Moscone Center Expansion, Phase III
Gensler/Michael Willis/Kwan Henmi

03 96060 00 AC CK CK 0101

Document Log
Issued Pending Response

Period: August 12, 1998 - November 11, 1998
Prepared: November 11, 1998

Received Pending Response
All Activity

 
Document  Recvd         Respond  By
Date   #  Date  From   Date  Orgnztn  <-------- Description --------->


980929 01 980930 WELCO RW 981015 KHAP DH JV meeting and KH planning 980930 01 980930 WELCO RW 981015 KHAP DH Management Planning Meeting 980930 02 980930 GWK-K DH 981015 GWK-G AG KH Management Plan 50% dwgs 981001 01 981001 WELCO RW 981016 GWK-K IR JV Coordination Meeting, 980929 981012 01 981012 WELCO RW 981027 KHAP WL Project Management, WBS 981014 01 981014 WELCO RW 981029 KHAP DH Project Review 981015 01 981015 WELCO RW 981030 KHAP WL Business Systems, Doc Log 981019 01 981019 WELCO RW 981103 GWK-K IR Transmittal Meeting Note Drafts 981019 02 981019 WELCO RW 981104 KHAP DH Evaluation Communication Metrics 981019 03 981019 WELCO RW 981103 GWK-K IR Team Meeting on 981016 981021 01 981021 WELCO RW 981105 GWK-K IR Mechanical Meeting, 981014, edits 981021 02 981021 WELCO RW 981105 GWK-K IR Transmit mech mtg edits, 981014 981026 01 981026 WELCO RW 981110 GWK-K IR Structural Meeting, 981015 edited 981026 02 981026 GWK-K RR 981110 GWK-G CC Telecom Meeting, 981021 edits 981027 01 981028 WELCO RW 981112 KHAP RR Mechanical Meeting, 981021 981028 01 981028 WELCO RW 981112 KHAP RR Structural Meeting, 981022 Draft 981029 01 981029 WELCO RW 981113 GWK-K RR Mechanical Meeting, 981021 draft 981102 01 981109 KHA WL 981124 GWK-G CC 50% Interior Package 981104 01 981104 GWK-K RR 981119 GWK-G CC Mechanical Meeting, 981021, edited