M E E T I N G  N O T E S

Gensler/Michael Willis/Kwan Henmi

Project Moscone Center Expansion- Phase III Project Number 01.6250.000
Meeting Location JV Team Project Office Meeting Date October 14, 1998
Subject Electrical Coordination Meeting Number

68

Present

JV Team/KH
The Engineering Enterprise (TEE)
Ivan Romano
KC Hogan
Discussion

This meeting was called by Ivan Romero to clarify the status of the special floor outlets in the Prefunction. The size of the special Prefunction floor outlets previously cited by TEE turned out to be incorrect, and the revisions to their layout incorporated into the prior generation of background updates was not in accordance with TEE's reconsidered understanding of the client's direction.

  1. The special floor outlets in the Prefunction that appear to follow a random pattern are pretty much as the client requested them. They should not be modified, with the following exceptions:

    1. On the ground floor, the outlets should be adjusted to miss the beams below. Currently 5 out of 9 outlets are directly over beams.

    2. On the second and third floors, adjust outlet location to miss beam lines.

      1. For booth banks at cols 3, 3.3 and 3.8, no outlets need be provided in the Prefunction space.

      2. The typical floor boxes at col F are designed to service these booths that extend into the Prefunction.

  2. TEE needs to do a layout of the small floor outlets in the exhibit hall for Tim Comey to review/approve telecommunications outlets

  3. The beams and fireproofing along column lines E.5 and F are deeper than the typical floor box. Because the floor boxes are situated relatively close to these column lines, the 6" conduit linking these floor boxes will not be able to come in at a straight shot horizontally per the typical detail on TEE's drawings.


Action / Decisions Pending / Follow up








KH to revise floor outlets by 10/19


















TEE to draw up a layout for owner review by 10/23


TEE to revise their detail for this special condition.

Gensler/Michael Willis/Kwan Henmi will rely on these notes as the approved record of matters discussed and conclusions reached during this meeting unless written notice to the contrary is received by Gensler/Michael Willis/Kwan Henmi within seven calendar days of the issue date of these meeting notes.


Distrubution

  1. GWK, Clonia Cautis
  2. GWK, Steven Hergert
  3. GWK, Bolivar Puyol
  4. The Engineering Enterprise, KC Hogan


Prepared by Ivan Romano Date Issued: 10/16/98