S U M M A R Y


DIARY: October 17, 1996 11:18 AM Thursday; Rod Welch

Discussion with COE on Dutra RFP for debris removal.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Marcus Tikotsky; Contract Specialist =415 977 8509
020102 - Contracting Division
0202 - Corps of Engineers, Sausalito      415 331 0404 fax or 800...
020201 - Mr. Leonard SooHoo, P.E.; Chief; Construction Service Branch
0203 - COE, Oakland Harbor Project        510 532 4838 fax or 800...
020301 - Mr. Glen N. Chafe; Inspector =510 532 4838
0204 - Corps of Engineers, Sausalito      415 331 0404 fax or 800...
020401 - Mr. Mike Murphy; Project Engineer
020402 - Construction Service Branch =Telephone/fax

SUBJECTS
Inner Harbor Work Area, Schnitzer
Piling encountered, Schnitzer
Debris Removal Modification, 961017
Todd Turning Basin

0706 -    ..
0707 - Summary/Objective
0708 -
070801 - Follow up ref SDS 9 0000, ref SDS 8 4044.
070802 -
070803 - Developed plans for Leonard to prepare RFP.
070804 -
070805 -
070806 -
0709 -
0710 -
0711 - Progress
0712 -
071201 - Leonard asked for ideas to prepare the RFP. We discussed options for
071202 - about an hour.
071203 -
071204 - A key concern is avoiding the expense of the Antone, or otherwise
071205 - minimizing its cost on changed work.
071206 -
071207 - The RFP will ask for a unit price to perform Debris Removal and haul
071208 - unsuitable material to a landfill of Dutra's choice, including making
071209 - any disposal of the wood and other materials it chooses.
071210 - ..
071211 - Leonard will compute the area of the Schnitzer and the Todd
071212 - Wings and assume an average of 2 feet across the entire area, for the
071213 - purpose of determining a quantity to budget.
071214 -
071215 -        1.  Remove debris in Todd and Schnitzer Wings            CY
071216 -                                                            ----
071217 -        2.  Dispose of contaminated material                     Tons
071218 -                                                            ----
071219 -        3.  Dispose of suitable material at Galbraith            CY
071220 -                                                            ----
071221 -        4.  Dredge suitable material and dispose at
071222 -            Galbraith; add to bid item _______ for
071223 -            reduced efficiency working with Debris Removal       CY
071224 -                                                            ----
071225 -
071226 -     [See follow up discussion with Tom Keesling, ref SDS 11 line 128.]
071227 -
071228 - There was discussion of including in the RFP another item for debris
071229 - removal by the Antone once the hard material has been encountered.
071230 -
071231 - Marcus suggested not including such an item, but rather have the
071232 - Contractor submit a claim for extra expense, if any, in handling any
071233 - such debris that might be encountered.
071234 -
071235 - A similar approach might be NOT to include a pay item for increased
071236 - cost of dredging in combination with debris removal, item 4. It can be
071237 - part of the debris removal cost, item 1.
071238 -
071239 - General estimates based on discussions with the Contractor indicate
071240 - this RFP may cost from $500K to $1.5M.
071241 -
071242 - Leonard will issue an initial RFP for approximately $100K so Dutra can
071243 - mobilize and commence work immediately.
071244 -
071245 -     [See discussion with Tom Benero on issuing RFP at ref SDS 10 line
071246 -     70.]
071247 -
071248 -
071249 -
Distribution. . . . See "CONTACTS"