S U M M A R Y
DIARY: October 2, 1994 10:33 AM Sunday;
Rod Welch
Modify CDWR schedule on Land issues.
1...Summary/Objective
..............
Click here to comment!
CONTACTS
SUBJECTS
Action Item status
PG&E letter on construction practices
PG&E submit environmental information by 941001
940818 Meeting CDWR Sacramento, CDWR & PG&E
Environmental Protection
Permits, Fish & Game, Arco - Devils Den
1108 - ..
1109 - Summary/Objective
1110 -
111001 - Followed up work at ref SDS 19 line 101. Created new schedule file,
111002 - ref OF 2, to update ref OF 1. Added tasks recommended by Bob to show
111003 - the impact of environmental reports and approvals at ref SDS 19 line
111004 - 101, and also at ref SDS 19 line 303.
111005 -
111006 - Added links to modifying the EIR .
111007 -
111008 -
111009 -
111010 -
1111 -
SUBJECTS
Land, SLO Hydro, Environmental Protection
Land, Casmalia, Environmental Protection
Distribution System
Biological & Cultural Survey, Tie Line
Biological & Cultural Survey, Distribution
Amend EIR, by CDWR
2009 - Summary/Objective
2010 -
201001 - Added schedule tasks for SLO Hydro and Casmalia, per ref SDS 19 line
201002 - 225, and also at ref SDS 19 line 319.
201003 -
201004 - Linked EIR for SLO Hydro into construction of both the Tie Line by
201005 - PG&E and the Communication Lease line by Pac Bell.
201006 -
201007 -
201008 -
2011 -
SUBJECTS
GO 131-D
Schedule File 941002a
Determine Requirements Legal Applicability
Plan Implementation
Implement Plan
2508 - Summary/Objective
2509 -
250901 - Tried adding a task at Project level, to recognize the work being done
250902 - on this task for CDWR, per ref SDS 19 line 347.
250903 -
250904 - Made this a separate schedule file, ref OF 3, so it is easier to
250905 - remove this stuff and/or do it differently, if necessary.
250906 -
250907 - Bob seems to indicate the first step of determining the requirements
250908 - has been completed. CDWR and PG&E now have to plan how to implement
250909 - what is required. This will entail creating specific tasks for
250910 - people to perform, and linking those tasks into the other tasks. My
250911 - general impression is that these tasks will control start of
250912 - construction.
250913 -
250914 -
250915 -
250916 -
2510 -