DIARY: December 5, 1994 08:06 AM Monday; Rod Welch

Visited Bob Masuoka re CDWR schedule for GO 131-D requirements.

1...Summary/Objective
2...Clean copies of EIR for public inspections


..............
Click here to comment!

CONTACTS 
0201 - PG&E Proj Mngmnt Transm Sys        415 973 6778 fax 8426
020101 - Mr. Bill DeHart, PMP
020102 - Project Manager, Room 1183B-V11C =415 973 5655 pger 510 810 3026
020103 - Project Management Group
0202 - PG&E Building & Land Svcs.         415 973 8273 fax or 800...
020201 - Mr. Robert Masuoka, P.L.S.
020202 - Senior Land Project Analyst Room 2027, Mail Code H21A =415 973 8273
020203 - Land Department

SUBJECTS
Central Coast Aqueduct, PG&E
Schedule Revisios, 941205
CDWR submit "Clean Copy" EIR data for GO
GO 131-D Implementation

1006 -    ..
1007 - Summary/Objective
1008 -
100801 - Followed up work at ref SDS 18 line 69.  Called Bob and arranged to
100802 - meet oa 0930.  Revised Schedule to show GO 131-D activity detail,
100803 - based on discussions between PG&E and CPUC on requirements.  Began
100804 - arrangements for Environmental training of PG&E construction crews.
100805 - Updated SDS record and Subject Index.
100806 -
100807 -
1009 -
1010 -
1011 - 0930 Bob here to revise Schedule
1012 -
101201 - Developed schedule tasks and sequencing for the WBS levels on the Arco
101202 - - Polonio part of the project.  This resulted in eliminating the BK
101203 - task to implement GO 131-D that was in the 941006 Schedule, as a
101204 - general activity.  Today we provided the detail and incorporated it
101205 - into each affected WBS level.  It is controlled by task BG that
101206 - developes a "plan" for carrying out the requirements.  Today, we are
101207 - setting out the "plan."
101208 -
101209 -     Bob said that for SLO and Casmalia, we can use the same fragnet we
101210 -     developed for Arco to Polonio Pass, except the Advice letter
101211 -     cannot be issued until we get the certified EIR, task GD0E6.
101212 -
101213 -        Note that we had to make some slight revisions because the
101214 -        Public Notices cannot be published and Advice Letter cannot be
101215 -        filed on SLO and Casmalia until after CDWR files the
101216 -        Supplemental EIR, since it is the subject of the Notice.
101217 -
101218 -
101219 - Here is the basic structure we added today, revising the Environmental
101220 - activities Bob developed on 940930 at ref SDS 4 line 326.
101221 -
101222 -   f: 03 00067 00 03 02 01 01 DD0DG.................... GO 131-D Implementation
101223 -   f: 03 00067 00 03 02 01 01 DD0DGB..................... Locations for Public Inspections
101224 -   f: 03 00067 00 03 02 01 01 DD0DGD..................... Brief Local Officials
101225 -   f: 03 00067 00 03 02 01 01 DD0DGF..................... Advice Letter
101226 -   f: 03 00067 00 03 02 01 01 DD0DGH..................... Notices to Public
101227 -   f: 03 00067 00 03 02 01 01 DD0DGJ..................... Public Response and PG&E Comment to CPUC
101228 -   f: 03 00067 00 03 02 01 01 DD0DGL..................... Executive Resolution
101229 -
101230 -   f: 03 00067 00 03 02 01 01 DD0DJ.................... Environmental Training Construction Crews
101231 -
101232 - Need to review to check incorporation of recent correspondence, per
101233 - ref SDS 17 line 118.
101234 -
101235 -
101236 - Clean copies of EIR for public inspections
101237 -
101238 - Bob indicated PG&E needs these copies, as requested previously at
101239 -
101240 -
101241 -
101242 -
1013 -

SUBJECTS
Environmental Training Construction Crews

1104 - Summary/Objective
1105 -
110501 - Bob and I discussed with Bill the need to arrange for environmental
110502 - training by CDWR of PG&E work crews.  Bill called Kevin Withrow to
110503 - coordinate on this.  We will review it with CDWR at the progress
110504 - meeting on Thursday.
110505 -
110506 - The objective is to accomplish the training without disruption of
110507 - ordinary hiring and movement of construction personnel, which may
110508 - fluctuate from day to day.  We entered in the Notes that CDWR will
110509 - provide this training on 2 hours notice.
110510 -
110511 -
110512 -
110513 -
1106 -

SUBJECTS
Permits, Caltrans
Aqueduct crossing, CDWR
Fish & Game, Arco - Devils Den
Fish & Game Amended Opinion on PG&E
Permit from Caltrans for Hwy 33 & 46
Permit to cross Aqueduct, by CDWR

1709 - Summary/Objective
1710 -
171001 - Bob thinks the permit issues are being handled by Jeff.
171002 -
171003 -     We need to check on the status of permits.  We have a lot of
171004 -     these, and should investigate in advance of meeting with CDWR on
171005 -     Thursday.
171006 -
171007 -
171008 - Received a letter from Bob, ref DRT 1 line 22, to CDWR dated 941130,
171009 - which reports on a field review of project site for endangered
171010 - species.  This letter seems to be requesting CDWR to obtain the
171011 - amended biological opinion from Fish & Game.  It cites Mary's
171012 - understanding from discussions with Fish & Game at ref SDS 4 line 205.
171013 -
171014 -
171015 -
171016 -
1711 -

SUBJECTS
Schedule, Review, CDWR
941205.mpp

2005 - Summary/Objective
2006 -
200601 - Reviewed status of other CDWR requirements in advance of starting
200602 - construction.  Bob wants to develop a list for discussion at the
200603 - Progress meeting on 941207.
200604 -
200605 - We decided this list will flow naturally from review of the Progress
200606 - Schedule and the attached notes.
200607 -
200608 -
200609 - Bill requested a Schedule summary, similar to what we did on Gold Hill
200610 - at ref SDS 18 line 205; instructions are at ref SDS 15 line 255.
200611 -
200612 -
200613 -
2007 -

SUBJECTS
Editing Task descriptions, Durations
Subject Index

2205 - Summary/Objective
2206 -
220601 - Revised WBS and SDS SI to add the new activities recommended by Bob
220602 - this morning, per above.
220603 -
220604 - Initially I made DD0D the GO 131-D stuff, but GDOD is already assigned
220605 - to something, so will change DD0D to DD0B, instead. However, we
220606 - already have a GD0B, so will change it to GD0A.  Somehow everything to
220607 - fit intelligently, and to be able to add things as they are needed
220608 - without loosing the order.
220609 -
220610 - What I finally wound up with is to leave the change for the 70 kV line
220611 - from Arco - Polonio Pass, so GO 131-D is DD0DB (except for reasons
220612 - explained below, had to change it to DD0DG), SLO is left as GD0EB, and
220613 - Casmalia is KD0EB.
220614 -
220615 -
220616 -
220617 -
2207 -

SUBJECTS
Cultural Resources
Environmental Protection
Biological & Cultural Survey, Tie Line

2606 - Summary/Objective
2607 -
260701 - This task is in the SDS WBS, but there is no activity for it in the
260702 - Schedule.  I recall that Bob Masuoka indicated that Cultural Resources
260703 - work only occurred on the SLO and Casmalia portions of the project.
260704 - Actually, it appears this work was completed prior to the Schedule
260705 - being prepared, so there is a WBS in the SDS SI, but not actual
260706 - activity on the Schedule for the Arco - Polonio Pass part of the
260707 - project, ref SDS 4 line 296.
260708 -
260709 - As a result, we have to change DD0DD, to DD0DG..
260710 -
260711 -
260712 -
260713 -
260714 -
Distribution. . . . See "CONTACTS"