DIARY: December 13, 1994 09:14 AM Tuesday; Rod Welch

Revised Schedule on CDWR.

1...Summary/Objective
2...Question???


..............
Click here to comment!

CONTACTS 

SUBJECTS
PG&E Schedule Report to CDWR, 941213p.mpp
Devils Den - Polonio Pass
Transmission Line Design, PG&E
Final Drawings from CDWR
Field Measure Switchyards & Finalize
Connect Transmission Line to Switchyards

1308 -    ..
1309 - Summary/Objective
1310 -
131001 - Follow up work at ref SDS 3 line 487.  Modified Schedule, ref OF 1,
131002 - to reflect Jeff's notice at Progress Meeting, that PG&E will field
131003 - measure the switchyards before completing engineering.
131004 -
131005 -
131006 -
1311 -
1312 -
1313 - Progress
1314 -
131401 - Since PG&E is instructed to design its work in advance of CDWR
131402 - facilities being completed, prudent design requires it to take field
131403 - measurements rather than rely on the construction drawings for the
131404 - CDWR's switchyards.  CDWR's design changes announded at the Progress
131405 - Meeting on 941208, ref SDS 3 line 265, support the decision for PG&E
131406 - to defer its final design, until after CDWR's Switchyards are
131407 - constructed.
131408 -
131409 -
131410 - Created new task DD1F to field measure switchyards and complete
131411 - engineering, which will occur after the switchyards are complete.
131412 -
131413 - The problem this is that this cannot be done "independent" from
131414 - CDWR's work.  It cannot be performed until after CDWR constructs the
131415 - Switchyards.
131416 -
131417 - Made task DD1F lag 16 weeks prior to the Scheduled completion of
131418 - CDWR's task #24, which is DD3G, so that DD1F completes on 950914.
131419 - Gave the Field Measure and Complete Engineering task, DD1F, only 3
131420 - weeks duration, so there is a week left to complete the connections
131421 - into the Switchyards.  Bill has indicated previously this is only a
131422 - few days work.
131423 -
131424 - Made task DD5E to connect to the switchyards, as another construct
131425 - activity, following field measurements.  Made DD5D4 to construct
131426 - Devils Den to Polonio Pass, a predecessor, and reduced its duration
131427 - by a week, so the last task is to connect to the plants.
131428 -
131429 - Modified sequencing accordingly.
131430 -
131431 -
131432 - Question???
131433 -
131434 - How reasonable is it to assume the switchyards will be ready for
131435 - field measurements by 950825, 16 weeks prior to scheduled completion,
131436 - when it appears CDWR's completion is slipping.
131437 -
131438 - However, the 950825 date is necessary in order for PG&E to complete
131439 - its work within the contract completion date:  951001.
131440 -
131441 -
131442 -
131443 -
131444 -
1315 -

SUBJECTS
PG&E Schedule Report to CDWR, 941213p.mpp
SLO Hydro Power Plant
Transmission Line Design, PG&E
Field Measure Switchyards & Finalize
Connect Tie Line to Switchyard
Engineering

1609 - Summary/Objective
1610 -
161001 - Made same kind of changes to this portion of the schedule.  It
161002 - appears though that more work is needed due to the delay in
161003 - construction of the Power Plant, ref SDS 3 line 266.
161004 -
161005 - This is a little different in that we are not constrained by PG&E's
161006 - completion date, since it is 960201, and the current schedule shows
161007 - completion oa 951002.
161008 -
161009 - Made task GD1F lag 25 weeks prior to the Scheduled completion of
161010 - CDWR's task #24, which is GD3G, so it completes on 950724.  Gave the
161011 - Field Measure and Complete Engineering task, GD1F, only 2 weeks
161012 - duration because there is only a single plant to measure and complete
161013 - the design.  I guess it will really take 4 weeks to schedule and get
161014 - the design completed.
161015 -
161016 - See also discussion above.
161017 -
161018 -
161019 -
1611 -

SUBJECTS
PG&E Schedule Report to CDWR, 941213p.mpp
SLO Hydro Power Plant
Transmission Line Design, PG&E
Field Measure Switchyards & Finalize
Connect Tie Line to Switchyard

1808 - Summary/Objective
1809 -
180901 - Made same kind of changes to this portion of the schedule.
180902 -
180903 - The Schedule is not constrained by PG&E's completion date, since it
180904 - is 951201, and the current schedule shows completion oa 951002.
180905 -
180906 - Made task KD1F lag 30 weeks prior to the Scheduled completion of
180907 - CDWR's task #24, which is KD3G, so it completes on 950921.  Gave the
180908 - Field Measure and Complete Engineering task, KD1F, only 2 weeks
180909 - duration because there is only a single plant to measure and complete
180910 - the design.
180911 -
180912 -
180913 -