700718 -
700719 - Bob McDougall and Om Lakhotia explained CDWR's planning considera-
700720 - tions to provide an interim system of valves at the SLO Hydro plant
700721 - location, to support delivery of water within the current schedule.
700722 - It is expected this system will require power.
700723 -
700724 - CDWR indicated construction of the Control Room may also be delayed
700725 - until the main hydro plant is built.  Jivat Gidvani pointed out that
700726 - PG&E's Transfer Trip system, was to be installed in the Control Room,
700727 - as protection for the Tie Line.  PG&E's procedures have prohibited use
700728 - of this type of Tie Line without adequate Line Protection.
700729 -
700730 - The matter is further complicated by the expected use of fiber optic
700731 - telecommunications for Transfer Trip.
700732 -
700733 -      ..
700734 -     Solutions
700735 -
700736 -     Some options to provide power to the valves were considered as
700737 -     follows:
700738 -
700739 -     1.  CDWR construct the Control Room in advance of the Power
700740 -         Plant, in order to support the Transfer Trip system.
700741 -
700742 -     2.  Build an interim control room exclusively for the transfer
700743 -         trip system, until the full facilities are constructed at a
700744 -         future time.
700745 -
700746 -     3.  Construct separate power "distribution" system to service the
700747 -         valves independent of the Tie Line.
700748 -         ..
700749 -     4.  Provide interim generators for the valve system.
700750 -
700751 -     5.  Construct the Tie Line under alternate Line Protection
700752 -         standards, e.g., omit transfer trip equipment.
700753 -
700754 -
700755 - Tom Marki said PG&E will submit comments to assist CDWR in its design
700756 - considerations.  Bill DeHart suggested contacting Glenn Rounds for
700757 - input.
700758 -
700759 -
700760 -
700761 -
7008 -
7009 -

SUBJECTS
DWR's Land Acquisition Activities
Right of Way Easements

7905 -
790501 - Jim Schindler reported CDWR has completed all of the preliminary
790502 - tasks needed to obtain easements for the Arco - Polonio Pass trans-
790503 - mission line.  At the meeting today, Jim directed his staff (Linda
790504 - Lundblad for Arco Sub - Devils Den, and Mike Bancroft for Devils Den
790505 - - Polonio Pass) to expedite the final step of obtaining easements so
790506 - PG&E can commence its work as scheduled on Feb 3, 1995. He indicated
790507 - that under certain scenarios, some easements from Arco Substation to
790508 - Devils Den Pumping Plant may be delayed until the March, 1995 time
790509 - frame.
790510 -
790511 - Bill DeHart reviewed understandings from the Oct 5 progress meeting
790512 - that this work needs to begin in February, so it can be completed by
790513 - on or about the end of March, 1995, based on endangered species
790514 - concerns, see ref SDS 2 line 441.
790515 - ..
790516 - This is further set out in Bob Masuoka's letter submitted by
790517 - PG&E on Nov 30, 1994 to Chuck Vogelsang at CDWR (see ref SDS 7 line
790518 - 181). Lori noted the excellent work Bob has done to expedite
790519 - environmental approvals (see also ref SDS 2 line 113).
790520 -
790521 -
7906 -
7907 -

SUBJECTS
Permits, GO 131-D, Implementation
Permit from Caltrans for Hwy 33 & 46
Permit to cross Aqueduct, by CDWR

8806 -
880601 - Bob Masuoka explained the schedule for GO 131-D filings which have
880602 - been incorporated into the Project Schedule for each of the primary
880603 - work phases.  The new Schedule submitted today, ref OF 2, shows a
880604 - common sequence of steps worked out with the CPUC, aimed at enabling
880605 - PG&E to commence construction in early February, 1995.
880606 -
880607 - PG&E obtained permission from the CPUC to file separately because of
880608 - the distinct locations and times of construction for each phase, as
880609 - shown in the Schedule and explained in the Notes for each task.
880610 -
880611 - PG&E needs CDWR's assistance on two points:
880612 -
880613 -    1.  Task DD0DGB setting up locations for the public to view the
880614 -        project EIR, requires CDWR to provide 15 sets of "Clean" copies
880615 -        of its EIR.  This is Action Item 6 at the Oct 5, Progress
880616 -        meeting, ref SDS 2 line 522.
880617 -        ..
880618 -    2.  Task DD0DGJ responding to public comments on the EIR
880619 -        within 5 business days of receipt by PG&E, through the 20
880620 -        calendar day response period by the public.
880621 -
880622 -        Bob will arrange with Ed Hills procedures to use Internet or
880623 -        other means to provide CDWR as much time as possible to prepare
880624 -        its response, in the event public comments are filed.
880625 -
880626 -        Bob advised an understanding that failure to respond within the
880627 -        5 day period could result in exemption being denied, which
880628 -        would trigger a 9 month or longer review process that would
880629 -        delay the project.
880630 -
880631 -
880632 - Bob reported PG&E has received the permit from Caltrans to cross
880633 - Highways 33 and 46; and has received the permit to cross CDWR's
880634 - Aqueduct.
880635 -
880636 -
880637 -
880638 -
880639 -
8807 -

SUBJECTS
Environmental Documentation, DWR
Amend EIR, by CDWR
Fish & Game Amended Opinion on PG&E
Environmental Training Construction Crews

9507 -
950701 - Bob confirmed understandings with respect to Action Item 7 from the
950702 - Oct 5 Progress meeting, ref SDS 2 line 578, that in order for PG&E to
950703 - begin work, the amended opinion from Fish & Game is needed, approving
950704 - PG&E's work in this area.
950705 -
950706 -
950707 -
950708 -  ..
950709 - Access of Delivery Trucks
950710 -
950711 - Bill DeHart asked about procedures for delivery by PG&E trucks, and
950712 - outside vendors?
950713 -
950714 - Ed Hills said there are procedures being used by the pipe contractor
950715 - for escorting trucks into areas outside the lizard fence. Deliveries
950716 - within the protection fence do not require rigorous procedures.
950717 -
950718 -
950719 -  ..
950720 - Environmental Training
950721 -
950722 - Ed said he is setting this up for PG&E staking and construction
950723 - crews.
950724 -
950725 - Bill DeHart asked about procedures to train new hires and people
950726 - brought onto the job for a few hours to perform short term tasks. This
950727 - relates to short term staffing.
950728 -
950729 - Ed indicated this can be done with conventional tailgate sessions,
950730 - similar to safety orientations.  Bob advised that PG&E has scheduled a
950731 - task DD0DJ for an initial training session, which he will coordinate
950732 - with Ed with the aim of minimizing the number of people who might be
950733 - assigned during the project that have not received environmental
950734 - training.  The Schedule Notes for this task (#17 on the Dec 7, 1994
950735 - Schedule), allow 2 hours notice to obtain training by CDWR staff. The
950736 - tailgate procedure Ed describes sounds amenable to this Schedule. PG&E
950737 - will accommodate any reasonable approach CDWR can provide.
950738 -
950739 -
950740 -  ..
950741 -
9508 -

SUBJECTS
Monthly Pay Estimate

9604 -
960401 - Lori asked about the status of pay estimate.
960402 -
960403 - Bill said an invoice will be issued in the near term.
960404 -
960405 -
960406 -
9605 -
Distribution. . . . See "CONTACTS"