This memorandum outlines the actions that Kwan Henmi (KH) is taking to meet the
project obligations discussed in our meeting Wednesday, September 23, 1998. We
are (1) increasing senior technical staff and defining the KH project team
staff structure, (2) clarifying the channels of communication and taking the
lead in recording team coordination meetings as they relate to KH scope of
work, and (3) outlining the priorities for the KH team to complete a productive
50% construction document submittal.
PROJECT TEAM STAFFING
KWAN HENMI PROJECT TEAM
- Project Architect: Ivan Romero.
- Senior Technical: Michael Foegelle, Janet Mackinnon, Robert Jansen, and an
additional senior technical team member.
Michael recently joined the team and KH will provide two (2) additional
senior technical resources, as quickly as possible. Janet will join the
office Monday, 10/5/98 and we are searching for a third new technical team
member.
- Technical/Production: Bolivar Puyol, Lawrence Kuan, and additional
CAD/production resources. Kwan Henmi will provide additional
CAD/production resources, as requested by Ivan.
- Technical Assistance and Quality Review: Robert Rudeen. Robert Rudeen (KH
Technical Director), will be available to support the KH project team with
detailing, document organization and quality review (a maximum commitment
of 16 hours per week). Robert is scheduled to the project Monday mornings,
the full day on Wednesdays, and Friday afternoons.
- Coordination Meeting Documentation: Rod Welch
COMMUNICATION
- Ivan, Steven Hergert and Clonia Cautis are to coordinate project
requirements and priorities. New coordination issues, corrections, and
concerns identified by Steven and/or Clonia should be brought directly to
Ivan's attention. Ivan (1) stays informed on all significant issues, and
(2) can direct KH resources as required to meet the needs of the project
and the scheduled deadline.
- Individual KH team members to take their direction from Ivan. Ivan to
communicate all assignments and priorities.
- Rod Welch will attend and document and scheduled project team and M/E/P
and Structural consultant coordination meetings. Meeting minutes, with
identified decisions and follow-up action items will be prepared and
distributed to project participants.
WORK PLAN: 50 PERCENT CONSTRUCTION DOCUMENT PRIORITIES
PROJECT ARCHITECT
Throughout the remainder of the project, Ivan will:
- Organize tasks and establish priorities for the KH scope of work, in
coordination with Clonia and Steven as required.
- Monitor progress, coordinate, and review the work of the KH project team
and related consultant work. As indicated above, all KH project team
members take their direction directly from Ivan.
- Attend project team coordination meetings and attend and lead consultant
coordination meetings as they relate to KH scope of work.
KH PROJECT TEAM TASKS, RESPONSIBILITIES, AND SCHEDULE
- Ceilings
- Tasks/Deliverables:
- Staffing: Design resolution and typical details by Robert Rudeen and/or
a new Senior Technical Resource (as determined by Ivan).
- Milestones:
- Explore design options and develop potential alternatives
immediately;project team to agree on a design approach Friday,
10/2/98.
- Updated document base plans for issuance to consultants on or about
Friday, 10/9/98.
- Applicable details issued with 50% Early Skin Package Thursday,
10/15/98.
- Complete work outlined Friday, 10/30/98.
- Stairs
- Tasks/Deliverables:
- Stairs worked out and documented in plan and section, including
sprinkler risers, structural supports, wall types, scope of
furring/finish partitions inside the stairs, access to structural
dampers, and railings.
(1) Exterior 50% Coordination Priority
- One cross section at typical stair showing interface with exterior
wall.
(1) Exterior 50% Coordination Priority
- Stair sections updated to reflect structural members.
(2) Consultant Coordination Priority
- Dimensions on stair plans.
- Stair 13 plan and section developed to same level with descriptive
notes.
- Staffing: Robert Rudeen and Janet Mackinnon (as determined by Ivan).
- Milestones:
- Initiate work as quickly as possible, Wednesday 9/30/98.
- Updated document base plans for issuance to consultants on or about
Thursday, 10/15/98.
- Applicable work issued with 50% Early Skin Package Thursday,
10/15/98.
- Complete work outlined Friday, 10/30/98.
Elevator/Toilet Cores
- Tasks/Deliverables:
- All three major elevator/toilet cores worked out with respect to
plumbing fixtures, partition types, structural framing, elevator
venting, machine room, access to fire dampers.
(2) Consultant Coordination Priority
- Enlarged plans of toilets and elevators with dimensions.
(2) Consultant Coordination Priority
- One section through each set of elevator shafts/machine
room/mechanical mezzanine showing structural frame and partition
alignments, duct and structural clearances.
(2) Consultant Coordination Priority
- Staffing: Ivan Romero and Michael Foegelle (as determined by Ivan).
- Milestones:
- Ongoing.
- Updated document base plans for issuance to consultants on or about
Thursday, 10/15/98.
- Complete work outlined Friday, 10/30/98.
Sections/Interior Elevations
- Tasks/Deliverables:
- Staffing: Robert Jansen and Lawrence Kuan.
- Milestones:
- Initiate work once ceiling design is complete on or about Monday,
10/5/98.
- Complete work outlined Friday, 10/30/98.
Miscellaneous
- Tasks/Deliverables:
- Staffing: Ivan Romero, Robert Rudeen, Robert Jansen, and Lawrence Kuan.
- Milestones:
- Ongoing.
- Updated basement ramps issued with 50% Early Skin Package, Thursday,
10/15/98.
- Complete work outlined Friday, 10/30/98.
Floor Plans
- Tasks/Deliverables:
- Staffing: Bolivar Puyol.
- Milestones:
- Ongoing.
- Updated document base plans for issuance to consultants on or about
Thursday, 10/15/98.
- Complete work outlined on Friday, 10/30/98.
- Exterior 50% Coordination Priority: Work tasks that are first
priority as required to coordinate with the 50% submittal of the
exterior early skin package.
- Consultant Coordination Priority: Work tasks that are second
priority as required to complete the base drawings as required
for coordination with project team consultants.
Ivan is currently reviewing the Moscone II 50% construction document package
and will develop a work plan outlining the documentation tasks to be completed,
for the October 30, 1998 50% construction documents deadline. Once completed,
we should assess the project status, confirm project schedule milestones, and
project team staffing and communication.