Gensler, Michael Willis, Kwan Henmi
Moscone Center Expansion Phase III
600 California Street
San Francisco, California 94108
415 433 3700



November 20, 1998                                                                     03 96060 61 98112001


Prepared by:  Robert Rudeen


Subject:  Moscone Center Expansion Project - Phase III
                Project Number:  96060
                Project Work Summary - Entered on 981123

Work Completed This Week

  1. Jury Duty

    I am on Jury Duty again this week.

  2. Meeting Notes

    Monday, when I arrived at Moscone in the late aftertoon after jury duty, I received meeting notes done by Steve Hergert of Michael Willis and Mike Foegelle of Kwan Henmi.

    Clonia had assigned Michael to do the meeting notes for the Mechanical meetings and Steve to do the meeting notes for Structural meetings.

    This effectively doubled the meeting notes since I was already working on them and was going to issue them on Tuesday.

    I spent Tuesday writing my reply to the extra set of meeting notes.

    We have confusion: It appears now (it's Friday) that Steve is doing the meeting notes for both meetings with input from Mike and me. Now, both Mike and Steve will be sitting in on both the meetings. This just adds to our delay by removing Mike from working on the exterior skin coordination.

  3. Structural Coordination Meeting held on _________________

  4. Mechanical Coordination Meeting held on _________________

  5. Movable Wall Package (operable partitions).

    The Prefunction Room interior elevations are completed. Work on the Operable Partition package continues.

  6. Floor Plan Updates

    Bolivar was interrupted this week to update the Plan layers because Michael Willis group added layers to the Plans. (2 days)

    Another interruption: Consultant composite overlays were received from the consultants this week. Bolivar spent 1.5 days trying to clean up the overlays. Light fixtures are missing.

    Very little progress was made on the Plans this week. Dimensions need to be completed before I can call the Plans 50% complete. It looks like they will only be started by mid December.

  7. Escalator Sections

    Michael worked on dimensions and sections. The sections were taken to a point and stopped so Mike could work on the interface between the exterior package and the interior package.

  8. Exhibit Hall Interior Elevations

    Lawrence was pulled off the Sections this week (per Clonia's request - (without my knowledge) to update the interior elevations of the Exhibit Halls. Gensler had been working on them for a few weeks.

    I wanted the Elevations to be coordinated with the Plans before the Elevations were updated. Anyway, except for a few door location problems, they are near completion and ready for notes etc.

  9. Opening Schedule

    Door numbers, sizes, ratings, types done.

    Exterior doors will be done by Michael Willis Group.

    Details and hardware are outstanding.

  10. Fire Damper Access Study completed.

  11. Fire Hose Valve Reel Study completed.

  12. Floor Box Review (they are 24" in lieu of 18")

  13. Sections at Elevators 3 & 4

  14. Concrete Shear Wall Added to the Basement at grid line D. Plans updated.

  15. Concrete Shear Wall added at the Basement level grid A.4. Plans updated.

  16. Escalators updated on the Plans.

  17. Duct Clearance Section - Prefunction Ceiling

    Section done to check beam clearance at Prefunction Room Ceiling (near elevators 7 & 8, grids F/4.3). Clonia says it's ok to have fire damper access through the ceiling of the Prefunction Room.

Work to be completed next week:

  1. Office: none.
  2. Staffing Meeting to make weekly assignments.
  3. Meeting with Structural (Wednesday 3:00)
  4. Finish Schedule
  5. Redlines (backcheck and coordination)
    There really isn't enough time to do a good check of the drawings before the next printing. So Ivan will work on the Prefunction Room details.
  6. Prefunction Room Details
  7. Elevator Machine Rooms 1,2,3 & 4
  8. Fire Separations on the Plans
    Study line widths for the plans. (no progress from previous week)
  9. Dimension the Plans (no progress from previous week)
  10. Wall Types
    Clean-up wall types. (on-going)
  11. Opening Schedule
    First pass at hardware and "typical" details
  12. Interior Elevations at Exhibit Halls
    Fine tuning the door locations.
  13. Ceiling Coordination at Exhibit Halls
  14. Exterior Skin interface with Interior
    Update exterior wall sections and draft new details.
  15. Basement Ramp Section
  16. Elevator Shaft Sections
  17. Operable Partition bid package work continues
    (very little progress from previous week)
  18. Next Printing: December 4th I personally think there is not enough time between printings to show much progress. We seem to be loosing a weeks worth of progress every time we print. This week is a short week because of Thanksgiving. The printing is next week. Clonia says it is the 75% printing. We are not 75% done.


Whom


Robert
Team
Robert
Robert




Ivan
Bolivar
Bolivar


Bolivar
Bolivar

Janet

Janet

Janet
Michael

Lawrence
Lawrence
Phillip






Hours



























NOTES:

  1. Robert R is on Jury Duty this week. Looks like Wednesday could be the last day (maybe sooner).
  2. Janet begins vacation on Tuesday this week.
  3. Short week: Thanksgiving is Thursday this week and several of the Team are taking Friday off.

c:/robert-personal/timesheets/Document1