S U M M A R Y


DIARY: November 2, 1994 01:48 PM Wednesday; Rod Welch

Meeting on Goldhill Horseshoe re letter of commitment on funds.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Proj Mngmnt Transm Sys        415 973 6778 fax 8426
020101 - Mr. Bill DeHart, PMP
020102 - Project Manager, Room 1183B-V11C =415 973 5655 pger 510 810 3026
020103 - Project Management Group
0202 - PG&E Proj Mngmnt Transm Sys        415 973 6778 fax 8426
020201 - Mr. Michael R. Emery
020202 - Project Manager, Room 1175B-V11C =415 973 4322 pager 807 3283
020203 - Project Management Group
0203 - PG&E Transm Contracts              415 973 3872 fax 972 0871
020301 - Ms. Pam Taheri,
020302 - Contract Manager, Rm 2334 Mail Code B23A =415 973 1660
020303 - Transmission Contracts =415 972 0871 (fax)
0204 - PG&E Law Department                415 973 nnnn fax or 800...
020401 - Mr. Glenn West Jr., Esq.;  =415 973 2776
0205 - The Welch Company                  415 781 5700
020501 - Mr. Rod Welch

SUBJECTS
Goldhill Horseshoe Transmission Upgrad
Contract, Develop Terms
SMUD agreement, Pam Taheri
Sierra agreement, Pam Taheri
GO 131-D procedures and Impacts
Interim Payment Approval from Sierra

1008 -    ..
1009 - Summary/Objective
1010 -
101001 - Followed up work at ref SDS 3 line 59, continuing Progress meeting
101002 - from this morning, on issue of GO 131-D and interim payment from
101003 - Sierra.
101004 -
101005 - The challenges of qualifying for GO 131-D exemption were further
101006 - reviewed relative to requesting agreement from Sierra to pay for
101007 - engineering costs in advance of having a signed project contract, per
101008 - discussions at ref SDS 3 line 239, and at ref SDS 3 line 280.
101009 -
101010 -      [This issues was discussed again on 941117 at ref SDS 4 line
101011 -      117.]
101012 -
101013 -
1011 -
1012 -
1013 - Discussion
1014 -
101401 - Mike advanced a scenario where PG&E could accomplish the engineering,
101402 - procurement and construction activities needed to obtain an exemption
101403 - for GO 131-D environmental permits.
101404 -
101405 - Pam feels the contract negotiations could take up to 4 months.  She
101406 - feels this lengthy period would prevent PG&E from completing the work
101407 - in time to qualify for an exemption from GO 131-D.
101408 -
101409 - The discussion today indicated to me that PG&E has made a GO 131-D
101410 - filing for an exemption on the basis of segmenting the project.  One
101411 - segment is to relocate an existing line.  The other segment is to
101412 - "reconductor" the line.
101413 -
101414 -     [Later it seems to have turned out that Reconductor work is auto-
101415 -     matically exempt from GO 131-D, but the Relocation portion is
101416 -     considered to be subject to GO 131-D, provided it is not completed
101417 -     in advance of 951231, per ref SDS 4 line 271.]
101418 -
101419 -
101420 -
1015 -
Distribution. . . . See "CONTACTS"