THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700


S U M M A R Y


DIARY: February 28, 89 01:00 PM .......; Rod Welch

Gracon claim presentation meeting.

1...Summary/Objectives
2...Claims Continuing Delay Until Access Across Powerhouse Provided
3...Gracon Increases Claim for Extra Time and Payment, Raises New Issues
4...Possible 130% Error in Time Extension Calculation
5...Gracon Claim Summary Seeks 87 Day Time Extension
6...Concurrent Delay Has Not Been Evaluated in Gracon's Claims
7...Total Cost Method to Calculate Damages is Unsubstantiated
8...Gracon Claims Denied Use of Cofferdam Road Caused Delay
9...Original Schedule Does Not Support Delay Claim
10...Gracon Failed to Perform Contract Schedule Requirements
11...Gracon's Schedule Did Not Allow for Coordination of Other Contracts
12...Engineer Directs Gracon to Submit Schedules Required by Contract
13...Entitlement Contract Authority Kurt's 881229 letter
14...Gracon Offers No Basis for Entitlement to Use Cofferdam Access Road
...Gracon Cites Coordination as Entitlement to Use Cofferdam Road
...Coordination Theory Does Not Support Claim for Unrestricted Access
15...Gracon's Damage Claim on Pumping Concrete 600' is Conflicting
16...Gracon's Actual and Justifiable Reliance Has Not Been Established
17...Gracon Has Not Established Damage Due to Lack of Access
18...Gracon Planned on Barge Access, Not Use of Powerhouse Road
19...Gracon Has Been Provided Adequate Access to Perform the Work
20...Gracon is 30 Days Behind Schedule Even if its Claim is Approved
21...Tie Down Change Requested to Expedite Work Actually Caused Delay
22...Ripple of Related Factors Cascaded into Compound Delay
23...Six (6) Month Slack Time Lost by Oversight, Neglect
24...Change to Expedite Caused Delay Because of Complex Factors
25...Weather Impacts Impede Effective Planning to Complete Work
26...Gracon Arranging for Alternate Barge Support to Maintain Progress
27...DNRC Needs Rubber Dams Installed OB 880421
28...Gracon Will Substantially Complete the Work by 880421

ACTION ITEMS.................. Click here to comment!

1...Gerry said Gracon will furnish information on these points.
2...Rod suggested Gracon's as-built CPM must establish actual delay.

CONTACTS 
0201 - O-0387 0101 Tudor Engineering Company  415 543 9820 fax   415 543 5538
020101 - Mr. Clyde Earnest,
0202 - O-0387 0201 Tudor Engineering Company  415 543 9820 fax   415 543 5538
020201 - Mr. Kurt Scholz, Project Engineer, =Telephone
0203 - O-0395 0202 Department of Natural      406 444 6699 fax   406 444 6721
020301 - Mr. Wayne Wetzel, Project Manager, =406 444 6791
0204 - O-0395 0201 Department of Natural      406 444 6699 fax   406 444 6721
020401 - Mr. Norman Barnard,
0205 - O-0393 0101 Gracon Corporation         303 667 2203
020501 - Mr. Gerald R. Ashbach, President
0206 - O-0393 0301 Gracon Corporation         303 667 2203
020601 - Mr. Dale Harrington, Superintendent, =406 266 5747
020602 - Broadwater Power Project
0207 - O-0393 0401 Gracon Corporation         303 667 2203
020701 - Mr. Mike Ream, Vice President, =Telephone, Construction Department
0208 - O-0393 0303 Gracon Corporation         303 667 2203
020801 - Mr. Michael S. `Bo' Brown, Project Manager
020802 - Broadwater Power Project

SUBJECTS
Gracon, Claim Denied
Mobilization & Access Upstream Cofferdan
Access Across Powerhouse
Access Across Cofferdam
Updated Schedule Submittal
Discharge across Rubber Dam
Time Extensions, Contract Completion

1009 -    ..
1010 - Summary/Objectives
1011 -
101101 - Gracon showed a series of calendar charts marked with dates of claim-
101102 - ed delay.  Color codes distinguish dates claimed by Malcolm in these
101103 - charts.  Gracon represented that its submission today covers all of
101104 - its claim notices, ref DRP 1 - 10, and other claims known to Gracon at
101105 - this time. ref SDS 0 2137  Gracon's claim submissions are erroneous
101106 - and conflicting, and do not substantiate entitlement to extra payment
101107 - and time extensions.  Gracon plans to submit additional information to
101108 - justify approval of its claims.  Gracon cited ripple effects of
101109 - compound factors caused loss of 6 months slack time that now makes the
101110 - spillway contract critical to completion of the Broadwater Dam
101111 - project.  Gracon will schedule to complete its work by 880410. ref SDS
101112 - 0 3233  Engineer directed Gracon to perform contract requirements to
101113 - submit updated schedules.
101114 -
101115 -
101116 -
1012 -
1013 -
1014 - Discussion
1015 -
101501 - Claims Continuing Delay Until Access Across Powerhouse Provided
101502 - Gracon Increases Claim for Extra Time and Payment, Raises New Issues
101503 -
101504 - In this meeting Gracon disclosed it is seeking considerably more days
101505 - than presented in its previous claim letters, ref DRP 1 - 3, and an
101506 - increase in the number of days it will require to complete the
101507 - contract.
101508 -
101509 - Bo advised that Gracon has not received the level of access it needs
101510 - and is granted under the contract, and so its claim will continue to
101511 - increase until such access is made available.
101512 -
101513 - During the second meeting at the site, about 1700, Gracon indicated it
101514 - could complete the project by 890421 under existing access conditions
101515 - which is restricted by the performance of other contractors working in
101516 - and around the Powerhouse. ref SDS 0 3233
101517 -
101518 - Under the claim for denied access to the stairway, Gracon now seeks 8
101519 - days, instead of the 7 days set out in its letter, ref DRP 3.
101520 -
101521 - Gracon seeks a total of 79 days for denied access across the
101522 - Powerhouse, and a variety of other issues some of which have been
101523 - previously noticed, but not quantified (see ref DRP 4  6 & 10)  and
101524 - others that have not been previously presented (see the "Summary"
101525 - below. ref SDS 0 1103).
101526 -
101527 - The Engineer had understood Gracon's claim for denied access across
101528 - the Powerhouse, ref DRP 2, was comprehensive because, according to
101529 - Gracon, it permeates every aspect of the work.  The additional claims
101530 - presented today, raise questions of concurrency, not resolved by
101531 - Gracon's presentation. ref SDS 0 1822
101532 -
101533 - Gracon's letter of 881221, states: "Time extensions will be necessary
101534 - at the rate of 1.4 calendar days per week of denied access," ref DRP
101535 - 2.  This letter contends a total of 16 weeks is subject to claim, as
101536 - of 890131, which then results in 12.4 calendar days of claimed delay
101537 - to period ending 890131.  The 1.4 calendar days correlates to the 20%
101538 - factor Gracon seeks as compensation on all labor and equipment during
101539 - the claim period under its "total cost" theory of recovery.
101540 -
101541 -
101542 -
101543 - Possible 130% Error in Time Extension Calculation
101544 -
101545 - Gracon's claim letter of 881221, ref DRP 2, also shows a request for
101546 - 29 calendar days extension on the cost "Summary" sheet  which appears
101547 - to conflict with the analog cited on page one of its claim statement
101548 - seeking 1.4 calendar days per week.  As seen, the 1.4 factor results
101549 - in 12.4 calendar days.
101550 -
101551 -
101552 - ..
101553 - Gracon Claim Summary Seeks 87 Day Time Extension
101554 - 
101555 - Summary, Gracon separate claims offered during this meeting:
101556 -
101557 -                                               Claimed
101558 -                                                 Delay    Notice
101559 -                                              Cal Days    (DRP #)
101560 -                                              =========   =======
101561 -   Cofferdam road, diminished access                8         3
101562 -   Cofferdam road, blocked by Sletten            see #1    see #1
101563 -   Malcolm - different conditions                   9       None
101564 -   Powerhouse access, denied                       40         2
101565 -   Quantity overrun (Malcolm)                       9       None
101566 -   Weather                                         14        10
101567 -   SCUL electrical panel                            7         7
101568 -                                                -------
101569 -      Total....................................... 87
101570 -
101571 -
101572 -
101573 -   Notes:
101574 -
101575 -     The "Notice" column correlates to Gracon's documents shown in the
101576 -     reference section, above.
101577 -
101578 -     This does not appear to be a current claim.  Under Gracon's the-
101579 -     ory, ref DRP 2, its entitlement to time extension continues to
101580 -     accrue at 1.4 calendar days for each week it is denied the level
101581 -     of access across the Powerhouse it interprets the contract to
101582 -     permit, and as seen below, that has not occurred, and will not
101583 -     likely occur prior to completion.
101584 -
101585 -     Claim #3 (Malcolm) is for extra time to perform as a result of
101586 -     encountering reinforcing steel drilling through the original
101587 -     structure, and the consequent option Gracon was offered to drill
101588 -     diagonally in order to avoid the condition.
101589 -
101590 -     Claim #7 (SCUL) relates to late delivery of equipment and modifi-
101591 -     cations to conduit layout between the Powerhouse and the Dam.
101592 -
101593 -
101594 - ..
101595 - Concurrent Delay Has Not Been Evaluated in Gracon's Claims
101596 - 
101597 - Clyde asked whether any of Gracon's claims contain concurrent delay?
101598 -
101599 - Bo Brown indicated a rigorous analysis has not been done on this
101600 - particular point.
101601 - ..
101602 - Rod asked if Gracon has any other pending or potential claims
101603 - against DNRC that are not included in the new claims Gracon submits
101604 - today?
101605 -
101606 - Bo said that Gracon's objective today is to get all potential claims
101607 - on the table.
101608 -
101609 - Clyde noted that Gracon will have to establish its entitlement, and
101610 - suggested an as-built CPM would be an acceptable method.
101611 -
101612 - Bo noted that Gracon plans to submit an as-built CPM to substantiate
101613 - its claim of delay and entitlement to extra time and payment.
101614 -
101615 - Kurt feels that the SCUL panel delivery delay is not a "critical"
101616 - activity.
101617 -
101618 - Bo indicated this matter will be apparent from Gracon's as-built CPM.
101619 -
101620 -
101621 -
101622 - Total Cost Method to Calculate Damages is Unsubstantiated
101623 -
101624 - Rod asked how Gracon's "total cost" method for computing damages
101625 - distinguishes between tasks dependent upon access, such as delivering
101626 - materials, and the actual work itself?
101627 -
101628 - Dale feels the inability to provide materials and equipment on a
101629 - timely basis also affected the productivity of the work operation.
101630 -
101631 - Rod noted an apparent conflict between this position and Gracon's
101632 - representation that it delivered materials by barge as contemplated
101633 - by the parties in entering the agreement, and there is nothing in the
101634 - record showing the barge was unable to handle materials in the
101635 - quantity needed to maintain continuous operations.  Accordingly
101636 - failure to do so would seem to reflect poor coordination and planning
101637 - by Gracon which is a duty of the contractor and therefore  not
101638 - actionable.
101639 -
101640 -
101641 -
101642 - Gracon Claims Denied Use of Cofferdam Road Caused Delay
101643 - Original Schedule Does Not Support Delay Claim
101644 -
101645 - Rod asked if Gracon's original schedule showed an anticipated
101646 - improvement in productivity between the period prior to 881010 when
101647 - Gracon claims it was obligated to use barge access only, and later
101648 - when it holds productivity would have dramatically increased by access
101649 - across the Powerhouse using the cofferdam road constructed by Sletten?
101650 -
101651 - Gerry said this difference is not reflected in Gracon's original
101652 - schedule issued to the Engineer, but that the information can be
101653 - developed from the bid estimate records and the as-built CPM.
101654 -
101655 -
101656 -
101657 - Gracon Failed to Perform Contract Schedule Requirements
101658 -
101659 - Rod asked if Gracon has submitted monthly schedules so the Engineer
101660 - can evaluate its schedule contentions presented today?
101661 -
101662 - Bo Brown said that Gracon has not done this.
101663 -
101664 - Clyde indicated this makes the as-built CPM all the more important.
101665 -
101666 -
101667 -
101668 - Gracon's Schedule Did Not Allow for Coordination of Other Contracts
101669 -
101670 - Rod asked if Gracon recognized the coordination required under General
101671 - Conditions Article 7.1, with the work of other contractors in its
101672 - application of section 01110?
101673 -
101674 - Gerry indicated this was not included in Gracon's cost and schedule
101675 - estimates, because Gracon relied on the provision that it would have
101676 - "unrestricted access" in section 01110  and that it was not clear to
101677 - Gracon in bidding the project and negotiating the contract that other
101678 - contractors would be working on the project after 881010 which
101679 - requires application of Article 7.1.
101680 -
101681 -
101682 -
101683 - Engineer Directs Gracon to Submit Schedules Required by Contract
101684 -
101685 - Clyde said that apart from the outcome of this matter, Gracon's
101686 - failure to perform the schedule requirement is serious lack of notice
101687 - to DNRC about Gracon's progress and planning, which denies the State
101688 - the opportunity to coordinate the work of others impacted by Gracon's
101689 - work.  Clyde said Gracon must correct this (see General Conditions
101690 - Article 14.2).  He asked that Gracon submit its updated schedule
101691 - showing what it will be working on and when it expects to finish the
101692 - various major components of the work.
101693 -
101694 - Gerry said Gracon needs input from the Engineer on the completion
101695 - objectives it should pursue.  He indicated Gracon can use this
101696 - information to determine whether it must accelerate its progress.
101697 -
101698 - Clyde explained that the Engineer has provided information to Gracon,
101699 - and will continue to make timely disclosure and response to Gracon's
101700 - requests for information.  Clyde said that Gracon's request this
101701 - evening for "input from the Engineer on completion objectives" is
101702 - incorrect.  Gracon must schedule to complete the work according to
101703 - contract completion dates, as adjusted by change orders. Clyde pointed
101704 - out that the Owner needs input from Gracon in order to coordinate the
101705 - other contracts and expects to receive scheduling data predicated on
101706 - the contractor's perception of its obligations within the meaning of
101707 - the contract.  After the Contractor performs this requirement  the
101708 - Owner can assess the benefit and need for discussions on acceleration.
101709 -
101710 -
101711 -
101712 - Entitlement Contract Authority Kurt's 881229 letter
101713 - Gracon Offers No Basis for Entitlement to Use Cofferdam Access Road
101714 -
101715 - Kurt asked for the contract provision from which Gracon derives a
101716 - right to use the cofferdam road, as claimed in its letter of 881221,
101717 - ref DRP 3 (see also DRP 1 answered by DCP 2).
101718 -
101719 - Gracon offered no authority during the meeting for this proposition.
101720 -
101721 -
101722 -   Gracon Cites Coordination as Entitlement to Use Cofferdam Road
101723 -
101724 -   Rod met briefly with Mike Ream on 890301 at the site to inquire
101725 -   further on this point.
101726 -
101727 -   Mike indicated Gracon relies on GC Article 7.1 which provides for
101728 -   coordination of work between contractors, as vesting it with a right
101729 -   of such access.
101730 -
101731 -
101732 -   Coordination Theory Does Not Support Claim for Unrestricted Access
101733 -
101734 -   If GC Article 7.1 can be construed to require Owner to give Gracon
101735 -   use of the Cofferdam road constructed and maintained by others, as
101736 -   suggested by Mike (which is not established), then Gracon could not
101737 -   have reasonably expected to have "unrestricted" access across the
101738 -   Powerhouse (claim #4), since the Engineer would have had a duty to
101739 -   permit access of other contractor's under the same theory Gracon
101740 -   applies to the cofferdam road matter.  Therefore, even if Gracon is
101741 -   incorrect in its application of Article 7.1, it is not clear how
101742 -   Gracon could have relied on contract section 01110 to expect
101743 -   "unrestricted access" across the Powerhouse when it expected
101744 -   restrictions to flow under Article 7.1 for Gracon's benefit with
101745 -   respect to the cofferdam road.
101746 -
101747 -
101748 -  ..
101749 - Gracon's Damage Claim on Pumping Concrete 600' is Conflicting
101750 -
101751 - Dale said that an example of Gracon's damages caused by denied access
101752 - to the cofferdam road, was having to pump concrete approximately 600
101753 - feet instead of being able to move the truck next to the stairs or the
101754 - Powerhouse.
101755 -
101756 - Clyde recalled that Gracon indicated during original contract
101757 - discussions that it planned to pump concrete 600 feet. There is a
101758 - transcript of the original contract discussions.
101759 -
101760 - This understanding was not disputed during the meeting today.
101761 -
101762 -
101763 -  ..
101764 - Gracon's Actual and Justifiable Reliance Has Not Been Established
101765 -
101766 - Kurt asked what contract authority Gracon relies on in asserting a
101767 - right to access across the Powerhouse.
101768 -
101769 - Gerry cited section 01110 which was mentioned in the Engineer's 881229
101770 - letter drafted by Kurt, see ref DIP 3.  Careful reading indicates a
101771 - literal application of this section, without notice of any other
101772 - provision  could convey an impression that one contractor would have
101773 - unrestricted access across the Powerhouse, which would necessarily
101774 - deny any access to others, including DNRC.
101775 -
101776 - Rod asked if it is Gracon's practice to construe contract provisions
101777 - without regard to the totality of circumstances otherwise apparent to
101778 - a reasonable bidder?
101779 -
101780 - Gerry indicated such is not Gracon's practice, and observed that
101781 - Gracon contemplated performing all of the contract provisions in a
101782 - reasonable and prudent manner.
101783 -
101784 - Rod observed the record at this point does not seem to establish there
101785 - was actual and justifiable reliance in the manner claimed.
101786 -
101787 - Gerry said Gracon will furnish information on these points.
101788 -
101789 -
101790 -
101791 - Gracon Has Not Established Damage Due to Lack of Access
101792 -
101793 - Clyde questioned whether even if Gracon had been permitted
101794 - "unrestricted access across the Powerhouse," that its actual progress
101795 - would have been improved.  Norm pointed out that the use of this
101796 - access to transport materials and equipment would have been impeded by
101797 - Gracon's drilling operation.
101798 -
101799 - Dale explained that this problem could have been ameliorated to some
101800 - degree by using the crane Gracon is using on the Dam deck.
101801 -
101802 - Rod suggested Gracon's as-built CPM must establish actual delay.
101803 -
101804 -
101805 -
101806 - Gracon Planned on Barge Access, Not Use of Powerhouse Road
101807 -
101808 - Kurt asked about Gracon's representations at pre-award meetings
101809 - conerning access.  He recalled Gerry advising that Gracon intended to
101810 - use a barge on the upstream side of the Dam, rather than access across
101811 - the cofferdam road.  He further cited Gerry's acknowledgement that the
101812 - contract does not permit unlimited access across the Powerhouse, and
101813 - that the maximum vehicle size Gracon could expect to move across the
101814 - Powerhouse would be a "light pickup truck."
101815 -
101816 - Gerry acknowledged these understandings, but maintained that they only
101817 - applied to access prior to 881010, and that Gracon at all times relied
101818 - upon the contract language of section 01110, that on 881010 it would
101819 - be permitted "unrestricted access" across the Powerhouse.
101820 -
101821 -
101822 -
101823 - Gracon Has Been Provided Adequate Access to Perform the Work
101824 -
101825 - Kurt mentioned the understanding that Gracon would accept access
101826 - across the cofferdam road in lieu of access across the Powerhouse, and
101827 - that Gracon has enjoyed such access from 881010 until today when the
101828 - stair was removed, ref DIP 2 line 1010.  Since Gracon now has access
101829 - across the Powerhouse, there is no basis for any claim of delay.
101830 -
101831 -
101832 -
101833 - Gracon is 30 Days Behind Schedule Even if its Claim is Approved
101834 -
101835 - Norm pointed out that even if Gracon is granted its request for the
101836 - entire 87 days of time extension, it would still be subject to ap-
101837 - proximately 30 days of presumed damages.
101838 -
101839 - Gerry advised that Gracon views the supplemental contract language as
101840 - extending the date of substantial completion from 881231 to 890201.
101841 -
101842 - Kurt feels that position is incorrect in that the parties merely
101843 - intended to give Gracon a grace period of 30 days with respect to the
101844 - imposition of presumed damages, and did not intend by the supplemental
101845 - language to extend or in any way change the actual date of substantial
101846 - completion.
101847 -
101848 - The purpose of the supplemental contract language was to avoid Gracon
101849 - charging for anticipated presumed damages in the contract price which
101850 - it indicated at the time of entering the contract would be needed in
101851 - light of its estimate that the time required to perform the work
101852 - would likely exceed the date of substantial completion.
101853 -
101854 -
101855 -
101856 - Tie Down Change Requested to Expedite Work Actually Caused Delay
101857 -
101858 - Bo Brown explained this claim arises from the Engineer's determination
101859 - to revise the location and or angle of penetration for certain tie
101860 - down anchors in order to avoid drilling through rebar.
101861 -
101862 - Kurt noted that this change was made at Gracon's request to expedite
101863 - its work.
101864 -
101865 - Rod asked whether, in bidding the work, Gracon expected to encounter
101866 - reinforcing steel to drill the tie down anchor holes?
101867 -
101868 - Bo said the plans do not show reinforcing steel to be encountered, but
101869 - that Gracon is aware that dams are constructed with reinforcing steel
101870 - and so bid to meet that contingency.
101871 -
101872 - Rod asked if it takes longer to drill through concrete and steel than
101873 - to drill solely through concrete?
101874 -
101875 - Bo said drilling through reinforcing steel takes a lot longer, which
101876 - is why Gracon reqested changing the location of the tie down holes.
101877 -
101878 - Rod noted that normally granting the contractor an option to construct
101879 - by methods that reduce the time of performance, should not result in a
101880 - claim for extended performance time.
101881 -
101882 - Bo feels there were difficulties trying to drill at an angle which
101883 - were not contemplated in adopting the change, that extended the time
101884 - of completion.
101885 -
101886 - ..
101887 - Ripple of Related Factors Cascaded into Compound Delay
101888 - Six (6) Month Slack Time Lost by Oversight, Neglect
101889 - Change to Expedite Caused Delay Because of Complex Factors
101890 -
101891 - Kurt asked why the tie down and grouting work item is now critical,
101892 - and so is delaying completion of the Spillway contract?
101893 -
101894 - Bo said the time required to propose, design, review and approve the
101895 - change was longer than expected because of mail difficulties,
101896 - vacations and key people on various staffs were busy with other things
101897 - that seemed more important than this task which originally had 6
101898 - months slack time.
101899 -
101900 - Therefore, the start of the this operation was delayed by 4 months.
101901 -
101902 - Drilling on an angle added 4 weeks to the work operation, and
101903 - excessive rock fracture required another 4 - 6 weeks which pushed the
101904 - work into cold weather that greatly slowed the work and made it impact
101905 - the critical path.  He feels their current rate of progress means they
101906 - cannot finish for at least another 3 weeks.
101907 -
101908 - The men are cold, equipment is breaking down, so production is very
101909 - slow.
101910 - ..
101911 - The subcontractor wants to pull off the job until the weather
101912 - warms up in two months.
101913 -
101914 -    [See later discussion with DNRC management, ref SDS 3 4367.]
101915 -
101916 -
101917 -
101918 - Weather Impacts Impede Effective Planning to Complete Work
101919 -
101920 - Wayne asked about the impact on completion of continued temperatures
101921 - below 50 degrees.  An example is Malcom Drilling's consideration to
101922 - pull off the job until higher temperatures occur. ref SDS 0 2825
101923 -
101924 - Dale advised that he feels 32 degrees is a more critical temperature
101925 - that impacts installation of the rubber dams.  He cited a variety of
101926 - work tasks that impede progress when the temperature falls below 32
101927 - degrees.
101928 -
101929 - Wayne asked how Gracon could develop a reliable schedule to complete
101930 - the work when it is likely temperatures will not begin to consistently
101931 - exceed 32 degrees until much later in the year?
101932 -
101933 - Dale indicated there are steps that can be taken to deal with colder
101934 - temperatures; he cited ice removal with heating equipment as an
101935 - example  but the general problem was not dealt with seriously at the
101936 - meeting this evening.
101937 -
101938 -
101939 -
101940 - Gracon Arranging for Alternate Barge Support to Maintain Progress
101941 -
101942 - Rod asked what effect the Engineer's directive of January 27 (ref DCP
101943 - 4), for Gracon to abandon the barge landing, will have on Gracon's
101944 - progress, specifically the intent to complete by 890421?
101945 -
101946 - Dale said he has discussed with Voith the possibility of renting
101947 - their crane as needed to load Gracon's barge in lieu of using the
101948 - barge landing at the downstream cofferdam.  He is uncertain whether
101949 - this is feasible due to the location of the crane and the size of
101950 - the pick.  If it is, progress should not be adversely affected.
101951 -
101952 - Dale indicated he has also discussed with Bill Clark of Swan Con-
101953 - struction, its schedule to begin removal of the barge landing, and as
101954 - a result, understands Swan does not intend to begin this work immedi-
101955 - ately.  Gracon intends to continue using the barge landing until Swan
101956 - begins work and this period may be sufficient to perform the major
101957 - tasks that depend on the barge landing.  Dale's primary concern is
101958 - loading the rubber dam for bay #2.  He feels this can likely be
101959 - accomplished within the next three (3) weeks, and that other arrange-
101960 - ments can then be made to land the rubber dam for bay #1 from the
101961 - Powerhouse area.
101962 -
101963 -
101964 -
101965 - DNRC Needs Rubber Dams Installed OB 880421
101966 -
101967 - Wayne explained DNRC needs the rubber dams installed in order to test
101968 - the generator by approximately 880421 because that is the date Voith
101969 - is scheduled to be ready to test.
101970 -
101971 - Failure to meet that date could result in lost revenue to the State.
101972 -
101973 - Kurt explained that the impact of the tie down testing and possible
101974 - remedial work would not necessarily delay testing.  The latter can
101975 - proceed and the generator could be placed on line, while corrections,
101976 - if any, are performed on the tie down system.
101977 -
101978 -
101979 - ..
101980 - Gracon Will Substantially Complete the Work by 880421
101981 - 
101982 - Clyde explained that DNRC is concerned about meeting completion
101983 - objectives and so asked for an adjournment for Gracon to develop a
101984 - cursory analysis based upon Dale's knowledge of the work and report
101985 - back on when Gracon feels it can achieve substantial completion.
101986 -
101987 - Following adjournment, a second meeting was convened at approximately
101988 - 1700. Gerry said Gracon feels they can realistically achieve substan-
101989 - tial completion to meet the objectives Wayne outlined, by 880421.  He
101990 - said Gracon will develop a formal schedule as requested by Clyde to
101991 - show the activities and resources Gracon will apply to meet this
101992 - objective, and Gracon will define the remaining activities to fully
101993 - complete the contract following "substantial completion."
101994 -
101995 -
1020 -
1021 -
Distribution. . . . See "CONTACTS"