Gensler/Michael Willis/Kwan Henmi
Fire separation drawings that indicate area separations for all four floor are important in the development of the floor plans, Partition schedule, and HVAC fire damper indication. KH will complete by October 14,m 1998.
No progress to date. KH will complete by October 14,98.
Hand drafted sketch was transmitted to A&P @ 25% printing. Column line F effort to begin and be transmitted to A&P by October 12, 98.
JV team requested a sample of the adjustable louver in silver.
JV team requested an American made alternates to the louvered round diffuser.
Please provide sketch options showing:
KH to revise and coordinate the diffuser location at all pre function ceilings around all floor openings.
Remove high velocity diffusers from opening edges.
Remove round diffusers from elevations where they are not coordinated with the HVAC drawings.
Amit indicated that perimeter ceiling diffusers are indicated on the HVAC drawings.
No progress.
Exhibit/swing space diffuser locations are acceptable as indicated on the latest ceiling layouts.
A&P will indicate which 2' x 2 squares are supply, which are returns.
KH to provide a section through the ceiling space to indicate all the ceiling devices :structural elements, supports for the movable walls, supports for gypsum board edges, movable wall supports, floor boxes, ceiling layer, etc.
KH to provide by 10/17/98.
JV team will study and coordinate with SDE.
A&P requested that column line 3 brace be a V type brace.
SDE to follow up.
JV team proposals for modification in progress.
A&P will use high efficiency louvers. A&P to advise.
Requirement: Pipe to extend 10' above roof, and 3' from adjacent wall, enclosed in a 2 hour shaft within building.
Exhaust pipes will terminate at the face of the building.Approval was received from the DBI.
KH to coordinate and indicate pipes within the interior shafts,
MWA to coordinate the exterior elevation penetrations.
CC red marked the area on the table set for coordination.
JV team to study options of not extending exhaust to roof.
Still pending.
JV team to issue electronic files to FBA.
(Issued and incorporated into FBA plans)
KH will transmit new backgrounds to consultants 10/19/98. Check with FBA if OK.
Files sent to FBA.
Sump locations must be modified slightly.
See Structural foundation plan for conflicts: S2.01.
everything in cabinet by A&P.
Not resolved.
KH will provide after the October 19,98.
Structural clearance issues were identified. See M7.02 for sections.
All sections assume 8'-6" height of hood connection. This was approved by Cini-Little. Pending approval from hood manufacturer (Gaylord).
No work yet in the kitchen area.
KH to provide a section through the kitchen area that addresses clearances below structure, double slab at ramp area, etc.
Hood issues still pending.
ISSUE STILL PENDING.
Still pending?
There will be a meeting next week with SF thermal.
Still pending.
x24 size was previously approved by the City. No issue.
KH to revise floor boxes. Coordinate with SDE.
CC transmitted Memo to CL. CL indicated that they will provide equipment data to us. Pending CL information.
Revisions will appear in 25% set.
CC to ask Tim Comey to provide.
Vertical ventilation shaft can only be located near column 5/C, away from the glass retail wall.
KH to provide a sketch for the basement area by 10/12/98.
A&P advised that the proposed louver re configuration does not work.
CC indicated that may be a different approach can be used to address the exhaust louver requirements:
ue area west of column line B/5 and 6. Louver at roof area can be provided on the west "tower" elevation. ue louver area now indicated above the lower roof area in the profiled metal area. pe a roof opening in the vicinity of the cooling tower. All advise by 10/8/98.