DIARY: February 21, 1998 02:32 PM Saturday; Rod Welch

Received order and request to join GC in Chaikin v. Weinmann, AAA.

1...Summary/Objective
2...Order on Prehearing Matters from Preliminary Hearing on 980206
3...Payment of arbitration fees due by 980522
4...Schedule Another Preliminary Hearing on 980401
5...Notice of Arbitration Hearing Date
6...Claimant Files Demand for Arbitration Against GC
...Arbitrator's Consent for New Claim
.............demand says nature of dispute is:
.............demand shows dollar amount of claim: $100,000
.............shall be subject to arbitration upon the written demand of
.............subject to an initial presentation of the claim or dispute
.............American Arbitration Association and shall be made within
.............a.reasonable time after the dispute has arisen. The award
.............Contract, the Owner, after seven days written notice to


..............
Click here to comment!

CONTACTS 
0201 - Law Offices Langford               510 .......  fax or 800...
020101 - Mr. James R. Langford, III, Esq.
0202 - Law Offices, A.J. Keiley           408....      fax or 800...
020201 - Mr. Anthony J. Keiley, III, Esq.
0203 - Amer. Arbtrn Assn.                 415 981 3901 fax 781 8426
020301 - Ms. Marcela Taylor; Case Administrator =415 984 5433
020302 - Case Administration

SUBJECTS
Schedule
Preliminary Hearing
980206 Hearing
Joining Parties

0606 -    ..
0607 - Summary/Objective
0608 -
060801 - Follow up ref SDS 10 4223, ref SDS 9 3458.
060802 -
060803 - Received the AAA order issued to schedule discovery and other case
060804 - management preparing for the hearing based on the preliminary hearing
060805 - conducted on 980206.  Received the formal notice setting hearing to
060806 - begin 980622.  Received Claimant's demand for arbitration against the
060807 - General Contractor.  AAA requested arbitrator's consent to admit this
060808 - matter as a new claim in this case.
060809 -
060810 -     [AAA's 980225 letter replaces this 980219 letter based on adding a
060811 -     3rd party. ref SDS 12 2767]
060812 -
060813 - Submitted ref DIT 1 1290 granting consent to join GC.
060814 -
060815 -         [On 980304 received AAA letter transmitting Arbitrator's
060816 -         consent to the parties. ref SDS 14 3582]
060817 -
060818 - Reviewed contract between the Owner and the Contractor, and found
060819 - provisions on claims and arbitration. ref SDS 0 2534
060820 -
060821 -
060822 -
0609 -
0610 -
0611 - Progress
0612 -
061201 -  ..
061202 - Order on Prehearing Matters from Preliminary Hearing on 980206
061203 -
061204 - Received, ref DRT 1 2880, from AAA prepared by Marcela.  It notifies
061205 - the parties that Marcela has been assigned as the Case Administrator
061206 - to replace Nina King.
061207 -
061208 - This letter incorporates the arbitrator's order resulting from the
061209 - second preliminary hearing held on 980206. ref SDS 8 4450, which was
061210 - issued to AAA on 980213. ref SDS 9 3458, as Welch letter. ref DIP 2
061211 - 2668
061212 -
061213 -     [On 980227 received AAA letter dated 980225 that replicates the
061214 -     contents of this AAA letter dated 980219 except it is addressed to
061215 -     Foti and modifies amount of fees based on 3 party case. ref SDS 12
061216 -     2767]
061217 -
061218 -     [On 980227 issued letter to AAA making 980225 letter the official
061219 -     order replacing this 980219 letter. ref SDS 12 3519]
061220 -
061221 -
061222 -  ..
061223 - Payment of arbitration fees due by 980522
061224 -
061225 - The letter further instructs the parties to deposit equal shares of
061226 - arbitration expenses totalling approximately $6.4K each. ref DRT 1
061227 - 0937 to pay for 7 days of hearing. ref DRT 1 1627, per estimates by
061228 - parties on 980206. ref SDS 8 4311 and telecon with Marcela on 980220.
061229 - ref SDS 10 1701
061230 -
061231 - Parties are to deposit arbitration fees by 980522. ref DRT 1 1438
061232 -
061233 -     [On 980227 AAA's 980225 letter changes the amounts each respondent
061234 -     is to deposit based on 3 party case. ref SDS 12 8840]
061235 -
061236 -
061237 -
061238 -  ..
061239 - Schedule Another Preliminary Hearing on 980401
061240 -
061241 - AAA letter confirms another preliminary hearing on 980401. ref DRT 1
061242 - 2594, per second preliminary hearing on 980206. ref SDS 8 2640
061243 -
061244 -     [On 980227 received AAA letter dated 980225 that gives another
061245 -     notice of preliminary hearing on 980401, except it is addressed to
061246 -     Foti and includes the scope of the initial preliminary hearing for
061247 -     information purposes, since most of the issues have been resolved,
061248 -     ref SDS 12 2410]
061249 -
061250 -
061251 -  ..
061252 - Notice of Arbitration Hearing Date
061253 -
061254 - Follow up ref SDS 8 1309.
061255 -
061256 - Received the formal notice setting the hearing for 980622 beginning at
061257 - 1300, per preliminary hearing on 980206. ref SDS 8 1309, confirmed in
061258 - my letter to AAA. ref DIP 2 1860, and the order issued by AAA received
061259 - today, ref DRT 1 1723, per above. ref SDS 0 2343
061260 -
061261 -     [On 980227 received AAA letter dated 980223 that replicates the
061262 -     contents of this AAA letter dated 980219 except it is addressed to
061263 -     Foti. ref SDS 12 2410]
061264 -
061265 -
061266 -
061267 -
061268 -
061269 -
0613 -

SUBJECTS
Joining Parties
Demand for Arbitration, 980227

0805 -
080501 -  ..
080502 - Claimant Files Demand for Arbitration Against GC
080503 -
080504 - Received, ref DRT 3 1987, which is a letter from the AAA case
080505 - adminsitrator, Marcela Taylor, to the Claimant's counsel, Anthony J.
080506 - Keiley, III, Esq, which acknowledges receipt of Claimant's new demand
080507 - for arbitration against the general contractor.
080508 -
080509 - AAA letter says joined Respondent, Mark Foti, General Contractor, may
080510 - file a response to Claimant's additional Demand for Arbitration within
080511 - 10 days from date of letter, 980219. ref DRT 3 1544
080512 -
080513 -    ..
080514 -   Arbitrator's Consent for New Claim
080515 -
080516 -   AAA requests Arbitrator's consent under rule R8 for Claimant's claim
080517 -   against the General Contractor to be admitted. ref DRT 3 1639
080518 -
080519 -   Submitted ref DIT 1 1290 granting consent to join GC, per following
080520 -   analysis:
080521 -
080522 -         [On 980304 received AAA letter transmitting Arbitrator's
080523 -         consent to the parties. ref SDS 14 3582]
080524 -
080525 -      Rule R8 says...
080526 -
080527 -         A party may at any time prior to the close of the hearing
080528 -         increase or decrease the amount of its claim or counterclaim.
080529 -         Any new or different claim or counterclaim, as opposed to an
080530 -         increase or decrease in the amount of a pending claim or
080531 -         counterclaim, shall be made in writing and filed with the AAA,
080532 -         and a copy shall be mailed to the other party, who shall have
080533 -         a period of ten (10 days from the date of such mailing within
080534 -         which to file an answer with the AAA.  After the arbitrator is
080535 -         appointed no new or different claim or counterclaim may be
080536 -         submitted to that arbitrator except with the arbitrator's
080537 -         consent.
080538 -
080539 -   Rule R8 could be construed to mean that the Arbitrator must consent
080540 -   to a change from the original claim.  In this case, the request to
080541 -   join a claim against another party seems like an administrative
080542 -   matter for AAA.  The arbitrator's role is to ensure fairness to the
080543 -   parties by avoiding escalation of claims not previously notified. In
080544 -   the case, claims between Owner and Contractor are to have first been
080545 -   submitted to and decided by the Architect, ref SDS 0 3992, which
080546 -   provides the protection of unjust suprise or lack of time to prepare
080547 -   a defense.
080548 -
080549 -   The Contract says the Owner may bring a claim against the General
080550 -   Contractor within a reasonable time. ref SDS 0 2511
080551 -
080552 -   I prepared, ref DIT 1 1290, granting consent for Claimant's claim
080553 -   against Mark Foti to be admitted to the claim against Weinmann.
080554 -
080555 -
080556 - AAA letter confirms its receipt from Keiley, ref DRT 3 2384, and
080557 - submits to the Arbitrator the following documents:
080558 -
080559 -
080560 -   a.  Stipulation of parties to add GC as Respondent
080561 -
080562 -       Letter, ref DRT 3 3922, from Keiley (Claimant's counsel) to AAA
080563 -       notifying AAA that parties have agreed by stipulation to add an
080564 -       additional respondent the general contractor, Mark G. Foti,
080565 -       which was discussed at the second preliminary hearing on 980206.
080566 -       ref SDS 8 1945
080567 -
080568 -       The letter shows signature of James Langford, Esq, counsel for
080569 -       Respondent agreeing to stipulation.
080570 -
080571 -   b.  Demand for Arbitration Against GC
080572 -
080573 -       Fax cover sheet dated 980218 submitting 15 total pages:
080574 -
080575 -       Letter dated 980218, ref DRT 3 1492, which submits the demand
080576 -       for arbitration. ref DRT 3 1608  This letter cits para 10.8 of
080577 -       contract between Claimant and Respondent GC.
080578 -
080579 -       Demand for Arbitration dated 980212 names
080580 -
080581 -                      Mark G. Foti
080582 -                      3396 Sequoia Avenue
080583 -                      Redwood City, CA  94061
080584 -                      650 366 7301
080585 -
080586 -          ...demand does not list counsel for respondent.
080587 -
080588 -          ...demand says nature of dispute is:
080589 -             ..
080590 -             Claim against general contractor by owner for
080591 -             damages caused by breach of contrct and/or negligence.
080592 -
080593 -                 Demand does not state what contract provisions were
080594 -                 breached.
080595 -
080596 -               [On 980226 AAA advises that Respondent does not
080597 -               understand this claim. ref SDS 11 3212]
080598 -
080599 -               [On 980227 issued schedule for Claimint to specify
080600 -               claims by 980317. ref SDS 12 3386]
080601 -
080602 -
080603 -          ...demand shows dollar amount of claim:  $100,000
080604 -
080605 -                 Demand does show if this is an additional amount to
080606 -                 that claimed against the architect.
080607 -
080608 -                 The "punch list" submitted with Claimant's statement
080609 -                 of claim, ref DRP 5 1763, seems to include claims that
080610 -                 appear to relate to defective work, ref DRP 5 2206,
080611 -                 and failure to perform by the general contractor, per
080612 -                 second preliminary hearing on 980206. ref SDS 8 3088
080613 -
080614 -
080615 -       Abbreviated Form of Agreement Between Owner and Contractor
080616 -          ..
080617 -          This document is nearly impossible to read, because it
080618 -          is a fax of something that has been copied and faxed many
080619 -          times.
080620 -
080621 -          ...dated 940701
080622 -
080623 -               [On 980302 AAA will issue instructions for parties to
080624 -               submit legible documents for the case record. ref SDS 13
080625 -               1987]
080626 -
080627 -          ...shows architect as Kevin Weinman, the respondent in the
080628 -          instant case.
080629 -
080630 -          ...270 CD for completion
080631 -
080632 -          ...Article 6.1.4 seems to list drawings A1 - A20 and S0 -
080633 -          S10.  Cannot recognized any listing of mechanical or
080634 -          electrical drawings.
080635 -
080636 -          ...Article 7.2 says:
080637 -
080638 -             The Contract Documents shall not be construed to create a
080639 -             contractual relationship of any kind (1) between the
080640 -             Architect and Contractor, (2) between the Owner and a
080641 -             Subcontractor or ... (3) between any persons or entities
080642 -             other than the Owner and Contractor.
080643 -
080644 -          ...Article 9.7 says:
080645 -
080646 -             The Contractor shall be responsible to the Owner for the
080647 -             acts and omissions of the Contractor's employees,
080648 -             Subcontractors and their agents and employees, and other
080649 -             persons performing portions of the Work under a contract
080650 -             with the Contractor.
080651 -
080652 -          ...Article 9.8 says:
080653 -
080654 -             The Contractor shall review, approve and submit to the
080655 -             Architect shop Drawings, Product Data, Samples and similar
080656 -             submittals required by the Contract documents with
080657 -             reasonable promptness.  The Work shall be in accordance
080658 -             with approved submittals.  When professional certification
080659 -             of performance criteria of materials, systems or equipment
080660 -             is required by the Contract Documents, the Architect shall
080661 -             be entitled to rely upon the accuracy and completeness of
080662 -             such cerfication.
080663 -
080664 -          ...Article 10.1 says:
080665 -
080666 -                        Administration of the Contract
080667 -
080668 -                This Article may address scope of Architect's duty to
080669 -                provide Contract Administration cited in contract
080670 -                between Owner and Architect. per discussion at second
080671 -                preliminary hearing, ref SDS 8 3088, and prior review
080672 -                on 980129. ref SDS 6 1878
080673 -             ..
080674 -             The Architect will provide administration of the
080675 -             Contract and will be the Owner's representative (1) during
080676 -             construction, (2) until final payment is due and (3) with
080677 -             the Owner's concurrance, from time to time during the
080678 -             correction period described in para 18.1 [????].
080679 -
080680 -          ...Article 10.2 says:
080681 -
080682 -             The Architect will visit the site at intervals appropriate
080683 -             to the state of construciton to become generally familiar
080684 -             with the progress and quality of the completed Workd and
080685 -             to determine in general if the Work is being performed in
080686 -             a manner indicating that the Work, when completed, will be
080687 -             in accordance with the Contract Documents. However, the
080688 -             Architect will not be required to make exhaustive or
080689 -             continuous on-site inspections to check quality or
080690 -             quantity of the Work.  On the basis of on-site
080691 -             observations as an architect, the Architect will keep the
080692 -             Owner informed of progress of the Work and will endeavor
080693 -             to guard the Owner against defects and deficiencies in the
080694 -             Work.
080695 -
080696 -          ...Article 10.3 says:
080697 -
080698 -             The Architect will not have control over or charge of and
080699 -             will not be responsible for construction means, methods,
080700 -             techniques, sequences or procedures, or for safety
080701 -             precautions and programs in connection with the Work,
080702 -             since these are solely the Contractor's responsibility as
080703 -             provided in Paragraph 9.1 and 16.1.  The Architect will
080704 -             nto be responsible for the Contractor's failure to carry
080705 -             out the Work in accordance with the Contract Documents.
080706 -
080707 -          ...Article 10.4 says:
080708 -
080709 -             Based on the Architect's observations and evaluations of
080710 -             the Contractor's Applications for Payment, the Architect
080711 -             will review and certify the amounts due the Contractor
080712 -             and will issue Certificates for Payment in such amounts.
080713 -
080714 -          ...Article 10.5 says:
080715 -             ..
080716 -             The Architect will interpret and decide matters
080717 -             concerning performance under and requirements of the
080718 -             Contract Documents on written request of either the Owner
080719 -             or Contractor.  The Architect will make initial decisions
080720 -             on all claims, disputes or other matters in question
080721 -             between the Owner and Contractor, but will not be liable
080722 -             for results of any interpretations or decisions rendered
080723 -             in good faith.  The Architect's decisions in matters
080724 -             referring to asthetic effect will be final if consistent
080725 -             with the intent expressed by the Contract Documents.  All
080726 -             other decisions of the Architect, except those which have
080727 -             been waived by making or acceptance of final payment,
080728 -             shall be subject to arbitration upon the written demand of
080729 -             either party.
080730 -
080731 -          ...Article 10.6 says:
080732 -
080733 -             The Architect shall authority to reject Work which does
080734 -             not conform to the Contract Documents.
080735 -
080736 -          ...Article 10.7 says:
080737 -
080738 -             The Architect will review and approve or take other
080739 -             appropriate action upon the Contractor's submittals such
080740 -             as Shop Drawings, Product Data and Samples, but only for
080741 -             the limited purpose of checking for conformance with
080742 -             information given and the design concept expressed in the
080743 -             Contract Documents.
080744 -
080745 -          ...Article 10.8 says:
080746 -             ..
080747 -             All claims or disputes between the Contractor and
080748 -             the Owner arising out of or relating to the Contract, or
080749 -             the breach thereof, shall be decided by arbitration in
080750 -             accordance with the Construction Industry Arbitration
080751 -             Rules of the American Aribtration Association currently in
080752 -             effect unless the parties mutually agree otherwise and
080753 -             subject to an initial presentation of the claim or dispute
080754 -             to the Architect as required under Paragraph 10.5. Notice
080755 -             of the demand for arbitration shall be filed in writing
080756 -             with the other party to this Agreement and with the
080757 -             American Arbitration Association and shall be made within
080758 -             a reasonable time after the dispute has arisen.  The award
080759 -             rendered by the arbitrator or arbitrators shall be final,
080760 -             and judgement may be entered upon it in accordance with
080761 -             applicable law in any court having jurisdiction thereof.
080762 -             Except by written consent of the person or entity sought
080763 -             to be joined, no arbitration arising out of or relating to
080764 -             the Contract Documents shall include, by consolidation,
080765 -             joinder or in any other manner, any person or entity not a
080766 -             party to the Agreement under which such arbitration arises
080767 -             unless it is shown at the time the demand for arbitration
080768 -             is filed that (1) such person or entity is substantially
080769 -             involved in a common question of fact or law, (2) the
080770 -             presence of such person or entity is required if complete
080771 -             relief is to be accorded in the arbitration, (3) the
080772 -             interest or responsiblity of such person or entity in the
080773 -             matter is not insubstantial, and (4) such person or entity
080774 -             is not the Architect or any of the Architect's employees
080775 -             or consultants.
080776 -
080777 -      [See consideration on 980401.
080778 -
080779 -
080780 -          ...Article 15.2 says:
080781 -
080782 -             Payments may be withheld on account of (1) defective Work
080783 -             not remedied, (2) claims filed by third parties, (3)
080784 -             failure of the Contractor to make payments properly to
080785 -             Subcontractors or for labor, materials or equipment, (4)
080786 -             reasonable evidence that the Work cannot be completed for
080787 -             the unpaid balance of the Contract Sum, (5) damage to the
080788 -             owner or another contractor (6) reasonable evidence the
080789 -             the Work will not be completed iwth the Contract Time and
080790 -             the the unpaid balance would not be adequate to cover
080791 -             actual or liquidated damages for the anticipated delay, or
080792 -             (7) persistant failure to carry out the Work in accordance
080793 -             with teh Contract Documents.
080794 -
080795 -          ...Article 18.1 says:
080796 -
080797 -             The Contractor shall promptly correct Work rejected by the
080798 -             Architect for failing to conform to the requirements of
080799 -             the Contract Documents, whether observed before or after
080800 -             Substantial Completion and whether or not fabricated,
080801 -             installed or completed, and shall correct any Work found
080802 -             to be not in accordance with the requirements of the
080803 -             Contract Documents within a period of one year from the
080804 -             date of Substantial compliance with the contract or by
080805 -             terms of an applicable special warranty required by the
080806 -             Contract Documents.  The provisions of this Article 18
080807 -             apply to Work done by Subcontractors, as well as to Work
080808 -             done by direct employees of the Contractor.
080809 -
080810 -          ...Article 20.2 says:
080811 -
080812 -             If the Contractor defaults or persistently fails or
080813 -             neglects to carry out the Work in accordance with the
080814 -             Contract Documents or fails to perform a provision of the
080815 -             Contract, the Owner, after seven days written notice to
080816 -             the Contractor and without prejudice to any other remedy
080817 -             the Owner may have, may make good such deficiencies and
080818 -             may deduct the cost thereof, including compensation for
080819 -             the Architects's services and expenses made necessary
080820 -             thereby, from the payment then or thereafter due the
080821 -             Contractor.  Alternatively, at the Owner's optino and upon
080822 -             certification by the Architect that sufficient cause
080823 -             exists to justiyf such action, the Owner may terminate the
080824 -             Contract and take possession of the site and of all
080825 -             materials, equipment, tools and construction equipment and
080826 -             machinery thereon owned by the Contractor and may finish
080827 -             the Work by whatever method the Owner may deem expedient.
080828 -             If the unpaid balance of the contract Sum exceeds costs of
080829 -             finishing the Work, including cempensation for the
080830 -             Architect's services and expenses made necessary bhereby,
080831 -             such execss shall be paid to the Contractor, but if such
080832 -             costs exceed such unpaid balance, the Contractor shall pay
080833 -             the difference to the Owner.
080834 -
080835 -
080836 -
0809 -
Distribution. . . . See "CONTACTS"