S U M M A R Y


DIARY: December 10, 1994 09:36 AM Saturday; Rod Welch

Reviewed and analysed various work from yesterday, planned follow up.

1...Summary/Objective
2...Added Task to Remove Existing SMUD Line


..............
Click here to comment!

CONTACTS 

SUBJECTS
PG&E SDS Training, Tito
CDWR Meetings, Notes & Follow Up
Final Contract

0605 -    ..
0606 - Summary/Objective
0607 -
060701 - Followed up work at ref SDS 5 line 58.
060702 -
060703 - Analysed results of the session yesterday with Tito.  Completed record
060704 - of work on CDWR notes ref SDS 3 line 43.  I need to call and get
060705 - attendees on Monday.  The list Lori sent is not legible.
060706 -
060707 - Completed notes of discussions on Gold Hill SMUD contract
060708 - preparations, ref SDS 4 line 49.
060709 -
060710 -
060711 -
0608 -

SUBJECTS
Gold Hill Upgrade, Controls, Schedule
Remove Existing Line, SMUD
SMUD Removes Existing Line
941126b; 941126a
Relocate Line, Cost & Schedule Impacts

1108 -
110801 -  ..
110802 - Added Task to Remove Existing SMUD Line
110803 -
110804 - Reviewing discussions on SMUD contract, ref SDS 4 7777, showed that
110805 - the Schedule does not have an activity for removing the existing line
110806 - in SMUD's 57' right of way, being conveyed to PG&E.
110807 -
110808 -      This has been a major issue of discussion, but was still over-
110809 -      looked in the 940920 Schedule, and as a result was omitted from
110810 -      subsequent revisions, predicated on information from project
110811 -      functional managers.
110812 -
110813 -      It was discovered by attempting to assign an SDS "subject" and
110814 -      finding there none had been created.
110815 -
110816 -          [See analysis of "Murphy's Law" at ref SDS 6 0000.]
110817 -
110818 -
110819 - Added this task to Schedule, ref OF 1, and ref OF 2.  Decided not to
110820 - make a new Schedule because it does not represent anything new pre-
110821 - sented by PG&E management.
110822 -
110823 - Will sequence this task after PG&E gives "Satisfactory Notice" that
110824 - the construction will proceed.  It just needs to be done prior to
110825 - PG&E beginning construction of the new facilities.
110826 -
110827 - Assigned this work of revising the Schedule to task BHD because it
110828 - only arises from the fact that the line is being relocated.
110829 -