DIARY: December 9, 1994 10:49 AM Friday; Rod Welch

Asked about need to upgrade substations on Gold Hill.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 

SUBJECTS
Upgrade Substations because line is

0403 -    ..
0404 - Summary/Objective
0405 -
040501 - Followed up work at ref SDS 5 line 31.
040502 -
040503 - Jivat asked if the Gold Hill Horseshoe Upgrade will increase the
040504 - capacity of the line, and indicated that if so, then the Substations
040505 - will have to be upgraded.
040506 -
040507 - Randy said the substations along the route of the upgrade have
040508 - already been upgraded to handle the capacity of the new line being
040509 - installed.  He feels there is no need for substation work.