S U M M A R Y


DIARY: November 4, 1994 01:43 PM Friday; Rod Welch

Received follow up on GH Upgrade, SMUD use of right of way.

1...Summary/Objective
2...GO 131-D Exemption NOT Needed


..............
Click here to comment!

CONTACTS 
0201 - PG&E Transm Contracts              415 973 3872 fax 972 0871
020101 - Ms. Pam Taheri,; Contract Manager, Rm 2334 Mail Code B23A =415 973 1660
020102 - Transmission Contracts =415 972 0871 (fax)
0202 - PG&E Law Department                415 973 nnnn fax or 800...
020201 - Mr. Glenn West Jr., Esq.;  =415 973 2776

SUBJECTS
Goldhill Horseshoe Transmission Upgrad
Contract, Develop Terms
GO 131-D
Interim Payment Agreements

1106 -    ..
1107 - Summary/Objective
1108 -
110801 - Followed up work at ref SDS 3 line 292 and discussions at ref SDS 4
110802 - line 61,  Received ref DRT 1 line 10 today via EM.  Also talked to
110803 - Glenn West on the way back from Bob Masuoka's office.  Cynthia and I
110804 - saw him in the elevator lobby.  He said they decided not to write a
110805 - letter to advise of prospective additional costs arising from GO 131-D
110806 - issues.
110807 -
110808 - GO 131-D Exemption NOT Needed
110809 -
110810 - Pam's letter today indicates ref DRT 1 line 25, that following the
110811 - meeting on Wednesday, 941102, Buck Jones has reported that...
110812 -
110813 -          ...it seems like we will have to go through a complete "131
110814 -          D" process as to the relocation, since the 12/31/95
110815 -          exemption date is unrealistic for this project.
110816 -
110817 -          The reconductoring phase, however, is exempt under GO 131-D
110818 -
110819 -      This would seem to change the perspective about expediting
110820 -      PG&E's work in order to qualify for GO 131-D exemption on
110821 -      relocating the line, per Buck's comments at ref SDS 3 line 244.
110822 -      In turn, this may obviate the need for seeking agreement by
110823 -      Sierra to make payments for expediting engineering in advance of
110824 -      having a signed contract and project approval from PG&E
110825 -      management, which was contemplated at the Progress Meeting on
110826 -      941102 at ref SDS 3 line 289.
110827 -
110828 -        [See follow up at ref SDS 5 line 180, analysing EM dated
110829 -        941115 from Buck urging that PG&E obtain approval from Sierra
110830 -        to finance efforts to qualify for GO 131-D exemption.]
110831 -
110832 -
110833 -
110834 -
1109 -

SUBJECTS
Goldhill Horseshoe Transmission Upgrad
941103 PG&E team in SF, Progress Meeting

1205 - Summary/Objective
1206 -
120601 - Followed up work at ref SDS 4 line 51, and at ref SDS 3 line 59.
120602 - Reported and analysed results of meetings.
120603 -
120604 -
1207 -
Distribution. . . . See "CONTACTS"