DUTRA DREDGING A MEMBER OF THE DUTRA GROUP 1000 POINT 5AN PEDRO ROAD SAN RAFAEL, CALIFORNIA 94901 (415) 121-2131 FAX (415) 121-1394 Contractor License #707580 A November 7, 1996 Department Of The Army San Francisco District Corps of Engineers 333 Market Street San Francisco, CA 94105 Attn: Thomas Benero, Contracting Officer Re: Contract No. DACW07-95-C-0003 Subj: Exception To Unsatisfactory Performance Evaluation Gentlemen:We are alarmed to have received the Corps' DD Form 2626, dated 13 June 1996, assigning Dutra Dredging Company an "unsatisfactory performance rating" in connection with progress on the Oakland Inner & Outer Harbor Dredging Project. The evaluation is highly subjective, prematurely judgmental and unwarranted by the facts. It reaches an erroneous and unjustified conclusion and may prove harmful, not only to the business interests of the Contractor, but to the economic balance and overall success of the Project.
At the outset it should be noted that the threat, of an "Unsatisfactory Interim Performance Rating", contained in the Contracting Officer's letter of May SO, and reiterated in his letter of June 3, 1996, pertained, as explained in those letters, to the submittal of an updated schedule and a forward projection of anticipated expenditures, within an arbitrary time frame prescribed by the Corps, NOT the diligent pursuit of the work, as stated in the remarks section of the DD Form 2626. Those submittals were delivered within the time frame dictated by the Corps, even though the forward projection of expenses is an extra-contractual requirement which has been submitted from time to time purely as an accommodation to the Corps. The employment of an adverse performance evaluation on the Oakland Inner and Outer Harbor Dredging Project apparently has nothing to do with missed submittal deadlines and everything to do with the frustrated expectations of those employing it.
The Corps asserts that the list of equipment and production rates presented at
our 7 June 1996 meeting with Corps officials, as confirmed in our
correspondence of June 11 and 12, does not support a contract completion date
of April 1997. That assertion is simply not true and cannot form the basis for
a charge of unsatisfactory performance. The conventional equipment itemized in
the noted correspondence made measurable progress preparatory to the arrival of
the Marine Hydraulic Excavator "Antone" in late August 1996. There should be no
difficulty in meeting the original contract completion date as extended. It
should be borne in mind that the Contractor is entitled to time extensions for
excusable delay, differing site conditions and an extensive increase in overall
quantities to be dredged under the Contract. Further on this point, it should
be noted that the Corps has refused to acknowledge that there are over 80O,OOO
more cubic yards of material above grade, as shown by the original survey, than
specified in the original contract, as well as site condition changes which add
yardage. This additional yardage equates to time which results in a completion
date well into August of 1997. Other time related issues also have been
ignored.
By setting an artificial and inaccurate time line for contract completion, the
Corps justifies the issuance on an interim unsatisfactory rating. The fact is
that we were not and are not behind schedule. The contractor has every right to
pursue the work in a manner which maximizes efficiencies and minimizes costs.
Because Corps personnel may not understand the work patterns, does not allow
the Corps to make a detrimental finding against the contractor just to satisfy
an apparently internal agenda. Unfortunately this is what appears to have been
done in the Corps notice of June 13, 1996.
Since that time the Corps has also retained funds from progress payments in the amount of 10% of each pay estimate. This retention is asserted by the Corps to be a method of assuring timely completion. Such is not the case. This retention scheme is purely punitive. Any thought process which speculates that withholding funds will accelerate work is severely flawed. Its result is the exact opposite. Cash flow is impaired with resultant harm to the contractor and the impairment of work efficiency. Retention under this Contract is unwarranted and unjustified. Moreover, it violates the spirit of the agreement and may constitute interference with the prosecution of the work.
We hereby request that the practice of withholding retention on the Project be stopped and that retained funds be released to the Contractor immediately. Additionally, we formally request the immediate retraction of the Corps' "Unsatisfactory Performance Rating". Continuing this course of action will result in unnecessarily negative perceptions of the San Francisco District's Engineer and his management staff; may damage the contractor's business reputation; could jeopardize the economic well-being of the (contractor and the Project; will certainly impair efficiency and production on the job and damage otherwise harmonious relationships on the Project and will inevitably result in claims and litigation at Project conclusion.
There will be ample time to successfully and timely complete the Contract work,
if the parties to this venture can begin to work together a little more
effectively. In closing, I specifically refer to the atmosphere created by the
Corps' actions. That atmosphere has resulted in weekly project meetings which
are overrun by contract management staff from the Corps instead of the
technical people for which it was intended.
There needs to be a single point of
contact from the Corps at these meetings. The Project Manager is supposed to be
that point of contact, not the Contracting Officer. Accordingly, in addition to
our request that the withholding of retention cease and that the Corps' DD form
2626 be withdrawn, we request that weekly Project management meetings return to
their original intent, that they be attended only by essential Project
personnel and that they be chaired by your Project Manager.
Sincerely,
Robert D. Johnston, Project Manager
And President Of The Company
cc. Lt. Col. Richard Thompson