DIARY: December 14, 1994 12:50 PM Wednesday; Rod Welch

Revised Schedule per telecon with CDWR, Bill, Kevin.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 

SUBJECTS
CDWR review & comment on Schedule Notes
941205, 941213, 941214
Field Measure Switchyards & Finalize
Connect Transmission Line to Switchyards
Construct Space for Comm. Control Area by

1207 -    ..
1208 - Summary/Objective
1209 -
120901 - Follow up ref SDS 7 0001.
120902 -
120903 - Added edits requested by Lori Brown at ref SDS 8 line 89, and as
120904 - explained below.  Bill, Kevin, Tom and Tito were meeting in the
120905 - conference room, so I made distribution to them at that meeting.
120906 -
120907 - Submitted ref DIT 1 line 36 to Bill, transmitting the revised
120908 - schedule, ref OF 3.  This completes action item 2 from 941005
120909 - progress meeting, and action 2 from 941208 progress meeting, ref SDS
120910 - 3 line 130, and at ref SDS 3 line 357.
120911 -
120912 -
120913 -
120914 -  ..
1210 -
1211 -
1212 - Progress
1213 -
121301 - Created a new schedule, ref OF 3 to apply the language and logic
121302 - changes discussed today, ref SDS 8 line 83.
121303 -
121304 - For some reason could not complete spell check.  MS Project crashed
121305 - 4 times about 3/4 through the exercise.  Manually corrected the
121306 - obvious errors.
121307 -
121308 - To extend the duration of the transfer trip summary line, and, by
121309 - extension, completion of the SLO Tie Line so it is near PG&E's
121310 - completion date, ref SDS 8 line 90, I moved task GH0D5D, which is a
121311 - task for CDWR to provide space for the Transfer Trip, from completion
121312 - on 950811, to 951201.
121313 - ..
121314 - I also arbitrarily extended the durations of the tasks to take
121315 - field measurements and to connect to the hydro plant a few weeks each
121316 - so they show up better on the schedule.  These tasks now have the same
121317 - or slightly more time that the comparable tasks on Devils Den,
121318 - Bluestone and Polonio Pass pumping plants, even though the latter is
121319 - theoretically 3 times the work.  Similarly these tasks on SLO Hydro
121320 - have more time than shown on Casmalia Hills pumping plant, even though
121321 - the work is comparable.
121322 -
121323 -    [Later it turned out the SLO and Casmalia Hills scope was
121324 -    eliminated, per
121325 -
121326 -
121327 -
1214 -