DIARY: October 2, 1997 01:51 AM Thursday; Rod Welch

Complete preliminary cost savings analysis Communication Metrics.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD            415 977 8400 fax 8483
020101 - Mr. Thompson F. Keesling, Architect; Assistant Chief =415 977 8473
020102 - Construction Operations Division =415 977 8480
0202 - Corps of Engineers, SFD            415 977 8400 fax 8483
020201 - Mr. Max R. Blodgett, II, P.E., L.S.
020202 - Chief =415 977 8444; Construction Operations Division =415 977 8480

SUBJECTS
COE Evaluation Communication Metrics
Analysis, Review, Research
Institutionalize Communication Metrics
CE HQ Evaluation
Calculate Risk Management Exposure NPV

1007 -    ..
1008 - Summary/Objective
1009 -
100901 - Follow up ref SDS 6 0000, ref SDS 4 0000.
100902 -
100903 - Completed analysis to formulate a cost savings/benefit calculation of
100904 - Communication Metrics.  Work was done in the record at ref SDS 6 2496.
100905 -
100906 - Developed a format for analysing cost savings using file ref OF 1 line
100907 - 22.  It is the first draft of a report to Jim Jones, per his request
100908 - last Friday, ref SDS 1 line 85 and at ref SDS 1 line 387.
100909 -
100910 -     [See delivery of first draft to Tom, ref SDS 7 0000.]
100911 -
100912 -     [See edits to draft memo to Jim, ref SDS 7 9911.]
100913 -
100914 -
100915 -
100916 -
1010 -
1011 -