DIARY: September 29, 1994 10:18 AM Thursday; Rod Welch

Called Greg re status Induction study for CDWR.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Trans Sys Engineering         415 973 3877 fax 9209
020101 - Mr. Gregory J. Chang
020102 - Programer Analyst; Rm 530B, Mail Code F5C =415 973 4314

SUBJECTS
Transmission Line Engineering - Grounding Study (Maria Ly)
Fault Condition
CDWR submit information for induction study
PG&E submit induction study

0806 -    ..
0807 - Summary/Objective
0808 -
080801 - Followed up work at ref SDS 6 line 28.
080802 -
080803 - Has PG&E received pipe coating spec from CDWR?
080804 -
080805 -    He has not received this from CDWR.  They will need about a week
080806 -    to complete the study after receving this information from CDWR.
080807 -
080808 -    Maria Ly is out this week.  Greg understands, she has requested
080809 -    the information, but CDWR has not responded.
080810 -
080811 - Scheduled follow up for 941004.
080812 -
080813 -
080814 - Status of meeting 941101 report date.
080815 -
080816 -    He has completed the steady state study.  Working on fault
080817 -    condition.  If they can get the report on pipe spec within the next
080818 -    week or so (i.e., by 941115), they can mee the 941101 date.
080819 -
080820 -
080821 -
080822 -
080823 -