DIARY: May 13, 2002 10:51 AM Monday; Rod Welch

Paul Robinson sent email asking about follow up on SDS.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - Sletten Construction Company         406 761 7920
020101 - Mr. Paul Robinson; Vice President
020102 - paul@sletten-inc.com
020103 - Executive Office

SUBJECTS
Sletten Construction Requests Removing Records Cites 880922
Case Study Broadwater Lessons Learned
SDS Saves Time and Money by Improving Management
Internet Object Organizational Memory Worry Accountability Confidenti
Confidentiality Fear Organizational Memory Marketing Customers Make S
Sletten Requests Removing Records on Broadwater Dam Project, Paul Rob
Robinson, Paul with Sletten Construction Inquires About SDS
Sletten Construction Inquires About SDS and Com Metrics, Paul Robinso

1610 -    ..
1611 - Summary/Objective
1612 -
161201 - Follow up ref SDS 19 0000, ref SDS 4 0000.
161202 -
161203 - Sent email to Paul asking if the explanation of SDS in POIMS,
161204 - submitted in the letter, ref DIP 1 0001, reflects his memory of
161205 - experience interacting with SDS on the Broadwater Dam project in 1988?
161206 -
161207 - Mentioned recent review on 020504 of FAR requirements that control
161208 - procurement of Sletten work with the federal government. ref SDS 20
161209 - 0001
161210 -
161211 -     [On 020517 called Paul to follow up. ref SDS 21 0001
161212 -