                       D R A F T 


Memorandum


To:  Art Gensler, Clonia Cautis

From:  Denis Henmi, William Long, Ivan Romero

Date:  September 30, 1998
 

Subject:  Project Management Plan
Yesterday, Clonia suggested using the Moscone II plans as criteria for defining the 50% design package. We have refocused our management to work on this task, and will notify the team on a scope based on this criteria.

Additionally, we would like an executive meeting at the first opportunity to develop improved facilities and lines of communication. This is needed to accomodate increased staff so we avoid congestion and information overload that adversely impact management and delay the work, due to current space limitations. Our aim is to ensure that cost, time and quality objectives are met, and further that Gensler's daily concerns are addressed in an orderly manner so that the ultimate design is supported by the project record. We need your input to accomplish these goals. Please advise when you can meet.