DEPARTMENT OF THE ARMY
It is requested that you revise your constructon schedule to include the completion of this project area. Include the equipment to be used, the location and quantity of capping material; the location and quantity of Wings material; the location of Turning Basin and Wings that are currently to grade; the quantity of material dredged to date from the Wings and Turning Basin; start and finish dates; and durations of all pertinent activities pertaining to completion of bid item No. 0006, "Dredge Inner Harbor & Dispose of Material in Galbraith Disposal Area." Your schedule shall be computed by CPM with the nodal logic, bar chart, and critical path shown.
Your plan to perform this work shall be submitted with the updated schedule and shall include the plant and methods you will employ to complete Bid Item No. 0006.
Sincerely,
Leonard SooHoo, P.E.
Chief, Construction Service Branch