THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700
rodwelch@pacbell.net


S U M M A R Y


DIARY: September 15, 1988 03:57 PM .......; Rod Welch

Continue DTL Findings, analysis of Voith letter, 880912.

1...Summary/Objective
2...Voith Makes False Representations to Engineer, Need Greater Scrutiny
...Comment
3...Tolerances
...Comment
4...Assembly Defects
...Comment
5...Voith complains of "Misinterpretation"
...Comment
6...Reasons for Out of Tolerance Condition
.....Comment
.....Comment
.....Comments
.....Comment


..............
Click here to comment!

CONTACTS 
0201 - O-0394 0201 Voith Hydro, Inc.
020101 - Mr. Greg Snyder, Project Manager, Projects, Western Region

SUBJECTS
Draft Tube; Prepare findings
Prelim Claim Analysis

0704 -
0704 -    ..
0705 - Summary/Objective
0706 -
070601 - Follow up ref SDS 3 0000.
070602 -
070604 -  ..
070605 - Voith Makes False Representations to Engineer, Need Greater Scrutiny
070606 -
070607 - Received from Jeff this afternoon, the letter from Greg Snyder for
070608 - Voith which was to have been submitted on 880909. ref SDS 2
070610 -  ..
070611 - Voith's letter is incorrect on representations Voith made to the
070612 - Engineer (e.g., tolerances, see below. ref SDS 0 7650).  Voith's
070613 - letter is internally conflicting throughout and presents a warning
070614 - about the integrity, communications, and/or competence of Voith, which
070615 - requires correction in order to avoid harm to Tudor and the State.
070617 -  ..
070618 - This requires increased scrutiny of Voith's work, e.g., shop drawings,
070619 - schedules and progress at off-site facilities.
070620 -
070621 -      [On 880916 recommend Tudor take action to improve communication
070622 -      with Voith and that Voith comply with contract. ref SDS 4 1135]
070623 -
070624 -      [On 880917 discussed with Jeff. ref SDS 5 8482]
070626 -       ..
070627 -      [On 880919 Jeff concurs with recommendations. ref SDS 6 3280]
070629 -       ..
070630 -      [On 880921 reviewed with Tudor's senior executive for project,
070631 -      Clyde Earnest. ref SDS 7 8526]
070633 -       ..
070634 -      [On 880925 clarified Welch assignment. ref SDS 8 2475]
070636 -  ..
070637 - Voith not only fails to offer rational, technical support for its
070638 - Field Representative's instructions, but actually disclaims the
070639 - necessity for same.
070641 -  ..
070642 - Voith management at best recalls differently material understandings
070643 - reached with Tudor.  It pervasively misapplies and misstates the
070644 - record.
070646 -  ..
070647 - The letter fails to show the following factors that are important to
070648 - the issue...
070649 -
070650 -     1.  The tolerances in the 880803 Directive are reasonable and
070651 -         necessary to the success of the project.
070652 -
070653 -     2.  Such tolerances could be achieved by following Voith's field
070654 -         instructions.
070656 -          ..
070657 -     3.  Voith's field instructions would not materially increase the
070658 -         cost of performance relative to what was incurred (in other
070659 -         words, it cost the same to do it right as to do it according
070660 -         to Sletten's "standard procedures."  This is important because
070661 -         it removes the relevance of the failure to disclose a
070662 -         particular tolerance.
070664 -          ..
070665 -     4.  Need a few examples where Voith has successfully coordinated
070666 -         assembly and installation of similar work on other projects
070667 -         under comparable contract terms.
070668 -
070670 -  ..
0707 -
0708 -
0709 - Detailed Analysis
0710 -
071001 - Initially Greg cites "NEMA bulletin 'Hydraulic Turbine and governor
071002 - Field Erection Information', the manufacturer's field representative
071003 - should not have to instruct the contractor's personnel in their
071004 - crafts, ..."
071006 -    ..
071007 -   Comment
071008 -
071009 -   The objective of this passage is unclear.  It sounds like Voith is
071010 -   disclaiming responsibility for giving instructions to Sletten, as if
071011 -   the underlying concept of the Sletten contract provisions are either
071012 -   incorrect, or irrelevant.  One could draw from this language support
071013 -   for Sletten's position that the contractor is entitled to rely on
071014 -   its own craftsmen to install according to written instructions.
071015 -   Since Sletten did not receive written instructions until after it
071016 -   made the errors, it might not be liable for such errors.
071018 -    ..
071019 -   Of course this particular industry reference was not cited in the
071020 -   Sletten contract.  Instead the contract specifies the manufacturer's
071021 -   field representative will be consulted.  Obviously, the Owner is
071022 -   entitled to purchase the level of support it wishes.
071024 -    ..
071025 -   Further, why didn't Voith recommend this view when it was consulted
071026 -   for specification language during the preparation of the Sletten
071027 -   contract bidding documents (if in fact it was consulted)?
071029 -    ..
071030 -   Why is this language in the letter, particularly in light of
071031 -   subsequent passages that indicate the importance of following
071032 -   manufacturer's instructions (see page 2 item #2, para 2)?
071033 -
071035 -  ..
071036 - Tolerances
071037 -
071038 - Voith contends "On August 15, 1988 we reviewed in a conference call
071039 - with Jeff Ghilardi his fax of August 8, 1988 and arrived at a
071040 - tolerance to be used for erection and installation.  It was agreed
071041 - that the column entitled 'August 3, 1988 Determination' in his fax was
071042 - to be used, except that Voith agreed to accept draft tube flange
071043 - flatness/plumb and roundness of [+ or -] 0.030"..."
071044 -
071045 -       [On 880917 Voith's field superintendent, Ken Carlson, advised
071046 -       Tudor that Voith's letter is wrong. ref SDS 5 8482]
071048 -        ..
071049 -       [On 880919 Ken Carlson provided diary notes showing Voith's
071050 -       letter on 880912 is incorrect. ref SDS 6 8476]
071051 -
071053 -    ..
071054 -   Comment
071055 -
071056 -   Jeff's Diary conflicts with the above position.  It is dated 880816
071057 -   rather than 880815, though this may reflect the fact that it was
071058 -   dictated one day and transcribed another.  What is critical is that
071059 -   it states:  "With regard to flange flatness the flange must be flat
071060 -   to within plus or minus ten-thousands."
071062 -    ..
071063 -   This is a material difference.
071065 -    ..
071066 -   The net impression results that Voith conveyed tolerances to Tudor
071067 -   at the job site that were desirable rather than necessary.
071069 -    ..
071070 -   Such impression arises from the entire body of Voith communications
071071 -   beginning in May 1988, all of which lack specific tolerance
071072 -   valuations, yet stridently insist that tolerances are necessary, as
071073 -   presented in Voith communications beginning in May 1988.
071075 -    ..
071076 -   The difficulty is that Tudor has consistently maintained that such
071077 -   tolerances are necessary when apparently they are not.  Voith is
071078 -   saying in effect that it did not give Tudor reasonable grounds to
071079 -   believe such tolerances are necessary.
071080 -
071082 -  ..
071083 - Assembly Defects
071084 -
071085 - Voith maintains it recognized assembly deficiencies in May but that
071086 - "... this situation did not exist when Voith's Fred Gross left the
071087 - site on May 25, 1988, ..."  "The only record [of as built tolerances]
071088 - in this case appears to be F, Gross's internal report, a copy of which
071089 - is attached."
071091 -    ..
071092 -   Comment
071093 -
071094 -   The F. Gross report attached to the Voith letter does not indicate
071095 -   that a "... situation did not exist ..." and contains no information
071096 -   about tolerances.
071097 -
071098 -   What appears important about the record is that Voith did not take
071099 -   any field measurements during assembly to determine tolerance.  It
071100 -   seems that if the unit does not meet required tolerances after
071101 -   assembly, then it could not be expected to do so after being placed
071102 -   in the Powerhouse.  This conduct might be construed as an admission
071103 -   that tolerance requirements are less significant than was later
071104 -   imposed on the contractor.
071106 -    ..
071107 -   For Voith to maintain its position, it must establish that the
071108 -   tolerances it requires are an ordinary result of following its
071109 -   assembly instructions, and that the failure to do so would be
071110 -   expected to cause the deviations encountered.  It must further show
071111 -   that the failure to disclose such instructions is accepted practice,
071112 -   in that a reasonable contractor would expect to encounter
071113 -   difficulties without having such instructions, and thereby would be
071114 -   alerted not to proceed without same.
071116 -    ..
071117 -   The question is whether it is enough merely to say that the work is
071118 -   to be performed in the presence of the Field Representative, without
071119 -   giving some warning that certain critical assembly information will
071120 -   be provided that is not otherwise available.
071121 -
071122 -
071124 -  ..
071125 - Voith complains of "Misinterpretation"
071126 -
071127 - Voith states
071128 -
071129 -      "... there has been a surprising amount of basic
071130 -      misinterpretation of dimensions on Voith drawings, most of which
071131 -      are unrelated to installation tolerances."
071132 -
071134 -    ..
071135 -   Comment
071136 -
071137 -   The record shows that Voith provided the only interpretations of
071138 -   Voith drawings, as seen from Tudor's 880803 directive which shows
071139 -   tolerances based on "VOITH FIELD INSTRUCTIONS."
071140 -
071141 -   Voith's charge is telling because it is completely unsupported,
071142 -   (i.e. what "...dimensions on Voith drawings..." have been misin-
071143 -   trepreted, in what manner, and by whom?) and thereby indicates a
071144 -   willingness by Voith management to disclaim performance by its Field
071145 -   representatives.  Alternatively, it may only show a lack of
071146 -   communication between the Field and the York office.
071148 -    ..
071149 -   This has implications not only for the current matter but also
071150 -   the Voith contract work.
071152 -    ..
071153 -   It is obvious Tudor did not determine on its own the valuations
071154 -   in the 880803 Determination.  It has no interest in setting
071155 -   tolerances to any particular valuation.  Voith does have an
071156 -   interest in tolerances.  Second, Tudor did not misconstrue a
071157 -   chance remark to determine tolerances, but rather engaged Voith
071158 -   in protracted discussions over a number of days  ref 2 line
071159 -   060801.
071160 -
071161 -
071163 -  ..
071164 - Reasons for Out of Tolerance Condition
071165 -
071166 -
071167 -   Voith contends "The first contributing factor is that the liner was
071168 -   assembled without prior notification to Voith so that a Field
071169 -   Representative could be sent to site to assist."
071171 -      ..
071172 -     Comment
071173 -
071174 -     This appears to conflict with Voith's position on page 1
071175 -     paragraph 1, as noted above line 071201.
071176 -
071177 -
071178 -   Voith admits "It is not unusual that such a liner could be
071179 -   successfully assembled without Voith's assistance."
071181 -      ..
071182 -     Comment
071183 -
071184 -     This directly conflicts with the underlying premise of the
071185 -     specifications prepared to Voith's instructions, and the position
071186 -     Voith has taken throughout the controversy.  If the tolerances are
071187 -     not disclosed, as here, how would the contractor know what
071188 -     standard to apply.  If Voith is attempting to contend the
071189 -     information in its drawings conveys the tolerances in the 80803
071190 -     Determination, then where is it presented therein, or by what line
071191 -     of reasoning can it be discerned.
071193 -      ..
071194 -     If tolerances are not discernable, and supplemental information is
071195 -     not needed from the manufacturer, then why cannot the contractor
071196 -     reasonably assume that using its "standard procedures" will be
071197 -     adequate?
071198 -
071200 -    ..
071201 -   Voith contends "... basic normal procedures were not being followed
071202 -   - e.g. the liner was being assembled lying on the ground, rust-
071203 -   preventive compounds had not been cleaned from the flange splits
071204 -   prior to assembly, and the drilled and bolted clips installed at
071205 -   shop assembly to locate the liner sections on re-assembly had not
071206 -   been used for their intended purpose.
071208 -      ..
071209 -     Comments
071210 -
071211 -     What source establishes any of the above procedures as "basic"
071212 -     and/or "normal?"  Since these are not set-out in the specifica-
071213 -     tion, how would the contractor or the Engineer know about them?
071214 -
071215 -     What about using "spiders" and not rolling the unit.  Are these
071216 -     not also "basic normal" procedures?
071217 -
071218 -
071220 -    ..
071221 -   Voith says with respect to the contribution of its Field
071222 -   Representative Fred Gross, "... the flange had been put into as good
071223 -   as condition as possible without cutting out all previous welds,
071224 -   which Voith was told not to be done to save time." [sic]
071226 -      ..
071227 -     Comment
071228 -
071229 -     This is considerably different from the characterization describ-
071230 -     ed on page one which gives the impression that a correction was
071231 -     in fact made (i.e. "...this [defective] situation did not exist
071232 -     when Voith's Fred Gross left the site on May 25...".
071234 -      ..
071235 -     Now it is merely as good "as possible."
071237 -      ..
071238 -     The underlying question though is whether knowing the condition
071239 -     of the DTL was not in fact fully corrected, Voith had reason to
071240 -     believe it would be difficult to achieve desired tolerances  and
071241 -     thereon accepted some measure of deviation.
071243 -      ..
071244 -     The implied contention that Sletten told Voith that to save time
071245 -     it was unwilling to cut the previous welds, is not supported by
071246 -     Gross' field report.  To be sure, it is a likely response from
071247 -     Sletten based on the record.  Yet, it is significant because, if
071248 -     Voith recognized that the time saved was more important than the
071249 -     tolerance value, as appears equally likely, then it could be said
071250 -     that Voith accepted the installed tolerance conditions that would
071251 -     reasonably flow from the (mis)assembly condition that was
071252 -     initially accepted in order to save time.
071253 -
071255 -  ..
071256 - Where is the notice to Voith of Sletten's expected start date.  Or is
071257 - there no such notice because it was intended to do it closer to the
071258 - date when Sletten was expected to begin the work?
071259 -
071260 -
071261 -
0713 -
0714 -
Distribution. . . . See "CONTACTS"