DIARY: March 22, 89 06:23 AM .......; Rod Welch

Job progress inspection, Sletten punch list review.

1...Summary/Objective
2...Cofferdam Removal About 25% Complete, Progress May Improve
3...Punch list Action Items Pending
4...Runner Blades
5...Inventory of piping

ACTION ITEMS.................. Click here to comment!

1...Accordingly, Sletten is on notice to perform the items listed.
2...This document does not appear to have been issued to the contractor.
3...Engineer to issue determination on quality and standards of
4...This sounds like an Engineer's determination is needed.
5...As of 890322, these determination appear to be pending.
6...I suggested that documents of this kind should be dated showing the

CONTACTS 

SUBJECTS
Sletten Contract
Progress Inspection

0604 -    ..
0605 - Summary/Objective
0606 -
060601 - Entered notes from inspection yesterday.
060602 -
060603 -
060604 -
0607 -
0608 -

SUBJECTS
Sletten Contract
Progress Inspection
Cofferdam removal, upstream

0806 -
080601 - Cofferdam Removal About 25% Complete, Progress May Improve
080602 -
080603 - Completed removal of about 25% of the sheets and did the first lift of
080604 - excavation.  Sletten is about 20% complete with the activity.
080605 -
080606 - The rest of the work may go more more quickly because the dewatering
080607 - culvert pipes had to be removed and is a one time task.
080608 -
080609 - It appears the backhoe requires about 4 hours to mobilize (switch
080610 - places with the crane), and excavate about 30 feet of berm.  It should
080611 - take less than that to remove the piling for that stretch.
080612 -
080613 -
0807 -

SUBJECTS
Sletten Contract
Punch List, Civil

1205 -
120501 -  ..
120502 - Punch list Action Items Pending
120503 -
120504 - Norm asked yesterday, ref SDS 3 line 1301, about the status of this.
120505 -
120506 -    [On 890324 advised Clyde of status. ref SDS 4 7391]
120507 -
120508 - I examined Tudor's file #706.
120509 -
120510 - Mechanical
120511 -
120512 -   Hal sent a letter to Sletten dated 890314, based on an inspection
120513 -   by K.M. Chen, made on 890310 (see ref DCT 2).
120514 -
120515 -   Accordingly, Sletten is on notice to perform the items listed.
120516 -
120517 -
120518 -
120519 - Punch List (see ref DCT 1)
120520 -
120521 -   This is a document in the file titled:  Walk Through Inspection,
120522 -   Tuesday, February 7, 1989.  It shows Sletten and DNRC personnel
120523 -   attended inspection.
120524 -
120525 -   This document does not appear to have been issued to the contractor.
120526 -
120527 -   A fax was sent to Clyde on 890303.
120528 -
120529 -
120530 -   Item #9 states:
120531 -
120532 -     Engineer to issue determination on quality and standards of
120533 -     finish work.
120534 -
120535 -
120536 -   Item #10 states:
120537 -
120538 -     Tudor/DNRC disposition louver in the stairway entrance.
120539 -
120540 -   This sounds like an Engineer's determination is needed.
120541 -
120542 -   Items #13, 14, 28, 33, 35, 38 - 41, 44 & 57 require similar
120543 -   Engineer determinations.
120544 -
120545 -   As of 890322, these determination appear to be pending.
120546 -
120547 -
120548 -   While driving home, JoAnn indicated Jeff recently dictated
120549 -   revisions which she has entered.  She also advised that Paul was in
120550 -   the office a week or so ago and requested a copy of the punch list
120551 -   document.  He got a copy of the earlier version, prior to Jeff's
120552 -   recent edits.
120553 -
120554 -   I suggested that documents of this kind should be dated showing the
120555 -   evolution of the record, and that when copies are issued, this
120556 -   information should also be shown in the file.
120557 -
120558 -   She will take care of this tomorrow.
120559 -
120560 -
120561 -
1206 -
1207 -

SUBJECTS
Voith Contract
Progress Inspection

1405 -
140501 - Runner Blades
140502 -
140503 - Another blade was moved into the Powerhouse today for installation.
140504 - There are two left still outside.
140505 -
140506 -
140507 - Inventory of piping
140508 -
140509 - Didn't get this done today.
140510 -
140511 - We should know what systems are involved and the status.  Ron
140512 - Dusterdick was recently on site and evaluated the Voith Contract
140513 - progress.  Perhaps he generated a report showing this status.
140514 -
140515 - Ken's intent to go to double shifts to improve progress was set back
140516 - as a result of the union strike that came up today.
140517 -
140518 - Voith fired a pipefitter for poor progress, and this led to a walkoff.
140519 -
140520 -
140521 -
140522 -
1406 -