DIARY: November 2, 1994 09:30 AM Wednesday; Rod Welch

Meeting on Gold Hill Horseshoe Transm. Upgrade.

1...Summary/Objective
2...Follow Up
3...Mike Emery Assigned Project Manager Replace Bill DeHart on Gold Hills
....................Schedule Diary System
.......Personal and Organizational Integrated Management Support
4...Schedule Submitted Showing Compliance with GO 131-D Requirements
5...Sierra Contract Requires Conceptional Agreement Halsey Junction Line
6...Schedule
....GO 131-D
....Completion Beyond Dec 31, 1995
7...Alternate Schedule Scenarios
8...Sierra Needs Power in 1997
9...Engineering
10...Payment from Sierra
11...Interim Agreement
12...Notification of Sierra
13...Possible Right of Way Conflicts
..1...New SMUD Pole in Right of Way
..2...Bridge Route
14...Public Notice PG&E Has Not Determined EMF Justifiable Health Concern
15...Agreement Reached with L&P for #300K
16...Progress Meeting Schedule


..............
Click here to comment!

CONTACTS 
0201 - PG&E Proj Mngmnt Transm Sys        41
020101 - Mr. Bill DeHart, PMP
020102 - Project Manager, Room 1183B-V11C
020103 - Project Management Group
020104 - Ms. Cynthia Chang; Project Analyst
020105 - Project Management Group
020106 - Mr. Michael R. Emery
020107 - Project Manager, Room 1175B-V11C
020108 - Project Management Group
0202 - PG&E Transm Contracts              41
020201 - Ms. Pam Taheri,; Contract Manager, Rm 2334 Mail Code B23A
020202 - Transmission Contracts
0203 - PG&E Law Department                41
020301 - Mr. Glenn West Jr., Esq.;
0204 - PG&E Trans Sys Engineering         41
020401 - Mr. Randy Hopkins, E.E.; Engineer; Rm 580, Mail Code F5C
0205 - PG&E Building & Land Svcs.         41
020501 - Mr. Buck Jones;
0206 - Pacific Gas and Electric Company   91
020601 - Mr. Edward Bedwell;
020602 - Local Government Relations
020603 - Mr. Jim Penrose;
020604 - TM&C
0207 - PG&E Building & Land Svcs.         41
020701 - Ms. Trang Luu;
0208 - PG&E Building & Land Svcs.         41
020801 - Mr. Michael Herz;

SUBJECTS
Gold Hill Horseshoe Transmission Upgrad
Progress Meeting PG&E Team

0504 -
0504 -    ..
0505 - Summary/Objective
0506 -
050601 - Follow up ref SDS 2 0000.
050603 -  ..
050604 - Met today in PG&E's conference room at 525 Market, per agenda at
050605 - ref DRT 2 line 10.
050607 -  ..
050608 - New team members were introduced.  Work is pending on contracts.
050609 - Analysis of GO 131-D is needed for schedule and budget impacts,
050610 - including risks of delays and additional cost, if exemption is not
050611 - awarded.  Stakeholders may need notice of GO 131-D impacts.
050612 -
050614 -  ..
050615 - Follow Up
050616 -
050617 -   1.  Conceptual framework agreement with SMUD will be completed
050618 -       within the next several weeks.
050619 -
050620 -   2.  Work will commence on finalizing the SMUD contract and on the
050621 -       Sierra contract after the SMUD conceptual framework is
050622 -       completed.
050624 -        ..
050625 -   3.  GO 131-D procedures and impacts will be developed.
050627 -        ..
050628 -   4.  Project schedule and budget will be updated to apply GO 131-D
050629 -       anticipated impacts.
050631 -        ..
050632 -   5.  Consideration will be given to notifying City of Folsom if
050633 -       project will not be completed by 951231.
050635 -        ..
050636 -   6.  Consideration will be given to notifying Sierra Pacific of
050637 -       additional costs that may arise if an exemption from GO 131-D is
050638 -       not obtained, and that to obtain an exemption requires Sierra to
050639 -       advance reasonable and necessary funds to prepare an adequately
050640 -       supported filing.
050642 -        ..
050643 -   7.  Ed and Buck will investigate possible conflict with SMUD line
050644 -       construction underway in the proposed re-location corridor.
050646 -        ..
050647 -   8.  Ed will report on results of election in City Folsom, whether a
050648 -       bridge is approved for the right of way PG&E intends to use.
050649 -
050650 -
050651 -
050652 -
0507 -

SUBJECTS
Introductions

0603 -
060401 -  ..
060402 - Mike Emery Assigned Project Manager Replace Bill DeHart on Gold Hills
060403 -
060404 - Bill DeHart introduced Mike Emery as the new project manager, who will
060405 - be transitioning over the next month or so, from Bill who is leaving
060406 - under PG&E's current re-organization.
060407 -
060408 - Bill introduced Rod Welch who is providing management support using a
060409 - software program to organize project information, called SDS:
060410 -
060412 -                     ..
060413 -                    Schedule Diary System
060414 -
060415 -
060416 -    PG&E has used SDS on the CDWR project the past few months and has
060417 -    had good results.  CDWR has asked PG&E to continue using SDS on
060418 -    that project.
060419 -
060420 -       [On 941110 Mike requested install SDS on his computer.
060421 -       ref SDS 4 0001
060422 -
060424 -  ..
060425 - Rod explained SDS implements a management technology called POIMS:
060426 -
060428 -        ..
060429 -       Personal and Organizational Integrated Management Support
060430 -
060431 -
060432 -
060433 -   Automation is applied to capture the project record to test under-
060434 -   standings, provide uniform understandings among team members, and
060435 -   link Action Items into a Schedule to insure things get done and not
060436 -   overlooked.  SDS tracks E-mail and other documents, but in addition
060437 -   the user can "think about" what was done, why, and implications.
060438 -   This is called:  investing intellectual capital.  It pays off be-
060439 -   cause daily tasks are supported by instant access to the history of
060440 -   prior work so mistakes are reduced and things get done on time.
060441 -
060442 -
060444 -  ..
060445 - Pam Taheri is taking over for Bob Lambert on contract management.  She
060446 - indicated Gene West will continue to support the project.
060447 -
060448 -
060449 -
0605 -

SUBJECTS
Schedule, Bill DeHart

0903 -
090401 -  ..
090402 - Schedule Submitted Showing Compliance with GO 131-D Requirements
090403 -
090404 - Bill submitted and explained a current CPM schedule, which is file
090405 - ref OF 2.  It reflects project understandings prior to today with
090406 - respect to completing relocation work by 960101 in order to qualify
090407 - for GO 131-D exemption.  This means activity durations have been
090408 - shortened.
090410 -  ..
090411 - Team members should review the schedule and notify Mike of changes
090412 - and/or impacts that should be considered for the schedule.
090413 -
090414 -   [See discussion in next segment on updating schedule to reflect GO
090415 -   131-D research.]
090416 -
090417 -
090418 -
0905 -

SUBJECTS
Contract, SMUD, General
Conceptual, PG&E draft
Permits, GO 131-D
Interim Payment Agreements, from Sierra
Schedule, Contracts

2507 -
250801 -  ..
250802 - Sierra Contract Requires Conceptional Agreement Halsey Junction Line
250803 -
250804 - Pam said progress on the Sierra contract cannot proceed until after a
250805 - conceptual framework for agreement is reached with SMUD on relocating
250806 - PG&E's Halsey junction line, to a right of way controlled by SMUD.
250808 -  ..
250809 - Pam submitted a draft of PG&E's proposed letter to SMUD ref DRT 1
250810 - line 22, transmitting PG&E's most recent response to SMUD's proposed
250811 - language for a conceptual agreement, see ref OF 1 line 8.
250813 -  ..
250814 - Pam explained that after the conceptual agreement with SMUD is signed
250815 - by the parties, PG&E can then begin work on a final contract to
250816 - implement the conceptual framework with SMUD, and at the same time
250817 - will begin work on a contract with Sierra Pacific.
250819 -  ..
250820 - Pam reported PG&E has changed the design of the pole line by adding a
250821 - 2nd circuit to accommodate SMUD's demand for a consideration in
250822 - exchange for use of its right of way PG&E was able to make this change
250823 - and also reduce its estimate of project cost.
250825 -  ..
250826 - Randy Hopkins advised that an OSHA safety issue arises with respect to
250827 - working on both lines simultaneously, however, PG&E expects that SMUD
250828 - will not be using this second circuit for the foreseeable future.
250830 -  ..
250831 - Pam said a key difference to be resolved with SMUD is over their
250832 - request to lease the 2nd circuit "in perpetuity."  PG&E has offered a
250833 - 20 year lease.
250834 -
250836 -  ..
250837 - Schedule
250838 -
250839 - Pam expects that next week the parties will close on all major
250840 - concepts.  She indicated that reaching final contracts with SMUD and
250841 - Sierra could take about 4 months, perhaps extending until the end of
250842 - February, 1995.
250843 -
250845 -     ..
250846 -    GO 131-D
250847 -    Completion Beyond Dec 31, 1995
250848 -
250849 -    Ed Bedwell noted that complying with GO 131-D may extend comple-
250850 -    tion beyond Dec 31, 1995.  Consideration should be given to noti-
250851 -    fying City of Folsom officials if it is reasonably expected that
250852 -    completion will be dramatically extended.
250854 -     ..
250855 -    Buck Jones explained current thinking on GO 131-D filing require-
250856 -    ments. If an exemption is attained, the cost will be about $5K with
250857 -    minimal schedule impact.  If the project is not given an exemption.
250858 -    there may be a cost of $50-$100K and approval process could sig-
250859 -    nificantly delay the project.
250861 -     ..
250862 -    Buck recommends major effort to finalize contracts before filing
250863 -    for GO 131-D permits.
250864 -
250866 -  ..
250867 - Alternate Schedule Scenarios
250868 - Sierra Needs Power in 1997
250869 -
250870 - Pam suggested that the project schedule be considered to reflect GO
250871 - 131-D, and the time for finalizing the contracts discussed today. She
250872 - proposed developing a project schedule based on Sierra needing power
250873 - in 1997.
250875 -  ..
250876 - Bill explained the current schedule reflects information from Engine-
250877 - ering.  He noted that GO 131-D is a new requirement that has not been
250878 - fully defined.  PG&E Land is working to identify procedures and im-
250879 - pacts on all new projects.
250881 -  ..
250882 - Bill feels Gold Hill relocation work will likely be subject to GO
250883 - 131-D.  PG&E will incorporate these impacts in the project schedule
250884 - as they become apparent.
250885 -
250886 -
250888 -  ..
250889 - Engineering
250890 -
250891 - Randy Hopkins indicated that engineering can be expedited for the
250892 - relocation to support filing on GO 131-D.  This may increase the
250893 - engineering budget by a moderate amount, but would require immediate
250894 - expenditure in advance of having a contract with Sierra.
250895 -
250896 -
250898 -  ..
250899 - Payment from Sierra
250900 - Interim Agreement
250901 -
250902 - Pam noted concerns about PG&E continuing to incur expenses prior to
250903 - obtaining contracts and project approval.
250904 -
250905 -     If PG&E seeks GO 131-D exemption for relocating the line, it will
250906 -     be required to complete this work prior to Dec 31, 1995.  This
250907 -     effort will increase the costs of engineering, procurement and
250908 -     construction.  At this time, the feasibility of accelerated
250909 -     performance and its cost have not been evaluated.
250911 -      ..
250912 -     If PG&E elects not to seek an exemption, then costs could increase
250913 -     by $50 - $100K in direct costs, plus an unknown amount to comply
250914 -     with any requirements that might emerge from the process.  An
250915 -     example, but by no means expected result of subjecting the project
250916 -     to the full GO 131-D permitting process, could result in raising
250917 -     the poles, or constructing structural and more secure barriers
250918 -     along the corridor, or special public facilities, in order to meet
250919 -     public concerns.  The GO 131-D process could extend completion of
250920 -     the project into 1997.
250921 -
250923 -  ..
250924 - Notification of Sierra
250925 -
250926 - Since Sierra will be liable for the cost of the project, there was
250927 - consideration of notifying them about these risks, and that to reduce
250928 - their exposure, PG&E is willing to enter into an interim agreement
250929 - for Sierra to finance the work required to obtain the GO 131-D
250930 - exemption.  This could be accomplished by a letter agreement, so PG&E
250931 - management can approve PG&E expending the effort required to seek an
250932 - exemption from GO 131-D.
250934 -  ..
250935 - Glenn West said this letter could be submitted to FERC to obtain
250936 - approval for Sierra to make payments to PG&E.
250937 -
250938 -     In order to issue such notice, PG&E needs to estimate the costs
250939 -     of obtaining GO 131-D exemption by exediting its work; this
250940 -     includes making a determination of whether it is actually
250941 -     possible to complete by 951231 even with accelerated performance.
250943 -      ..
250944 -     PG&E needs an estimate of costs in the event GO 131-D exemption
250945 -     is not obtained.  This includes:
250946 -
250947 -         a.  Cost and time of the process.
250948 -
250949 -         b.  Cost of alternate scenarios in the event remedial work is
250950 -             ordered, with an assessent of factors which could lead to
250951 -             such orders, so that the level of risk can be considered.
250952 -
250953 -
250955 -  ..
250956 - Pam indicated that Sierra is very cost conscious.  It was not apparent
250957 - from the discussion today that they have alternate means to accomplish
250958 - the objectives of this project.  Therefore, they may be interested in
250959 - supporting PG&E's effort to reduce the cost of the project by obtain-
250960 - ing the GO 131-D exemption.
250961 -
250962 -     This effort was continued at a follow up meeting reported at ref
250963 -     SDS 3 line 51.
250964 -
250965 -
250967 -  ..
250968 - Possible Right of Way Conflicts
250969 -
250970 - Ed Bedwall reported on two possible conflicts in PG&E's use of SMUD's
250971 - right of way.
250972 -
250974 -       ..
250975 -  1.  New SMUD Pole in Right of Way
250976 -
250977 -      Ed saw some poles for a 69 kV line laid out within the corridor
250978 -      where PG&E intends to relocate its line in the SMUD right of way.
250979 -
250980 -      Randy indicated PG&E needs only 57 feet of SMUD's 200' right of
250981 -      way.
250983 -       ..
250984 -      Ed and Buck Jones will investigate this matter tomorrow.  Bill
250985 -      will meet with Ed at the site tomorrow, prior to a meeting with
250986 -      CDWR in Sacramento at 1000.
250987 -
250989 -       ..
250990 -  2.  Bridge Route
250991 -
250992 -      Next Tuesday, city of Folsom will vote on alternate routes for a
250993 -      bridge to cross the American River.  One of the choices for the
250994 -      bridge would conflict with the route PG&E intends for the
250995 -      relocation project.
250996 -
250997 -
250998 -
2510 -

SUBJECTS
Public Relations, EMF
Remedial Action Scheme (RAS)

2904 -
290501 -  ..
290502 - Public Notice PG&E Has Not Determined EMF Justifiable Health Concern
290503 -
290504 - Mike Herz reported an article was published recently which has been
290505 - viewed as incorrectly indicating PG&E is relocating the Halsey
290506 - Junction line in order to address EMF issues.  Mike recommends that
290507 - PG&E make clear in its communications that PG&E is performing this
290508 - project for business reasons set out in its contracts, and that PG&E
290509 - has not concluded EMF warrants remedial action.
290510 -
290511 -     Ed feels the article Mike cites cannot be reasonably construed to
290512 -     say PG&E is relocating its line due to EMF.  Mike concurred, but
290513 -     noted that PG&E is making an extra effort to reduce the chance
290514 -     that even "unreasonable" conclusions do not gain currency within
290515 -     the community on EMF relative to PG&E work and facilities.
290517 -  ..
290518 - Mike has been assigned to support the project in dealing with news
290519 - media.  He requested notice of public events where news media are
290520 - expected to be in attendance.
290521 -
290522 -
290523 -
2906 -

SUBJECTS
Developer Negotiations, Bob Crooks
Contracts, L&P

3104 -
310501 -  ..
310502 - Agreement Reached with L&P for #300K
310503 -
310504 - Ed Bedwell reported for Bob Crooks.  About three (3) weeks ago PG&E
310505 - reached agreement with L&P to contribute $300K plus an amount for
310506 - contingencies.
310507 -
310508 -     The agreement has been "lost in the mail."  It is dated October
310509 -     11, or 24 [????]
310510 -
310512 -  ..
310513 - The parties were at impasse in negotiations at $200K.
310514 -
310515 -     The mayor of the City of Folsom helped in obtaining the good
310516 -     offices of a city council member to mediate the agreement between
310517 -     PG&E and L&P.
310518 -
310519 -     Press coverage alerting the community of PG&E's efforts to
310520 -     relocate its line, touching on health concerns, helped the devel-
310521 -     oper recognize the advantage of increasing its financial contri-
310522 -     bution to the project to $300K.
310524 -      ..
310525 -     Following announcement of the agreement, L&N took public credit.
310526 -     Its negotiating posture had been vigorous.
310528 -  ..
310529 - The community has responded favorably to press notice that PG&E will
310530 - relocate the line.
310531 -
310532 -     One person has objected to PG&E relocating its line.
310533 -
310534 -     Some people have expressed disappointment that SMUD is not
310535 -     removing its line.
310536 -
310537 -
310538 -
310539 -
3106 -

SUBJECTS
Next Meeting

3203 -
320401 -  ..
320402 - Progress Meeting Schedule
320403 -
320404 - Mike will notify the team of the next progress meeting date.
320405 -
320406 -
320407 -
320408 -
320409 -
320410 -
320411 -
320412 -
3205 -