Gensler, Michael Willis, Kwan Henmi
Moscone Center Expansion Phase III
600 California Street
San Francisco, California 94108
415 433 3700




October 30, 1998                                                                     03 96060 61 98103001


Prepared by:  Robert Rudeen


Subject:  Moscone Center Expansion Project - Phase III
                Project Number:  96060
                Project Work Summary - Entered on 981030

Work Completed This Week

  1. 50% CD Printing due at noon today.

    KH drawings are about 25% to 30% complete.

  2. No meetings this week, due to major printing.

  3. Stair Sections

    I was able to complete the redmarks for stairs 7 & 8. Lawrence was not able to complete the stair sections by the end of the week. Clonia said it was acceptable to paste-up my redmarks.

  4. Wall Types

    I was not able to sit with Clonia again to go over the partition types. At the last minute Clonia decided that the partitions were important to this printing because a cost estimate is being done. I took a pass at it and Janet imputed them. Mike and Phillip did the cores that they worked on.

  5. Movable Wall Package (operable partitions).

    No work done.

  6. Plotter problems

    Gensler's plotter system is proprietary. Is changing. Our machines are configured for windows 95, not windows NT (tues)

  7. Interior Elevations

    Clonia asked for a plot of the interior elevations.

    One of the steel frames had been misplaced and she was furious. She even wrote a memo to Art Gensler. The problem was trivial and was a two minute fix.

    We do not have time to check and correct drawings that she wants at the spur of the moment.

    She blamed KH for the mistake - it may have been her designers mistake because he was working on them. In this case, it was an easy fix but, it took time away from something else and it created yet another time where everyone becomes a bit more hesitant to do work.

  8. Exterior Bid Package

    I had a short meeting with Clonia to discuss the Exterior Bid Package.

    I foresee big problems with contractor coordination.

    There will not be a single point of responsibility. For example, if the building leaks, who is responsible? I said it is a big mistake to make this two bid packages. There should be one package, and one source of responsibility. She said all that has been solved and should not be a problem. -- I'm not convinced.

Work to be completed next week:

  1. Office: Attend KH Staffing Meeting
  2. Attend Staffing Meeting to assign weekly assignments.
  3. Attend Meeting with Mechanical
  4. Attend Meeting with Structural
  5. Wall Types
  6. Clean-up wall types.
  7. Opening Schedule
  8. Opening Details
  9. Fire Separations on the Plans
  10. Study line widths for the plans.
  11. Exterior Skin interface with Interior.
  12. Update exterior wall sections and draft new details.
  13. Elevator Machine Rooms to be put onto the Plans (completion needed)
  14. Redlines
  15. Stair Sections
  16. Operable Partition bid package
  17. Dimension the Plans
  18. Interior Elevations

Whom


Robert
Team Robert
Robert
Janet

Janet
Janet
Bolivar

Michael

Bolivar


Lawrence
Phillip
Bolivar
Robert J.

Hours























NOTES:

  1. Ivan is on vacation this week
  2. Robert R is on Jury Duty this week.