THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700


S U M M A R Y


DIARY: September 26, 1994 12:20 PM Monday; Rod Welch

Called Bob Masuoka re PG&E CDWR schedule matters.

1...Summary/Objective
....Comment


..............
Click here to comment!

CONTACTS 
0201 - PG&E Building & Land Svcs.         415 973 8273 fax or 800...
020101 - Mr. Robert Masuoka; Room 2027, Mail Code H21A =415 973 8273

SUBJECTS
Coastal Branch Aquaduct, CDWR
Interface with CDWR Activities
Delays, General, CDWR Schedule
Pipeline Reach No. 1, by CDWR
Construct; Action Items, 940922 Meeting CDWR in Sacramento on

0907 -    ..
0908 - Summary/Objective
0909 -
090901 - Followed up work at ref SDS 15 line 113, and discussion with Kevin
090902 - Winthrow at ref SDS 16 line 262.
090903 -
090904 - Left message for Bob to call on this.
090905 -
090906 - This completes work on Action Item #3 at ref SDS 14 line 107.
090907 -
090908 -
0910 -
0911 -
0912 - 1305 Bob called back
0913 -
091301 - Bob said he has returned Lori's call at ref SDS 14 line 184.
091302 -
091303 - He said CDWR's construction easement is 60' wide and 60' beyond that,
091304 - for construction room.  He expects there will be spoils and
091305 - construction activity in the vicinity of the TL route, so the pipeline
091306 - must be constructed in advance of building the TL, including removal
091307 - of spoils.
091308 -
091309 -    Comment
091310 -
091311 -    It seems to me the requirement Bob proposed at ref SDS 8 line 157,
091312 -    and was questioned by Lori at ref SDS 14 line 165, should remain
091313 -    for this task.
091314 -
091315 -    It is not practical for PG&E to build ahead of the pipeline,
091316 -    because the poles and the line would be an obstical to the
091317 -    construction operation, although a lot of pipelines have been built
091318 -    next to power lines.  This would be the best solution, but it is
091319 -    unlikely the pipeline contractor would agree to this without an
091320 -    adjustment in compensation.
091321 -
091322 -    Therefore, it really seems that the start of TL construction should
091323 -    be based on the projected end of pipeline construction, minus the 3
091324 -    or 4 months needed to construct the TL line, because otherwise PG&E
091325 -    will run out of work, will have to stop and start, and this will
091326 -    cost extra money.
091327 -
091328 -    The current schedule sort of reflects this sequencing, except there
091329 -    is no actual tie from CDWR's work to PG&E's task of staking, so if
091330 -    CDWR's schedule slips, it does not show any impact on PG&E's work.
091331 -
091332 -
091333 -
091334 -
091335 -
0914 -
0915 -
0916 - 1528 called Bob back
0917 -
091701 - Asked if he has a copy of the pipeline that shows the TL, so we can
091702 - evaluate the issue of impacts and sequencing, per discussion with Bill
091703 - at ref SDS 16 line 306.
091704 -
091705 -
091706 -
091707 -
0918 -
0919 -
0920 - 1536 Bob called back
0921 -
092101 -
092102 -
092103 -
092104 -
092105 -
092106 -
0922 -

SUBJECTS
FAA Application Filing Requirements
FAA Notification, File

1205 - Summary/Objective
1206 -
120601 - Has Bob notified Ed Hills that the FAA app needs to be filed prior to
120602 - 950301 otherwise a 45 - 90 day delay could be encountered by requiring
120603 - another filing, per ref SDS 14 line 448.
120604 -
120605 - Bob said he has not done this, but will do so.  He believes the
120606 - information was submitted to Ed as part of other information from FAA,
120607 - but he will call Ed and point this out, per Lori's request.
120608 -
120609 -
120610 -
120611 -
Distribution. . . . See "CONTACTS"