Gensler/Michael Willis/Kwan Henmi
IR did not have a list of the previous items described in the previous memos.
Column locations are now indicated on the revised backgrounds. What is not yet reflected are the kitchen revisions, wall thicknesses, grease duct, furring at perimeter concrete walls, gas meter vault.
IR assigned the work to the new technical person.
IR can not yet indicate when the core will be completed.
CC indicated that Helen advised that she did not know that she was to include the toilet accessories into the restroom plans, so she may have to redo some work. Michael provided her with the information. Restroom information will be incorporated in the October 19, 98 background updates to be transmitted to all consultants.
No progress yet on the second stair to the west mechanical mezzanine.
Hard-line drawings of the interior wall sections need to be started.
Michael's wall section needs to be expanded to include info regarding the wall type, damper enclosure, etc.
No progress yet.
CC indicated that Gensler needs to review the layouts before they are ready to be transmitted to consultants.
IR will provide a print of the ground floor west sketches restroom today, 10/6/98.
CC expressed concern that with the present progress pace we may not be able to accomplish the 50% set our client expects.
CC indicated that the review with IR was limited to the cartoon set for the detail sheets, the Finish and Door schedule information.
CC indicated that the Door and finish Schedule needs to be updated in the excel format to indicate any additional rooms or doors.
An additional room number column will be helpful if added to the excel form.
CC's previous comment was that the Client and the cost estimator already included the information contained in the Typical detail DD booklet in their estimate. Just moving the information from an 8 1/2 x 11 format to, a 36 x 48 format will not add new information to the 50% package.
However, the information is needed for the 100% package. This may not be a priority item for the 50%.
We need to see established goals of moving from a DD phase to a CD phase.
We reviewed the Moscone II set and CC indicated the wall sections, the large scale elevations/sections that are more than a indication of finishes, but of construction elements.
Questions: based on the Moscone set, what is the team going to produce for the 50% set?
CC reviewed the October 5, 98 memos to IR regarding progress prints that deleted information from the Design Development package.
IR will review and advise why the information was deleted. CC asked that the information be put back on the drawings.
KH has a new senior person.
By doing this the movable wall pockets will be represented in the stair detail plans.
KH will provide this 10/6/98.
Stair roof plan will be added by MWA to the respective detail plans by 10/8/98.
MWA provided the meeting notes.
CC suggested that KH and MWA collaborate on the meeting notes production.
The final meeting notes from each meeting that are used for consultant distribution should use the format as described in the Project management manual.
The meeting minutes should be completed in due time. (two days plus or minus)
Cc r:\mosc\managers\cautisc\moscone\2-design\a-arch\gensler\mn-01.doc