DIARY: September 26, 1994 08:49 AM Monday; Rod Welch

Modified CDWR schedule to reflect new information.

1...Summary/Objective

ACTION ITEMS.................. Click here to comment!

1...I am just guessing, but made the links on the Caltrans and Aqueduct

CONTACTS 

SUBJECTS
Coastal Branch Aquaduct, CDWR
Interface with CDWR Activities
Delays, General, CDWR Schedule
Pipeline Reach No. 1, by CDWR
940926 Revisions from 940922 meeting

0807 -    ..
0808 - Summary/Objective
0809 -
080901 - Follow up ref SDS 18 0000.
080902 -
080903 - Applied changes discussed with Bill.
080904 -
080905 - These changes were submitted on 940926. ref SDS 17 0001.
080906 -
080907 - After submitting that schedule, reflecting the way CDWR would like the
080908 - project to go, ref OF 8 0001, was prepared reflecting what seems like
080909 - the actual or most likely sequencing based on industry practice.
080910 -
080911 -
080912 -
080913 -
0810 -
0811 -
0812 - Schedule Changes
0813 -
081301 - Completed entering the notes that clarify the scope of tasks and
081302 - understandings from discussions with Lori Brown, per
081303 -
081304 - Conformed notes so common tasks at different WBS levels are explained
081305 - uniformly.
081306 -
081307 -
081308 -
0814 -

SUBJECTS
Arco - Devils Den PP
Devils Den - Polonio PP

1005 -
100501 - Broke this up per analysis at ref SDS 15 line 128, to reflect the
100502 - discussions with Veronica Hicks and Lori Brown at ref SDS 14 line 400,
100503 - and with Kevin Coffee at ref SDS 15 line 164.
100504 -
100505 -
100506 -
1006 -

SUBJECTS
Arco - Devils Den PP

1104 -
110401 - Broke this up per analysis at ref SDS 15 line 128, to reflect the fact
110402 - that the work from Arco - Devils Den needs to be performed prior to
110403 - mid-Apr 1995, per Mary Bolland's memo of Sep 20, 1994, ref SDS 14 line
110404 - 353, and discussion with Kevin Coffee ref SDS 15 line 176.
110405 -
110406 -     This section is not within the pipeline area of operations, and
110407 -     so can be done independent of that work.
110408 -
110409 -
1105 -

SUBJECTS
Devils Den - Polonio Pass PP
Pipeline Reach No. 1, by CDWR

1305 -
130501 - The section from Devils Den to Polonio Pass, is within the pipeline
130502 - construction zone, and so should be performed after the pipeline work
130503 - is complete, see analysis at ref SDS 19 line 87.
130504 -
130505 -     As a result, I created a link to show completion of the pipeline
130506 -     should lag start of the work on the TL by 8 weeks.  This is just
130507 -     a guess, 2 weeks is probably better to insure PG&E has full
130508 -     access to its work area.
130509 -
130510 -
130511 - I am just guessing, but made the links on the Caltrans and Aqueduct
130512 - crossing permits control this work instead of the TL from Arco to
130513 - Devils Den.
130514 -
130515 -    [turned out this was an error.  Bill said on 940927, that these
130516 -    permits are for work in the Arco Sub - Devils Den line; I made
130517 -    that change.]
130518 -
130519 -
130520 -
130521 -
130522 -
1306 -

SUBJECTS
SLO Hydro, Transmission Line, Engineering
Casmalia, Transmission Line, Engineering

1505 -   ..
150501 - Looks like we can reduce this time frame by a few months per
150502 - discus- sion with Charles Jones at ref SDS 18 line 172.
150503 -
150504 - Since we are still working with CDWR to develop adequate sequencing, I
150505 - want to hold off on changing these durations until the correlation
150506 - with CDWR work is more firmly settled.  These changes were not
150507 - reflected in the schedule for 940923, ref OF 7, but were entered for
150508 - evaluation purposes in the new schedule prepared today, ref OF 8.
150509 -
150510 -    These changes result in Casmalia showing it will complete on Nov 6,
150511 -    1995, about 3 weeks prior to the contract completion date of Dec 1,
150512 -    1995.
150513 -
150514 -    [This new schedule dated 940926 was submitted to Lori on 940927,
150515 -    per ref SDS 20 line 50.]
150516 -
150517 -
150518 -
1506 -

SUBJECTS
SLO Hydro, Transmission Line, Engineering
Casmalia, Transmission Line, Engineering
Material Lead Time

1706 -
1707 -
170701 - Looks like we can reduce this time frame by a few months per discus-
170702 - sion with Kevin Winthros at ref SDS 18 line 216.
170703 -
170704 - Since we are still working with CDWR to develop an adequate sequenc-
170705 - ing, I want to hold off on changing these durations until the correla-
170706 - tion with CDWR work is more firmly settled. These changes were not
170707 - reflected in the schedule for 940923, ref OF 7, but were entered for
170708 - evaluation purposes in the new schedule prepared today, ref OF 8.
170709 -
170710 -
170711 -
1708 -

SUBJECTS
Arco - Polonio Pass
Stake for Construction
Pipeline Reach No. 1, by CDWR
Construct

2007 -
200701 - See discussion about final grades at ref SDS 18 line 281.
200702 -
200703 - I want to leave the notes about the need to have CDWR restore the
200704 - area to final grades through the area were CDWR's other contractors
200705 - are working, which is the pipeline and plant areas.
200706 -
200707 -
200708 -
200709 -
200710 -
200711 -