Gensler/Michael Willis/Kwan Henmi
600 California Street, Floor 1100
San Francisco, CA 94108



October 3, 1998


Prepared by:  Steven Hergert

 

Subject:  Moscone Center Expansion Project - Phase III
                 Project Number:  01.6250.000
                 Structural Coordination Meeting, Oct 1, 1998
                 Meeting Notes..... #65

Present
  1. FBA.................................. Hamid Fatehi
  2. FBA.................................. Alain Placido
  3. SDE.................................. Jack Laws (JL)
  4. SDE.................................. Jon Andrews (JA)
  5. JV Team/Gensler.............. Clonia Cautis (CC)
  6. JV Team/MWA................. Steven Hergert (SH)
  7. JV Team/KHA.................. Ivan Romero (IR)


Discussion

  1. JV team requested that FBA and SDE limit work in PG&E vault area pending final decision from client and studies currently underway by TEE.

    Action / Decisions Pending / Follow up

    JV team to forward information as soon as possible.

  2. FBA requested wind tunnel schedule of completion.

    Action / Decisions Pending / Follow up

    JV team requested FBA proceed with design. If trouble areas discovered in study, team will address at that time.

  3. Basement driveway will be lowered 3" due to elimination of mud slab and protection slab. Floor elevation at truck path "average" will be -4'-3". Kitchen floor elevation to remain as designed. Truck dock slab will be sloped 3"to edge.

    Action / Decisions Pending / Follow up

    AGS to modify ramp and drainage plan. KH team to coordinate.

  4. Details and clarifications requested by JV team were discussed.

    Action / Decisions Pending / Follow up

    See attached details for information provided.

  5. Other details needing structural direction were given to FBA and SDE.

    Action / Decisions Pending / Follow up

    Coordination to follow.

  6. JV team requested clarification on building movement at the property line at the existing mechanical building.

    Action / Decisions Pending / Follow up

    Jon to review and forward information to JV team.


Issues still pending:

  1. Penetrations (for mechanical ducts) through structure at Brace line B were discussed. A&P confirmed (via phone conversation with IR during meeting) that 2'- 11" clear is not sufficient space for their ducts. SDE will lower bottom members of engaged trusses 6" min.

    Issue being finalized by A&P. Alan currently coordinating/verifying.

    Action / Decisions Pending / Follow up

    SDE lowering steel 6".

    JV team to incorporate revisions.

    JV team notified A&P of steel modification.

    A&P will verify if penetrations are sufficient.

    [On 980929 Kwan Henmi developing solution, per JV Coordination meeting.]

    [On 981001 Structural Consultant notified of progress at Structural Coordination meeting.]

  2. Elevator framing was discussed. SDE confirmed framing diagrams had been sent to JV team.

    JV team requested modifications to steel tube sizes.

    KH team to provide sections and backgrounds to go to consultants 10/19/98.

    Action / Decisions Pending / Follow up

    SDE will reissue faxes sent prior.

    SDE confirmed requested tube dimensions are not feasible.

    SDE will provide possible sizes for IR/JV team.

    [On 981001 Kwan Henmi needs information for 50% design package, reported at Structural Coordination meeting.]

  3. All parties discussed framing concepts for the Howard Street entry plaza. SDE suggests extending basement walls to perimeter of plaza stairs. After additional discussion at the September 24 meeting, this option was agreed upon by all parties.

    At 10/1/98 meeting, SDE and FBA still coordinating.

    Action / Decisions Pending / Follow up

    JV team to modify base files and distribute. [On 981001 no progress reported on implementing solution at Structural Coordination meeting.]

  4. CC requested coordination between FBA and SDE for column locations in the basement.

    FBA and SDE have coordinated. Electrical engineering coordination (associated with NW corner electrical room) still pending. KH team to complete by 10/5/98.

    Action / Decisions Pending / Follow up

    FBA and SDE to coordinate.

    New drawings will be issued at 25% (September 30) deadline.

    [On 981001 JV team will verify electrical equipment will fit structural column layout, from discussion at Structural Coordination meeting.]

  5. Drawings of existing buildings were requested for SDE and FBA.

    Additional drawings from the city will be sent by JV team when located and forwarded by city.

    Action / Decisions Pending / Follow up

    JV team provided copies of what we currently have on file.

    [On 981001 initial submission of available drawings reported at Structural Coordination meeting.]

  6. Elevator shaft/elevator machine room framing to be resolved this week.

    CC requested steel framing member and column sizes (at elevators) and sketches from SDE by the end of the week.

    Sizes still being coordinated. JV drawings to be modified to incorporate structure.

    Action / Decisions Pending / Follow up

    JV team to meet with Al Williams 9/18/98.

    Information to be provided to SDE/FBA.

    Sketches to be provided by SDE late 9/18.

    KH team to resolve by 10/12.

    [On 981001 SDE had provided input, Kwan Henmi to resolve elevators, see Structural Coordination meeting.]

  7. Stair sections incorporating structure, verifying head clearances, and locating railing to be done by JV team (KHA) and forwarded to FBA and SDE.

    KH to provide sections for Hward street by 10/9.

    Action / Decisions Pending / Follow up

    JV team to complete. (KHA)

    Still pending.

    [On 981001 Kwan Henmi target to submit information is 981019, see Structural Coordination meeting.]

  8. JV team showed SDE ceiling hook location options.

    All hooks on 11'-3" grid to coordinate with main structural elements.

    Action / Decisions Pending / Follow up

    JV team to send electronic files of ceiling drawings to SDE. [On 981001 Kwan Henmi submitted hang point information following Structural Coordination meeting.]

  9. JV team and SDE reviewed framing at mechanical shafts on Minna Street.

    SDE would like to relocate framing to grid lines or slightly off center (within the flange of the column).

    Still pending at 10/1/meeting: "in progress" stair and louver study will determine framing locations.

    Action / Decisions Pending / Follow up

    JV team will study stair and shaft layout further.

    Direction on framing to be provided to SDE as soon as possible.

    [On 981001 WMA will prepare a drawing to study adjustmennts needed in structural framing, see Structural Coordination meeting.]

  10. With Paoletti present, SDE and JV team verified the thickened slab is required over the chiller room for sound dampening.

    Electrical floor boxes, currently sheet metal should be concrete, similar to plumbing boxes.

    Thickened slab issued not resolved. Verification of required weight, with Paoletti, still to occur.(150 v. 75 psf.)

    CC sent letter to RJA for code/fire rating interpretation.

    Action / Decisions Pending / Follow up

    SDE to confirm if concrete floor box enclosures possible.

    SDE confirmed 10/1. Detail to be provided.

    [On 981001 SDE provided 150 PSF slab design; will provide alternate design to soundproof slab for further study, see Structural Coordination meeting.]

    [On 981001 Life Safey consultant writing a letter on requirements for floor boxes; alternate designs for fireproofing will be developed, see Structural Coordination meeting.]

  11. CC recommends suspended elevator pits to be concrete.

    Action / Decisions Pending / Follow up

    SDE to note in design and JV team to incorporate into plans and sections.

    SDE confirmed corporated.

    [On 981001 SDE will submit design OA 981006. see Structural Coordination meeting.]

  12. FBA provided a detail illustrating the transition between the sandwich slab and the composite mat and topping slab.

    JV team will create plan diagram showing extent of sandwich slab vs. composite slab.

    Above information to be used in generating a cost study of the proposed alternate.

    (10/1 meeting: CC will forward to Hanscomb.)

    Action / Decisions Pending / Follow up

    FBA suggested a reduction in the 2'-6" rock section as a reduction alternate in lieu of eliminating the rock entirely.

    JV team will study options.

    Issue still pending. JV team to illustrate scope of "stepping" required with option

    [On 981001 coordination needed on impacts of design changes to floor slab. see Structural Coordination meeting.]

  13. FBA proposed options for clarifying the support of the north pre-function window wall. Connections between the window wall frame and the gravity column will be slotted.

    Coordination still pending.

    PS to detail enclosures and connections.

    Action / Decisions Pending / Follow up

    JV team confirmed the column and the window wall support steel connection will be clad/covered.

    Details to be provided by JV team.

    [On 981001 JV team will prepare details. see Structural Coordination meeting.]

  14. Currently there is no direction structurally for the exterior wall near the existing mechanical building.

    Action / Decisions Pending / Follow up

    JV team to study and provide direction.

    Issue still pending.

    [On 981001 Consideration to moving building 1.5' at Structural Coordination meeting.]

  15. Thermal expansion, related to the 100 degree figures provided by A&P, would translate to 2 1/2" of building "expansion" over the full width of the building (along 4th Street).

    FBA recommends thermal joints where structural systems change.

    Issue still pending.

    VERY CRITICAL ISSUE.

    Action / Decisions Pending / Follow up

    JV team recommends a second look at the 100 degree figure by A&P.

    JV team will consider recommendation and respond.

    FBA to confirm 100 degree variation.

    [On 981001 there was consideration of this subject at Structural Coordination meeting.]

  16. JV team to provide SDE with proposed damper relocations for SDE incorporation. Proposal provided.

    Proposal provided.

    Action / Decisions Pending / Follow up

    SDE to incorporate revisions

    JV team to provide additional direction at grid lines A, 1, and 6.

    [On 981001 information was provided, and more to follow for lines A, 1 and 6, as reported at the Structural Coordination meeting.]