S U M M A R Y


DIARY: September 19, 1994 03:09 PM Monday; Rod Welch

Meeting with Bob to review schedule on CDWR.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Building & Land Svcs.         415 973 8273 fax or 800...
020101 - Mr. Robert Masuoka; Room 2027, Mail Code H21A =415 973 8273

SUBJECTS
Coastal Branch Aquaduct, CDWR
Interface with CDWR Activities
Devils Den, Bluestone, Polonio Pass
70 KV Transmission Line Arco - Polonio Pass
Plan Maps & Legal Descriptions, Prepare
Easement Terms & Conditions per PG&E
Easement Language, PG&E submit

1009 -    ..
1010 - Summary/Objective
1011 -
101101 - Followed up work at ref SDS 6 line 107.  Reviewed schedule with Bob
101102 - and developed adjustments to present to Bill DeHart.  Submitted copy
101103 - of current schedule to Bob.
101104 -
101105 -
101106 -
1012 -
1013 -
1014 - Discussion
1015 -
101501 - Bob said task DD0D Prepare Plan Maps and Legal Descriptions for Arco
101502 - Sub to Devils Den PP, is complete.
101503 -
101504 -     He feels there should be a new task for PG&E and CDWR to agree on
101505 -     the language for obtaining easements.  Work on Easements cannot
101506 -     begin until that task is complete.
101507 -
101508 -     Bob said Jeff Little is working on it.  He called Jeff while we
101509 -     were meeting and left a message for him to advise on status of his
101510 -     work.
101511 -
101512 -        [This indicates PG&E has performed Action Item #7 from Aug 18
101513 -        meeting with CDWR in Sacramento, ref SDS 1 line 131.]
101514 -
101515 -
101516 -
1016 -

SUBJECTS
RW, Acquire by CDWR, Review by PG&E

1104 - Summary/Objective
1105 -
110501 - Reviewed this scope based on discussions with Bill at ref SDS 3 line
110502 - 232.
110503 -
110504 - Bob said it can take from 9 months to a year to obtain easements, in-
110505 - dicating that the approximate 9 months shown for task DD0H may be
110506 - optimistic.
110507 -
110508 -     Since CDWR indicated at the meeting in Sacramento on Aug 18, 1994
110509 -     that they would make an expedited effort, in light of the delay in
110510 -     starting the task, ref SDS 1 line 296, the planned duration is
110511 -     appropriate, see Action Item ref SDS 1 line 98.
110512 -
110513 -
110514 -
110515 -
1106 -

SUBJECTS
Permit from Caltrans for Hwy 33 & 46
Plan Maps & Legal Descriptions, Prepare
Engineering

1406 - Summary/Objective
1407 -
140701 - Bob said task DD1D, Engineering, controls task DD0K Obtain Caltrans
140702 - Permit.  He indicated there is no link from task DD0D Prepare Plan
140703 - Maps, ..., to DD0K.
140704 -
140705 -
140706 -
1408 -

SUBJECTS
Cultural Resource & Biological Pre
Stake for Construction
Pipeline Reach No. 1, by CDWR
Construct

1807 - Summary/Objective
1808 -
180801 - Bob indicated that the sequence of construction will be that after
180802 - CDWR completes the pipeline work, and the grades are fully restored,
180803 - then PG&E will begin task DD2H Staking for construction.  He said this
180804 - work has to be done before task DD2D Cultural Resource and Biological
180805 - Pre-Construction Survey, can commence, because the latter operation
180806 - needs to know where PG&E's poles will be installed, which is deter-
180807 - mined by the survey.
180808 -
180809 -     Bob indicated a 2 week lag in starting task DD2D should be
180810 -     adequate.
180811 -
180812 -
180813 - I will review this with Bill to see if there are other considerations
180814 - that account for the current sequencing of having these tasks run
180815 - parallel, rather than sequenced, with some lag.
180816 -
180817 - Bob reviewed the notes for task DD3D Pipeline Reach No. 1, by CDWR and
180818 - seemed satisfied it adequately defines the scope of the work needed to
180819 - be accomplished in order for PG&E to commence.  He mentioned specifi-
180820 - cally that PG&E needs finish grades to be restored prior to staking
180821 - the line, so PG&E's engineering will work in the field.  I will add
180822 - something to make this point clear.
180823 -
180824 -     [See follow up at ref SDS 7 line 298.]
180825 -
180826 -
180827 -
1809 -

SUBJECTS
San Luis Obispo Hydro Interconnectoin
115 KV Transmission Line
FAA Notification, File

1906 - Summary/Objective
1907 -
190701 - Bob said task GD1L must complete NLT 950301, otherwise it will be
190702 - necessary to re-open an application which can take another 45 to 90
190703 - days.
190704 -
190705 -    Is there someway to reflect this in the schedule.
190706 -
190707 -
190708 -
1908 -

SUBJECTS
Culturl Resources & Biological Pre
Stake for Construction
Construction

2206 - Summary/Objective
2207 -
220701 - Bob recommends making the same sequence changes to this part of the
220702 - schedule that were recommended for the Arco - Polonio Pass 70 kV line.
220703 -
220704 -
220705 -
220706 -
220707 -
220708 -
2208 -

SUBJECTS
Casmalia Plant Interconnection
115 KV Transmission Line
Survey

2306 - Summary/Objective
2307 -
230701 - Bob said this work was completed on 940916, last Friday.
230702 -
230703 -
230704 -
2308 -

SUBJECTS
Culturl Resources & Biological Pre
Stake for Construction
Construction

2606 - Summary/Objective
2607 -
260701 - Bob recommends making the same sequence changes to this part of the
260702 - schedule that were recommended for the Arco - Polonio Pass 70 kV line.
260703 -
260704 -
260705 -
2608 -

SUBJECTS
Delays, GO 131-D
Permits, GO 131-D
Interface with CDWR Activities

2906 - Summary/Objective
2907 -
290701 - Bob feels the current delays that seem possible or even likely under
290702 - the revised schedule that integrates CDWR schedule work, will cause
290703 - the GO 131-D permit problem to be unavoidable.
290704 -
290705 - This will be presented at the meeting with CDWR on Thursday, 940922.
290706 -
290707 -
Distribution. . . . See "CONTACTS"