Discussion
Progress / Status of drawings:
- IR indicated that the items listed in Gensler's previous memos have not
fully been addressed.
- Revised basement backgrounds to include structural column information
will not be transmitted to our consultants before the 25% printing.
- IR will finish the elevator 5 and 6 core by himself, too complicated for
a new person.
- Michael will continue with the second stair to the west mechanical
mezzanine. The backgrounds do not yet relfect the resolved stairs.
- CC asked that all the information developed by Michael with regard to the
B line be indicated on the elevations. Hard-line drawings of the interior wall
sections need to be started. Michale's wall section needs to be expanded to
include info regarding the wall type, damper enclosure, etc.
- Restrooms have not yet been resolved. CC indicated that Gensler needs to
review the layouts before they are ready to be transmitted to consultants.
- CC asked about the strategy of getting the drawings to a 50% status. CC
expressed concern that with the present progress pace we may not be able to
accomplish the 50% set our client expects.
- CC asked that KH indicate what a 50% set represents. We need to see
established goals of moving from a DD phase to a CD phase. We reviewed the
Moscone II set and CC indicated the wall sections, the large scale
elevations/sections that are more than a indication of finishes, but of
construction elements. Questions: based on the Moscone set, what is the team
going to produce for the 50% set?
- Conclusion: senior manpower missing.
- KH may bring a new senior, problem solver person.
- SH indicated that they would l9ke more of PS's time to resolve design
issues.
- CC indicated that for the 25% printing we should only print drawings that
indicate progress.
Ms. Clonia Cautis, AIA
Project Manager