-  Regarding the exhibit hall 2nd and third floor ceilings.  As of
      yesterday, I do not seem to get through to Robert: can you provide a
      ceiling layout were all strucutral trusses and bracing is indicated.
      Indicate thicknesses in your coordination plan of the above members.  As
      I explained to Robert before and again yesterday, at 22' 6" oc there is
      already a structural member in the east/west direction that we should use
      for the hang point layout.  It is there for structural reasons (it is
      indicated as a bracing element on the structural framing plan)  Let's use
      it!!! Not spending unnecessary Client $'s is our task!  We have a limited
      Construction budget.  OUt task is to design around the parameters given.
      
      [On 982909 entered in
      
      JV Coordination meeting.]
 
       
-  As of my meeting with you and Robert on 9/17/98, I indicated to you that
      the 7/8" dimension between the gypsum board soffit and track cover is not
      acceptable: there is some give and take at the perimeter of the
      acoustical ceiling.  Try to use it.
      
      [On 982909 entered in
      
      JV Coordination meeting.]
 
       
-  Restrooms:  As I indicated to you before, and also yesterday, please
      verify the women/men ratio at each of the restoom locations.  We can not
      blury our head in the sand.  This is a major facility we cannot be wrong.
      I hope you have an answer by Monday.  Start with the women # of water
      closets.  With this # take a look at the UPC code (copy given to your
      team, hope you still have it).  The code requirements will tell you how
      many occupants you can accomodate with the # of water closets you have in
      one location.  Calculate the woman lavatories based on the occupancy
      established for the water closets.  Since women/men are 50/50 look at how
      many fixtures you need for me's restrooms.  (wc, lavs, urinals). You may
      need to play with the layout to arrive at a reasonable ratio. Please
      advise.  We need to also advise the client.  Thank you.
      
      [On 982909 entered in
      
      JV Coordination meeting.]