Gensler, Michael Willis, Kwan Henmi
I am on Jury Duty again this week.
Monday, when I arrived at Moscone in the late aftertoon after jury duty, I received meeting notes done by Steve Hergert of Michael Willis and Mike Foegelle of Kwan Henmi.
Clonia had assigned Michael to do the meeting notes for the Mechanical meetings and Steve to do the meeting notes for Structural meetings.
This effectively doubled the meeting notes since I was already working on them and was going to issue them on Tuesday.
I spent Tuesday writing my reply to the extra set of meeting notes.
We have confusion: It appears now (it's Friday) that Steve is doing the meeting notes for both meetings with input from Mike and me. Now, both Mike and Steve will be sitting in on both the meetings. This just adds to our delay by removing Mike from working on the exterior skin coordination.
The Prefunction Room interior elevations are completed. Work on the Operable Partition package continues.
Bolivar was interrupted this week to update the Plan layers because Michael Willis group added layers to the Plans. (2 days)
Another interruption: Consultant composite overlays were received from the consultants this week. Bolivar spent 1.5 days trying to clean up the overlays. Light fixtures are missing.
Very little progress was made on the Plans this week. Dimensions need to be completed before I can call the Plans 50% complete. It looks like they will only be started by mid December.
Michael worked on dimensions and sections. The sections were taken to a point and stopped so Mike could work on the interface between the exterior package and the interior package.
Lawrence was pulled off the Sections this week (per Clonia's request - (without my knowledge) to update the interior elevations of the Exhibit Halls. Gensler had been working on them for a few weeks.
I wanted the Elevations to be coordinated with the Plans before the Elevations were updated. Anyway, except for a few door location problems, they are near completion and ready for notes etc.
Door numbers, sizes, ratings, types done.
Exterior doors will be done by Michael Willis Group.
Details and hardware are outstanding.
Section done to check beam clearance at Prefunction Room Ceiling (near elevators 7 & 8, grids F/4.3). Clonia says it's ok to have fire damper access through the ceiling of the Prefunction Room.
Work to be completed next week:
|
Whom
Robert
Janet
Janet
Janet
Lawrence
|
Hours
|
NOTES: