The Welch Company Nov 16, 1991 REV
440 Davis Court #1602 By: Rod Welch
San Francisco, Ca 94111 FILE NO: 03 00054 11257 01 03 0101
415 781 5700




Re:  Voith Broadwater Contract 1189.1
          Turbine, Generator, Electrical, and Auxiliary Equipment
D o c u m e n t R e v i e w

Background Comment ================== This is to develop information from the contract between DNRC and Voith to support evaluation of DNRC claims against Voith. It may also contribute to presenting claims by DNRC against Tudor.

Exhibit: (this is not yet an exhibit in any case)

Project Name: Broadwater Power Project

Owner: State of Montana Department of Natural Resources and Conversation, Engineering Bureau 1520 East Sixth Avenue Helena, MT 59620-2301

Tudor Submittal File 00730 Section 11257: Speed Increaser =============================== Voith did not submit speed increaser "shop drawings" and nearly all of the sub- mittals it did make were over a year late and were rejected by Tudor enmasse.

This is shown in one of Tudor's green "Contractor Transmittal" forms dated March 28, 1989, which shows most of the speed increaser submittals in the jobsite files (set out below) were received by Tudor on Feburary 15, 1989, and were returned marked "Revise and Resubmit" on the grounds that they "need English translation." There is no record Voith complied with the Engineer's directive to re-submit or that Tudor approved Voith's speed increaser submittals.

There are no due dates in Tudor's submittal log for the Voith contract. "Due" dates entered in this format (shown below) are taken from the Nov 3, 1987 meet- ing minutes which appear to be based on a Renk submittal schedule attached to those meeting minutes.

There are no indications in the record so far that Tudor directed Voith to com- ply with contract submittal and scheduling requirements. Failure to post "due" dates in the submittal log hid Voith's failure to perform until it was too late, resulting in the summary rejection of March 28, 1989 (discussed above).

There is not a one-for-one correlation with respect to submittal descriptions between the sources for the submittal information shown below, mainly with respect to "Due" dates, since Tudor did not post any.

The order shown below is that shown in Tudor's jobsite files.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11254.59 00 02-18-88 None Renk AGMA/Life Cycles cale 11-23-87 02-19-88 03-04-88 A

This appears to be the item on Renk's Sep 8, 1987, submittal schedule titled "Final AGMA 218 and Lifetime calculations" which Voith seems to have scheduled in the Nov 3, 1987 meeting for Tudor to receive on Nov 23, 1987, but which was actually received on February 19, 1988.

This was about 90 days late.

This submittal is missing from Tudor's jobsite files.

There is also no Tudor green "Contractor Transmittal" for this item which should have been prepared on March 4, 1988. It is not in the file.

Conflicts with Tudor 11257.02 ----------------------------- Tudor notes in returning Renk's "Mass Scheme" submittal (11257.02 shown below) that Voith must submit specified AGMA information. Since the "Renk AGMA/Life Cycles cale" submittal (11254.59) was received on Feburary 19, 1988, then, if it adequately addressed all AGMA data issues there would have been no need to request AGMA data on transmittal 11257.02 just 3 days later.

Accordingly, it seems likely that this submittal for 11254.59 did not satisfy the request Tudor made for more AGMA data on submittal 11257.02. Since the submittal is missing from Tudor's jobsite files, the extent of Voith's compli- ance with AGMA standards is not known.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.01 00 11-04-87 R-3200557/0 Outline (speed increaser) 11-15-87 11-04-87 R

This drawing is not in Tudor's jobsite files

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.02 00 02-03-88 3200590/4 Mass scheme (Renk) 11-23-87 02-04-88 03-01-88 C

This drawing appears to be in Tudor's jobsite files with a received stamp on the back of Feb 4, 1988. It seems to be the Renk submittal identified on its Sep 8, 1987 message titled "Information of masses of inertia and flexible lengths" and appears to have been included in the single item on the Voith submittal list of Nov 3, 1988 titled "Foundation Loading Data" which was to have been received by Tudor on November 23, 1987.

It was approximately 70 days late.

AMGA Data Requested ------------------- It has another Tudor stamp on the back with respect to disposition that seems to show a date of 2/29/88, with a comment:

Submit design calculations in accordance with AGMA standards. There is a comment below this comment:

Rec'd submittal #16. This appears to be initialed beginning with "D" but the other initials are unclear.

It is also unclear whether the requested data was actually received. See also discussion above for 11254.59 under "Conflicts with Tudor 11257.02."

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.03 00 1-18-88 2693-0002 0 Renk Outline dwg (3200557/0) 11-15-87 02-19-88 03-04-88 D

This drawing appears to be in Tudor's jobsite files with a received stamp of Feb 19, 1988. It has another Tudor stamp on the extreme left side that seems to show a date of 2/1/88, but indicates "Revise and Resubmit."

The drawing has many notations showing it does not comply with Tudor specs. See below for possible re-submittal.

  1. Need complete system lubrication schematic showing how hub tank and reserve oil enters system.

  2. Pressure switches on lube line must be positioned on CL pumping unit per Tudor's spec.

  3. Dial temperature and flow indicators all must be positioned to allow easy access above the SI shaft.

  4. Oil flow indicator with 2 SPDT contacts, was noted as being "Not to Spec." There are two locations where this is noted; the second notation says: Flow switch must be per Tudor spec 11257 2.8 E, note 3 places.

This appears to be the drawing on Renk's Sep 8, 1987, submittal schedule titled "Final outline drawing" which Voith appears to have scheduled in its Nov 3, 1987 meeting minutes to in Tudor's office on Nov 15, 1988.

Tudor shows this submittal to be "Revised and Resubmitted". There is no subsequent entry where this drawing was resubmitted and approved for construction.

Corrected Drawing ----------------- There is another drawing numbered 3200557/0 with Voith number 2693-0002 Rev 03. It shows a "Tudor-no: 11257-03.03" in the ID block, and is stamped "Received Feb 21, 1989" by Tudor in San Francisco. It is stamped received by Voith "5/24/88."

Tudor Submittal --------------- There is a separate green "Contractor Transmittal" document in Tudor's jobsite file #00730 which lists this submittal as "2693-0002 Renk Outline Drawing." It is marked as received by Tudor on Feb 15, 1989, rather than Feb 21, 1989, so it may correspond to this submittal even though the received dates do not exactly correspond. Tudor also marks this submittal by Voith as "Revise and Resubmit."

This drawing contains some of the corrections noted to be made on the submittal Tudor received on Feb 19, 1988. For example: Was Changed to ------------- ------------------------ Runaway speed n=232 RPM n=252 RPM High Pressure Oil inlet line showed for oil quantity _______ ~2.65 US galns. min. * Position of "dials" Not Viewable Moved somewhere Errors Not Corrected -------------------- Tudor notes 1 - 4 above on the original submittal do not appear to be reflected in this second submittal which was received by Tudor Feb 21, 1989, 3 months after the Speed Increaser was delivered to the job. As noted above Tudor has a Transmittal dated March 28, 1989, in which this submittal is marked "Revise and Resubmit." There is no record this was done. Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.05 00 05-24-88 2693-0003 1 Assembly dwg (3200623/0) -------- 02-21-88 03-28-89 D 02-15-89

This drawing is not listed on either Renk's Sep 8, 1987 submittal list or Voith's Submittal Drawing list at the Nov 3, meeting.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Defective Gear Set Suspension Bolts ------------------ This drawing shows the bolts that broke which initially supported the gear set.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.06 00 05-24-88 2693-0006 Wiring Diagram gear box (3200625/1 01-03-88 02-21-89 03-28-89 D 02-15-89

This drawing is listed on Renk's Sep 8, 1987 submittal list or Voith's Submittal Drawing list at the Nov 3, meeting to be received by Tudor on Jan 3, 1988.

It was 14 months late.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.11 00 02-24-88 2693-0004 Flow Diagram (3200954/1) 01-03-88 02-21-89 03-28-89 D 02-15-89

This drawing is identical to the one below, except the one below is marked by Voith as "Reviewed No Exceptions" and was received by Voith on Feb 24, 1988, whereas the next one was received on May 27, 1988. It is not clear in the record, why there are two of these drawings. There are no other drawings in the record that are duplicated as this one was.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.07 00 05-27-88 2693-0007 Flow Diagram (3200954/1) 01-03-88 02-21-89 03-28-89 D 02-15-89

This drawing may be the item titled "Outline drawing Oil Supply" or "Piping diagram Oil Supply" on Renk's Sep 8, 1987 submittal list or Voith's Submittal Drawing list at the Nov 3, meeting to be received by Tudor on Jan 3, or Feb 3, 1988.

If It was either of these submittals, it was approx. 14 months late.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.08 00 11-03-87 2693-0001 Installation Dwg (4874938/1) 12-15-87 02-21-89 03-28-89 D 02-15-89

This drawing may be the item titled "Installation Manual" on Renk's Sep 8, 1987 submittal list or Voith's Submittal Drawing list at the Nov 3, 1987 meeting to be received by Tudor on Dec 15, 1987.

If so, it was approx. 16 months late.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.09 00 05-27-88 2693-0008 Top Tank (3200955/1) -------- 02-21-89 03-28-89 D 02-15-89

This drawing is not on Tudor's submittal log. It does not seem to be among the submittals on Renk's Sep 8, 1987 submittal list or Voith's Submittal Drawing list at the Nov 3, 1987 meeting.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.10 00 06-08-88 2693-0010 Oil Supply Unit (3200980/1) 01-03-88 02-21-89 03-28-89 D 02-15-89

This drawing may be the "Outline Drawing Oil Supply" listed on Renk's Sep 8, 1987 submittal list and on Voith's Submittal Drawing list at the Nov 3, 1987 meeting which was shown to be received by Tudor on Jan 3, 1988.

It was therefore received 13 months late.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.

Tudor Contractor Transmittal File No. Rv Date Drawing No. Title/Description Due Received Returned St -------- -- -------- ------------- ----------------------------- -------- -------- -------- -- 11257.13 00 05-21-88 2693-0009 Oil Supply Unit main tank (3200956/4) 01-03-88 02-21-89 03-28-89 D 02-15-89

This drawing may be part of the "Outline Drawing Oil Supply" listed on Renk's Sep 8, 1987 submittal list and on Voith's Submittal Drawing list at the Nov 3, 1987 meeting which was shown to be received by Tudor on Jan 3, 1988.

It was therefore received 13 months late.

There is no Tudor or Voith disposition stamp on the drawing. It was rejected by Tudor on March 28, 1989. There is no record of resubmittal by Voith or approval by Tudor.