Pacific Gas & Electric Company
Grid Customer Services
77 Beale Street
P.O. Box 770000
San Francisco, CA 94177

Memorandum


Date: September 27, 1994

To:     Chris Snyder

From:   Bill DeHart

Subject:   SDS - Change Order

Chris:

Since starting last month, we have had very successful results in the application of SDS on the CDWR Project. As you know, our intent was to use SDS on a trial basis to determine if the tool would significantly improve the manner in which we manage project information and facilitate decision making.

SDS has greatly improved our communication with CDWR. I use it regularly for meeting notes and managing the various forms of interaction with the project team as well as CDWR. It is providing a clear "trail" for decisions and a very efficient means for tracking follow-up actions. Lori Brown, our contact with CDWR, has found SDS very useful and has requested that we continue its use on the project.

Our contract with the Welch Company has a limit of $11,050. In order to complete the application of SDS and my training we need to increase the contract limit by $5,000. To reflect this change, I requested Materials and Fleet to prepare the attached change order for your concurrence. As you are aware, this effort is funded by the project.

Sincerely,



Bill DeHart




Attachment






Pacific Gas and Electric Company                           62-4675 (Rev. 11/93)
Contract Change Order                                      Materials and Fleet


                                                         PG&E COPY

DATE   September 20, 1994                                   Page 1 of 1


       Materials and Fleet                         Change Order No. 1
                                                   Contract No.  Z10-5-245-94

THE WELCH COMPANY
440 Davis Court #1602, San Francisco, CA  94111


JOB LOCATION:    Various

CONTRACT FOR:    Automated Management Support with SDS and POIMS Technology


The following changes are hereby authorized subject to the terms
and conditions contained in the contract referred to above dated:


     1.  Extend completion date of Contract through October 31, 1994.





TOTAL:   ADDITION    Five Thousand and No/100-------------------DOLLARS


Recommended    _____________________    Previous Contract Total     $11,500

Constructor's Approval _____________    Addition                      5,000

Materials Dept. Approval   KLR:ac       Revised Contract Total      $16,500


R/C Division   __________ Center_______

                                          P  NAME (TYPE OR PRINT)
  X  SECRETARY (PG&E COPY)
  X  CONTRACTOR                              LUTHER M. DOW
  X  WORK SUPERVISOR
  X  INVOICE APPROVER                     G  SIGNATURE          DATE
     V.P. IN CHARGE     William DeHart
     MANAGER                                 /S/Luther M. Dow   9/28/94
     CLAIMS                                  TITLE
     MATERIALS AND FLEET                  &
     LAW                                     MANAGER TRANSMISSION SYSTEM

                                             PG&E NEGOTIATOR       PHONE
                                          E
                                             WILLIAM DEHART        415 973 1511




CONTRACTOR:  Send invoices in triplicate  C  FIRM NAME (TYPE OR PRINT)
for each payment when due, showing con-
tract No. and Change Order No.  See       O  THE WELCH COMPANY
Contract for invoice mailing address.
                                          N  NAME (TYPE OR PRINT)

                                          T  ROD WELCH

                                          R  SIGNATURE          DATE

                                          A  /s/Rod Welch      Sep 22, 1994

                                          C  TITLE

                                          T  Owner
AFTER SIGNATURE, RETURN BOTH COPIES TO:
                                          O  CONTRACTOR'S REPRESENTATIVE  PHONE
  Karen L. Roorda, H8A
  P.O. Box 770000                         R                       415 781 5700
  San Francisco, CA  94177